Miscellaneous Information / Notes |
INTERIOR RENOVATION FOR "STEAM HORSE BREWERY"; |
CHANGE OF OCCUPANCY FROM F1 TO A2/F2. FLOOD ZONE |
AE. |
|
|
|
|
|
5/25/17 ADRIENE P/U PERMIT SPALMER |
5/25/17 READY TO ISSUE PENDING PAYMENT OF FEES, |
EMAILED CONTR, LARGE BIN 'A' SH |
5/23/17 RESUB FOR IMPACT FEES; A BRAND NEW SET OF |
PLANS WAS SUBMITTED WITH IMPACT STAMP RES |
4/20/17 - DENIED FOR IMPACT FEES/CONTACTED |
CONTR./PLACED IN LARGE DENIED UNDER "A".TKL. |
4/14/17 JENNIFER RESUB PER DENIED COMMENTS RES |
4/11/17 ROUTED TO LARGE DENIED UNDER 'A'. CALLED |
CONTRACTOR. RL |
4/10/17 EARLY START REQUEST SUBMITTED AND |
FORWARDED TO ROBERT BROWN. SEE ATTACHED. SAK |
4/3/17 ADRIAN RESUB PER DENIED COMMENTS; TOLD |
S.HILL AS PER COMMENT BELOW RES |
|
**2ND SET OF SUPPORTING DOCUMENTS REQUIRED |
(PRODUCT APPROVALS, SPEC SHEETS, ETC.) OK TO |
PROVIDE MID-REVIEW CYCLE, ROUTE TO C22, APPLICANT |
IS TO LET ME KNOW WHEN IT IS SUBMITTED, WILL DO |
COURTESY 2ND REVIEW FOR THIS CYCLE IF POSSIBLE** |
SH |
|
3/27/17 - DENIED/CONTACTED CONTR./PLACED IN LARGE |
DENIED UNDER "A".TKL. |
3/7/17 PASSED BY FIRE WITH PROVISO COMMENTS, |
RETURNED TO C22.PML |
3/6/17 RESUB ADDRESSING DENIED COMMENTS NO FEES GD |
2/21/17 IN LARGE DENIED A/GPJ |
2/8/17 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
C22.PML |