Miscellaneous Information / Notes |
INTERIOR AND EXTERIOR ALTERATIONS FOR NEW STORAGE |
FACILITY AT "UNIT 3" |
|
|
|
|
|
3/18/15 CRAIG P/U TCO SPALMER |
3/18/15 ISSUED TCO.OWES $500.00.TO CO BOX, "R".KC |
3/16/15 RELEASED HOLDS PER GC E-MAIL.KC |
3/13/15 RECD. GC LETTER REQUESTING HOLDS ON FUTURE |
INSPECTIONS. A HOLD WAS PLACED ON ALL BUILDING |
INSPECTIONS.KC |
1/20/15 TCO REQUESTED GAVE TO KEN C., MS |
|
8/25/14 PERMIT P/U BY NATHAN, AG. |
8/23/2014 CALLED CONTRACTOR, PERMIT IS READY FOR |
ISSUANCE, OWES FEES, FILED UNDER "R" LARGE PLANS. |
JW |
8/21/14 RESUB ADDRESSING DENIED COMMENTS NO FEE |
SPALMER |
8/6/2014 APPLICATION DENIED. CONTACTED APPLICANT. |
IN LARGE DENIED "R" RIELLY CONSTRUCTION CORP. DAH |
8/5/14 PASSED BY FIRE PREVENTION WITH COMMENTS, |
RETURNED TO C16.PML |
7/30/14 SHEETS CHANGED, ROUTED TO BOARD FOR REVIEW |
SH |
7/29/14 SET CHECKED OUT NOT RETURNED AND SHEETS |
NOT SWAPPED OUT; EMAILED APPLICANT, PUT PLANS ON |
MM DESK SH |
7/29/14 REQUEST TO EXPEDITE. MM |
7/29/14 RESUB ADDRESSING DENIED COMMENTS NO FEE. |
MM |
7/21/2014 DEDUCTED $15,000.00FROM THE MASTER |
PERMIT. DEMO VALUE WAS INCLUDED IN MASTER. JW |
7-16-14 UNDER "R" LARGE DENIED BIN SEE BELOW.. PER |
NAT HEALY DEDUCTED $15,00O FOR INTER DEMO |
14070531, (ORIG APPL VALUE WAS $350,000.00 - |
$15,000.00 = $335,000.00 NEW CONTR VALUE) WL |
7/3/14 ONE SET OF PLANS PU BY NAT FOR IMAPCT SEW |
7/2/14 REVIEW COMPLETE, IN LARGE DENIED R, CALLED |
BILL. SAK. |
6/4/14 PLAN REVIEW FEES WERE PAID SEPARATELY. OK |
TO PROCEED WITH THE REVIEW. |
6/2/14 CALLED AND LEFT A MESSAGE FOR BILL RIELLY, |
RIELLY CONSTRUCTION CORP., TO ADVISE HIM THAT PALM |
BEACH SELF STORAGE LLC., CHECK 1001 (DATED |
5/23/14) WAS RETURNED NSF, AND WE WILL NOT PROCEED |
WITH THE PLAN REVIEW UNTIL WE RECEIVE PAYMENT. RB |
5/29/14 PASSED BY FIRE PREVENTION, RETURNED TO |
C16. PML |