Miscellaneous Information / Notes |
08-16-2012 REVISION; ADDITIONAL M/H WORK TO PULL |
NEW FIBER CABLE FROM BANYAN AND DIXIE TO CLEMATIS |
AND DIXIE STARTING 08-12-2012 FROM 7PM-3AM. |
30-EXCAVATE AND REPAIR DAMAGED FPL DUCT BANK AT |
INTERSECTION OF DIXIE AND CLEMATIS ST. THE WORK IS |
TO TAKE 6 DAYS AND THE CREW WILL WORK A FULL 24HR |
SHIFT. COORDINATE ALL WORK WITH WEST CONSTRUCTION, |
ROAD CLOSURES AND NO OVERLAPPING MOT SIGNS. |
CONTACT T.H. 644-7451 FOR ALL WORK PERMIT |
ISSUES/INSPECTIONS. |
|
FPL: WILLIAM THOMAS, 561-616-1628 |
CONTRACTOR: HYPOWER INC, C. SPITZER, 954-445-5133 |
START DATE: 08-05-2012 |
DURATION: 30 DAYS (6 DAYS) |
END DATE: 09-04-2012 |
BAGGING OF PARKING METERS IS REQUIRED WHEN |
BLOCKING PARKING STALLS. |
LIGHTED BARRICADES REQUIRED PER M600 IF LEFT UP |
AFTER DARK OR OVER NIGHT. |
ALL TYPE I&II BARRICADES TO HAVE SAND BAG BALLASTS |
OVER BOTTOM RAILS. |
7) PLEASE BE SURE TO CALL IN THE FOLLOWING |
INSPECTIONS (LISTED ON THE BACK OF THE PERMIT): |
B800,801,802,803,804,805,806 |
8) PLEASE BE SURE TO FOLLOW THESE SPECIAL |
CONDITIONS (LISTED ON THE BACK OF THE PERMIT): |
A,B,C,D,E,F,G,H,I,J,K,L,M600 SEE ATTACHED. |
|
|