Miscellaneous Information / Notes |
-PB-CONSTRUCT NEW SINGLE FAMILY HOME |
**PRIVATE PROVIDER FOR INSPECTIONS** |
|
|
2/7/23 STEVE.K DROPPED OFF REPORT LEFT AT RICHARD |
.G DESK. BB |
8/29/22 STEVEN KENEDDY DROPPED OFF PILING LOG, |
ROUTED TO RICHARD GATHRIGHTS DESK. AM |
8/24/22 PERMIT ISSUED. LEM |
8/24/22 REVIEWS COMPLETE, WAITING ON IMPACT STAMP. |
LEM |
8/18/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
8/12/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
8/11/22 EXPEDITED PLAN REVIEW REQUEST RECEIVED AO |
8/11/22 REJECTED TASK BACK TO CUSTOMER, REVISED |
PLANS WERE NOT VERSIONED. EMAILED APPLICANT TO |
REUPLOAD. AO |
7/26/22 RECEIVED NTBO FOR INSPECTIONS. ADDED |
DOCUMENTS TO PROJECTDOX, REVIEWED DOCUMENTS UNDER |
PP STOP AND ADJUSTED FEES. DB |
7/22/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
7/19/22 IMPACT FEE QUEST UPLOADED. PBCGOV EMAILED |
PER REG AO |
6/29/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
6/14/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
4/27/22 ISSUED LETTER GRANTING AUTHORIZATION TO |
START WORK UP TO FIRST INSPECTION PRIOR TO |
ISSUANCE OF THE PERMIT. RB |
4/27/22 RECEIVED CONTRACTOR LETTER REQUESTING |
AUTHORIZATION TO START WORK UP TO FIRST INSPECTION |
PRIOR TO ISSUANCE OF THE PERMIT. RB |
4/20/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
3/22/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
2/28/22 ADJUSTED FEE FOR ICC TABLE. SENT EMAIL |
WITH REFUND REQUEST FORM TO CUSTOMER.DB |
2/1/22 ADJUSTED VALUE TO NOT INCLUDE SITE WALL AND |
LANDSCAPING VALUES. LEM |
1/31/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
1/3/22 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT. CP |
1/03/22 PROVISO'S: SITE WALLS PG. C-1 AND POOL PG. |
L1.1. CT |
1/03/22 SFHA DFE 9.0' NAVD. CT |
1/03/22 DEF. FIELDS COMPLETE. CT |
1/03/22 VALUE VERIFIED. CT |
11/2/21 PLANS UPLOADED,INCOMING COMPLETE.CD |
10/25/21 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
FEES. LEM |