Miscellaneous Information / Notes |
180-RENEWAL FOR #16010291. CONCRET RESTORATION FOR |
PREVIOUS D/B ALONG SOUTH SIDE OF BANYAN BLVD FROM |
AUSTRALIAN TO SAPODILLA. 4 BORE PITS REQUIRED IN |
S/W. |
|
CONTRACTOR:HOTWIRE COMMUNICATION, PHIL GALLUB, |
305-219-0286 |
SUB: ALL QUALITY ELECTRICAL CONSTRUCTION , |
305-525-4170 |
START DATE: 06-29-2017 |
DURATION: 180 DAYS |
END DATE: 12-26-2017 |
BAGGING OF PARKING METERS IS REQUIRED WHEN |
BLOCKING PARKING STALLS. DO NOT PARK ON THE |
SIDEWALK. R/W & S/W RESTORATION PER CURRENT CITY |
STD. COPY OF BORE LOGS & AS-BUILTS REQUIRED. |
LIGHTED BARRICADES REQUIRED IF EQUIPMENT OR |
DUMPSTER (POD) IS LEFT IN ROADWAY OR PARKING STALL |
AFTER DARK OR OVER NIGHT. ALL TRAFFIC LOOPS SHALL |
BE RESTORED PRIOR TO FINAL INSPECTION. CONTACT |
SIGNAL PALM BEACH COUNTY SIGNAL SHOP SUPERVISOR AT |
561-233-3900 FOR COORDINATING LOOP |
RE-INSTALLATION. ALL TYPE I BARRICADES TO HAVE |
BALLASTS OVER BOTTOM RAILS. NO WORK ALLOWED |
BETWEEN 7:00AM-9:00AM&4:00PM-6:00PM. |
PLEASE BE SURE TO CALL IN THE FOLLOWING |
INSPECTIONS (LISTED ON THE BACK OF THE PERMIT): |
B800,801,802,803,804,805 |
PLEASE BE SURE TO FOLLOW THESE SPECIAL CONDITIONS |
(LISTED ON THE BACK OF THE PERMIT): |
A,B,C,D,E,F,G,H,I,J,K,L,M600,602,603,660 |