Miscellaneous Information / Notes |
INSTALL 32KW GENERATOR WITH NATURAL GAS HOOK UP |
|
|
|
8/31/21 ROUTED SIGNATURE DOC TO STORAGE SH |
8/31/20 REVIEWS COMPLETE, APPLICANT INVITED TO |
DOWNLOAD PLANS, PERMIT CARD UPLOADED, .CC |
8/31/2020 SIGNATURE REVIEW APPROVED. ORIGINAL |
PAPER SIGNED/SEALED PLAN SHEET ROUTED TO STORAGE |
BIN.PV |
8/22/2020 SIGNATURE REVIEW FAILED. THE SUBMITTED |
PAPER SIGNED/SEALED PAD ENGINEERING UPLOADED TO |
PROJECT DOX AND ROUTED TO PERMIT LIBRARY IN MAY |
SECTION.PV |
8/21/2020 PAPER IN DROP BOX WITH S.HILL NAME ON |
IT; ROUTED TO S5 RES |
8/21/20 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT DIGITAL SIGNATURES. LEM |
8/17/20 RESUBMIT RECEVIED, NOTHING UPLOADED, |
INCOMING COMPLETE. LEM |
8/3/20 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT DIGITAL SIGNATURES. LEM |
7/22/20 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
7/20/20 RESUBMIT REMINDER SENT. LEM |
6/19/20 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
6/15/20 RECEIVED ORG. APPLICATION PLACED IN |
UNISSUED MASTER BIN TSG |
6/1/20 PLANS UPLOADED, INCOMING COMPLETE. LEM |
5/29/20 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
FEES. LEM |