Miscellaneous Information / Notes |
#150 INTERIOR DEMO & TENANT BUILDOUT AS PER PLANS |
STRUC, ELEC, MECH |
|
|
|
|
|
1/12/09 MECH REVISION DATED 12/30/08 P/U BY DAN |
SLS |
1/12/09 CALL FOR P/U, UNDER(B), LEFT VM MESSAGE |
FOR WAYNE MILLER ADARROUGH |
1-09-09 SPOKE WITH PAUL,SUPER, AND WAYNE MILLER |
P.M., HAROLD M.MECH. CHIEF. RELAYED MECHANICAL AND |
FIRE ARE NOT SATISFIED FOR T.C.O.AS OF TODAY. TM |
01/06/2009 RCVD A LETTER FOR A REQUEST FOR A TCO |
FEES $500.00 ROUTED TO KEN CONRAD'S DESK MMILLER |
12/30/08 MECH REV ADD DUCT WORK & FIRE DAMPERS $80 |
SEW |
11/14/08 NOC SUBMITTED AND UPDATED INSPECTION HOLD |
RELEASED SEW |
11/12/08 PERMIT/PLANS PU BY DAN NEEDS NOC HOLD ON |
INSPECTIONS TILL WE RECEIVE SEW |
11/7/08 - PERMIT READY TO BE PRINTED. CALLED WAYNE |
MILLER FOR P/U. FILED UNDER B. *LARGE BIN* NEEDS |
NOC~MC |
11/6/08 - SENT TO MC FOR PROCESSING. ADQ |
11/4/08 - ZONING FAILED. SENT TO INCOMING FOR |
FURTHER PROCESSING. ~MC |
10/31/08 2ND RESUB W/PLANS & APPL SEW |
10/31/08 PU BY WAYNE SEW |
10/29/08 APP FOR EARLY START BLDG ONLY/AMM |
10/29/08 CALLED FOR P/U "B" LARGE BIN MRW |
10/29/2008 RCVD LETTER FOR REQUEST FOR EARLY START |
SENT TO DIANE FULCHER'S DESK MMILLER |
10/28/08 CHANGE OF CONTRACTOR $100 PUT APPLICATION |
WITH PERMIT PKG WILL NEED A NEW NOC SEW |
10/15/2008 1ST RESUB PLANS PLUS APP NO FEE MMILLER |
10-7-08 JERRY OBERLEY PICKUP DENIED PLANS WL |
10/7/08 CALLED FOR P/U "S" LARGE BIN MRW |
9/9/08 JERRY RETURNED THE APPLICATION BACK WITH |
FINANCE HOLD SIGN OFF SEW |
9-3-08 APPL BACK TO JERRY OBERLEY TO GET FINANCE |
HOLD SIGN OFF (SUBCONTRACTOR PERMIT #'S STILL NEED |
TO BE ADDED & APPL NEEDS TO BE STAMPED & |
INITIALED) WL |