Miscellaneous Information / Notes |
NEW 99 UNIT APARTMENT BUILDING TYPE: IIIB / IA |
|
|
|
|
11/27/17 CAROLYN P/U STOCKING CERTIFICATE SPALMER |
11/21/2017 06/21/2018 CERTIFICATE OF OCCUPANCY |
PRINTED AND PLACED AT FRONT COUNTER, FILED UNDER |
"B" WITH COPY SENT TO SCANNING. MM |
8/4/17 LIMITED TCO PREPARED. LISTS UNITS THAT ARE |
INCLUDED, EXCLUDES AMENITIES. EMAILED TO OWNER DH |
7/12/17 DAVINA P/U TCO/STOCKING CERTIFICATE |
SPALMER |
7/11/17 EMAILED BRADLEY CONSTRUCTION AND NEIL |
KOZOKOV TO PAY THE $1093.00 TCO/STOCKING |
CERTIFICATE FEE AND PICK UP THE SIGNED ORIGINAL |
CERTIFICATE. RB |
6/30/17 CONDITIONAL C/O REQUEST RECEIVED ROUTED TO |
DOUG HARVEY NATALEE |
7/13/15 PERMIT P/U BY NEIL ,MS |
7/10/15 PLANS IN FILENET. CP |
7/10/15 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
DOWNLOAD PLANS, PAY FEES AND PICK UP PERMIT CARD. |
CP |
7/10/15 PEDDS GIVEN TO SKENNEDY. CP |
07/10/2015 RESUB ROUTED TO JW NSD |
6/30/15 PEDDS RECEIVED, WAITING ON PLAN REVIEW TO |
BE COMPLETED. LEM |
6/30/15 SPECIAL INSPECTOR AGREEMENT & SOIL REPORTS |
GIVEN TO JIM WITMER SPALMER |
6/30/15 RECEIVED PEDDS & GIVEN TO LAURA MERCHANT |
SPALMER |
6/15/15 APPLICANT INVITED TO SUBMIT PEDDS PER |
SKENNEDY. CP |
6/10/15 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
RESUBMIT. LEM |
6/10/15 DENIED BY MECH/EMAILED CONTR/CC |
5/11/15 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
CP |
4/29/15 EMAIL REMINDER SENT TO RESUBMIT. LEM |
3/30/15 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
RESUBMIT. CP |
3/18/15 ART IN PUBLIC PLACES FORM EMAILED TO |
[email protected] CP |
3/2/15 PLANS RECIEVED,INCOMING COMPLETE. CP |
2/2/15 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
RESUBMIT ADDRESSING DENIED COMMENTS. CP |
12/11/14 PLANS UPLOADED INCOMING COMPLETE. CP |
12/10/14 APPLICANT INVITED TO UPLOAD PLANS VIA |
PROJECTDOX. CP |