Miscellaneous Information / Notes |
-PB LOT 23 CONSTRUCTION OF NEW SINGLE FAMILY |
RESIDENCE |
****** PRIVATE PROVIDER INSPECTIONS ONLY****** |
******PLANNING AND BUILDING CONSULTANTS LLC******* |
|
|
3/27/23 CO ISSUED. SCANNING FOR FILENET. |
ATTACHMENT IN C+. FILED UNDER "E". KP |
8/18/22 RECEIVED PRE-CONSTRUCTION SUBTERRANEAN |
TERMITE TREATMENT PAPERWORK, ROUTED TO FILE NET |
PER DYLAN BATTLES. AM |
7/13/22 PERMIT ISSUED. LEM |
7/12/22 REVIEWS COMPLETE, WAITING ON UPDATED |
SUB-CONTRACTOR INFO TO ISSUE PERMIT (PLUMB). LEM |
7/12/22 ADJUSTED FEES FOR PRIVATE PROVIDER |
INSPECTIONS SH |
7/12/22 NTBO RECEIVED FOR INSPECTIONS ONLY REG |
7/5/22 IMPACT FEE QUEST UPLOADED. PBCGOV EMAILED |
AS PER JG AO |
06/27/22 TALKED TO NICK TO GO OVER COMMENTS. JG. |
6/17/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. AO |
5/26/22 RSEUBMIT RECEIVED, INCOMING COMPLETE. LEM |
5/12/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
4/18/22 APPLICANT RESUBMITTED DIGITALLY,INCOMING |
COMPLETE AO |
4/15/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
4/14/22 APPLICANT RESUBMITTED DIGITALLY,INCOMING |
COMPLETE AO |
4/13/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT. LEM |
2/17/22 PLANS CORRECTED,INCOMING COMPLETE.CD |
2/15/22 WAITING FOR CORRECTIONS.CD |
2/14/22 PLANS REJECTED,NEED TO PROPERLY NAME THE |
PLAN SHEETS IN THE DRAWING FOLDER. CUSTOMER |
EMAILED TO CORRECT.CD |
2/2/22 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
FEES. LEM |