Miscellaneous Information / Notes |
SHELL - NEW CONST OF A SHELL ONLY PERMIT FOR |
5 STORY TO INCLUDE FOUNDATIONS STRUCTURAL |
CONCRETE. |
THE REMAINDER OF THE 20 STORY BUILDING IS COVERED |
UNDER PERMIT 15031312. NO CERTIFICATE OF OCCUPANCY |
OR CERTIFICATE OF COMPLETION TO BE ISSUED TO THIS |
PERMIT. |
|
|
|
|
STOCKING PERMIT GRANTED 8/14/17 REG |
8/14/17 FEE ADDED REG |
8/10/17 REQUEST FOR STOCKING PERMIT ROUTED TO |
RICHARD GATHRIGHT & SCANNED TO THIS PERMIT SPALMER |
08/23/16 RECEIVED AND REVIEWED "DRY-IN" PLAN.KC |
08/31/2015 JAMES P/U PERMIT CARD NSD |
8/27/15 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
DOWNLOAD PLANS & PICK UP PERMIT CARD. CP |
8/27/15 PEDDS GIVEN TO SKENNEDY. CP |
08/27/15 PEDDS AND ORIGINAL PERMIT APP SUBMITTED |
AND ROUTED TO CAROLINE/LAURA ASM |
8/24/15 PEDDS & ORIG APPLICATION FORM REQUIRED |
BEFORE PERMIT CAN BE ISSUED. CP |
08/19/15 IMPACT FEES SUBMITTED AND ROUTED TO JIM |
WITMER ASM |
8/18/15 GIVEN TO SKENNEDY. CP |
08/18/15 PEDDS SUNMIITED ROUTED TO CAROLINE ASM |
8/4/15 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
SUBMIT IMPACT FEES, PEDDS & FEES. CP |
7/14/15 - PASSED ELECTRICAL REVIEW. NOTIFIED LEM. |
MA |
7/1/15 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
6/16/15 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
RESUBMIT. CP |
6/15/15- MECH DENIED/FIRE LINE SUBMITTAL DOCUMENTS |
REQUIRED/CC |
6/2/15 - FAILED ELECTRICAL REVIEW AS NOTED. MA |
4/14/15 FEES PAID, INCOMING COMPLETE. LEM |
4/7/15 PLANS UPLOADED WAITING ON FEES. CP |
3/18/15 APPLICANT INVITED TO UPLOAD PLANS, PAY |
FEES, AND EMAILED ART IN PUBLIC PLACES FORM. LEM |