Miscellaneous Information / Notes |
CHANGE OUT COOLING TOWER AND OUTSIDE AIR UNITS |
|
|
|
|
|
|
|
5/10/17 HAROLD P/U PERMIT NATALEE |
5/9/17 READY TO ISSUE PENDING PAYMENT OF FEES, |
EMAILED CONTR, FILED LARGE BIN 'P' SH |
5/9/17 - ZONING PASSED. HANDED TO SH FOR |
PROCESSING. LL |
5/9/17 PLUMB APPROVED SENT TO SH BY GPJ |
5/9/17 MECH PASSED/SENT TO GJOHNSON/CC |
**5/9/17 EXPEDITED NO FEE** SH |
|
5/2/17 HAROLD RESUB TO ADDRESS DENIED COMMENTS |
SHOLDER |
4/26/17 PASSED BY FIRE, FAILED BY OTHER DEPTS., |
CONTACTED APPLICANT, RACHAEL RETURNED TO B19.PML |
4/24/17 PLUMB DENIED RETURN TO B19/GPJ |
4/20/17 - ZONING FAILED. RETURNED TO B19. LL |
4/19/17 CONTRACT SUBMITTED SHOWING AN INCREASED |
JOB VALUE OF $390,000.00/MECH FAILED/RETURNED TO |
B19/CC |
4/13/17 HAROLD RESUB TO ADDRESS DENIED COMMENTS |
SHOLDER |
3/20/17 PASSED BY FIRE, RETURNED TO B19.PML |
3/16/17 HAROLD RESUB TO ADDRESS DENIED COMMENTS |
SHOLDER |
3/6/17 PLAN REVIEW COMPLETE, CUSTOMER NEEDS TO |
RESUBMIT, FILED UNDER SMALL DENIED "P". CP |
3/2/17 PLUMB DENIED RETURN TO B05/GPJ |
2/24/17 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
B05.PML |