Miscellaneous Information / Notes |
REROOF TILE TO TILE |
|
2/16/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
DOWNLOAD PLANS, PERMIT CARD UPLOADED AO |
11/8/22 REVIEWS COMPLETE, WAITING ON UPDATED |
CONTRACTOR INFO TO ISSUE PERMIT. LEM |
TALKED TO PHIL (CONTRACTOR). HE'S DRIVING. HE WILL |
CALL ME BACK TO GO OVER COMMENTS TO HELP HIM |
PROCESSING THE PERMIT. JG. |
10/21/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT. FORWARED TO JG AO |
10/21/22 SIGNATURE REVIEW FAILED. JNB |
10/21/22 BUILDING REVIEW FAILED. JNB |
10/11/22 RESUB RECEIVED, INCOMING COMPLETE AO |
9/15/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT, PLAN REVIEW COMMENTS SENT VIA EMAIL AO |
8/31/22 APPLICANT RESUBMITTED DIGTALLY,INCOMING |
COMPLETE AO |
10/14/21 REJECTED TASK BACK TO CUSTOMER. TASK |
COMPLETED WITHOUT CORRECTIONS UPLOADED AO |
10/6/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
10/4/21 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
COMPLETE AO |
6/21/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
6/21/21 BUILDING REVIEW FAILED. JNB |
6/18/21 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
COMPLETE AO |
5/13/21 REJECTED TASK BACK TO CUSTOMER. TASK |
COMPLETED WITHOUT CORRECTIONS UPLOADED AO |
5/11/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
5/11/21 SIGNATURE REVIEW NOT REQUIRED. JNB |
5/11/21 BUILDING REVIEW FAILED. JNB |
5/10/21 PLANS UPLOADED, INCOMING COMPLETE. LEM |
5/5/21 EMAILED CPUELL TO UPDATE OWNER. LEM |
5/5/21 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
FEES. LEM |
|