Miscellaneous Information / Notes |
ROOF REPLACEMENT |
|
|
|
|
|
06/16/22 OWNER P/U PERMIT PACKAGE. JG. |
6/16/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
DOWNLOAD PLANS, PERMIT CARD UPLOADED AO |
4/18/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
4/18/22 BUILDING REVIEW FAILED. JNB |
4/14/22 RESUB RECEIVED, INCOMING COMPLETE AO |
4/13/22 RESUB UPLOADED INTO PROJECTDOX.PAPER |
ROUTED TO APRIL STORAGE BOX IN SCANNING.CD |
4/12/22 RESUB TO ADDRESS DENIED COMMENTS, ROUTED |
TO INCOMING. AM |
3/8/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
3/8/22 BUILDING REVIEW FAILED. JNB |
2/28/22 RESUB UPLOADED TO PROJECTDOX, PAPER |
ORIGINALS FILED IN HOLD BOX. INCOMING COMPLETE AO |
2/25/22 OWNER RESUB TO ADDRESS DENIED COMMENTS |
ROUTED TO DIGITAL CONVERSION SHOLDER |
1/25/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
1/25/22 BUILDING REVIEW FAILED. JNB |
1/20/22 RESUB UPLOADED TO PROJECTDOX, PAPER |
ORIGINALS FILED IN HOLD BOX. INCOMING COMPLETE AO |
1/19/22 RESUB TO ADDRESS DENIED COMMENTS, ROUTED |
TO INCOMING. AM |
11/8/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
11/8/21 BUILDING REVIEW FAILED. JNB |
11/5/21 PLANS UPLOADED,INCOMING COMPLETE. PAPER |
ROUTED TO NOVEMBER STORAGE BOX IN SCANNING.CD |
11/5/21 CHANGED FROM PAPER TODIGITAL.CD |
11/4/21 ROUTED TO INCOMING. AM |