Miscellaneous Information / Notes |
6TH FLOOR SUITE 655 INTERIOR BUILD OUT OF NEW |
OFFICE SUITE |
|
|
|
|
3-30-10 DARA PICKUP COC WL |
03/30/10 ISSUED COC LETTER. TO CO BOX, "M".KC |
11-10-09 IAN LEVINE PICKUP REV #1 WL |
11/6/09 MECH REVISION CALLED FOR P/U. SPOKE TO |
RICK. ALL ELECTRICAL SHEETS RETURNED, NOT |
REVIEWED. NO CHANGES SHOWN ON PLANS. SM BIN UNDER |
"M" RJR |
10-19-09 REV #1 $170 ELEC/MECH WL |
7/27/09 NOC FAXED AND UPDATED INSPECTION HOLD |
RELEASED SEW |
07/22/2009 FEES PAID PERMIT PLUS PLANS P/U BY |
STEPHANIE MMILLER |
7/22/9 READY TO ISSUE, FEES, CALLED CONTR,BIG BIN |
'M' SMH |
7/21/9 PLANS ROUTED TO MAW DESK SMH |
7/21/09 $170 FEE ADDED FOR EXPEDITED ELEC REVIEW. |
DV PALMER |
7/21/09 EXPEDITED REVIEW REQUEST SUBMITTED AND |
ROUTED TO DWISE SEW |
7/21/09 CHANGE OF CONTR $100 SEW |
07/14/2009 1ST RESUB PLANS PLUS APP NO FEE MMILLER |
07/08/2009 DENIED PLANS PLUS APP P/U BY STEPHANIE |
MMILLER |
7/8/09 CALLED CONTRACTOR READY FOR P/U **LARGE |
BINS** "G" SPALMER |
7-01 PLANS TO D WISE OFFICE FOR MECH REVIEW JW |
06/08/2009 PLANS ALREADY ROUTED TO INCOMING RCVD |
REQUEST FOR "EXPEDITED REVIEW ROUTED TO DOUG |
WISE'S MMILLER |