Miscellaneous Information / Notes |
DEMO HOUSE AND BUILD NEW ONE. |
|
|
|
|
|
07/23/2009 APPROVED LANDSCAPE PLANS P/U BY ERIC |
MMILER TOWNSEND MMILLER |
7/21/09 - LANDSCAPE PLAN APPROVED. CALLED |
APPLICANT FOR P/U. FILED UNDER W. ~MC |
7/21/09 LANDSCAPE SUBMITTAL- CUSTOMER TOOK |
UPSTAIRS TO LANDSCAPING(KUSNER)SEW |
5-20-09 ERIC T PICKUP REV TAKEN AS SUBMITTAL |
(DATED 5-14-09) *SEE BELOW* WL |
5-20-09 PER M CRUZ REV FEE DUE (ADDED FEE $80) WL |
5/19/09 - APPROVED FOR DRIVEWAY. CALLED CONTRACTOR |
FOR P/U. FILED UNDER W. ~MC |
5/14/09 BLDG SUBMITTAL PER SPENTEK FOR REVIEW OF |
DRAWING SEW |
1-12-09 ERIC TOWNSEND PICKUP REV #8 MECH (DATED |
12-29-08 & BLDG REV (DATED 1-7-09) WL |
1/12/09 REV DATED 12/29/08 READY FOR P/U, UNDER(S) |
SPOKE TO ANDREW3 |
1-8-09 TALKED TO ERIC WOODLAND. BLDG REVISION |
FILED UNDER "W". JG. |
1-7-08 REV #8 BLDG $80 "NEW RAS CALC'S" WL |
1-6-09 TALKED TO JOHN AVERKAMP TO GO OVER THE RAS |
117 CALCULATIONS. JG. |
1-5-09 ERIC TOWNSEND PICKUP BLDG REV (DATED |
12-12-08) WL |
12-29-08 LEFT MESSAGE ON ERIC TOWNSEND'S |
CELLPHONE. BLDG REVISION UNDER "W". JG. |
12/29/2008 MECHANICAL REVISION #07 FEES $80.00 |
MMILLER |
12/29/2008 DENIED MECHANICAL REVISIO THAT WAS |
SUBMITTED ON 12/16/2008 WAS P/U BY ANDREW MMILLER |
12-29-08 MIKE GREINER PICKUP ROOFING REV (DATED |
12-19-08) WL |
12-23-08 TALKED TO MIKE. ROOFING REVISION UNDER |
"A". JG. |
12/22/08 REV DATED 12/16/08, DENIED AND READY FOR |
P/U, UNDER(W) SPOKE TO ANDREW ADARROUGH |
12/19/08 BLDG REV CHANGE ROOF COVERING FROM 24GA |
STANDING SEAM METAL TO .032 ALUM STANDING SEAM $80 |
SEW |
12/16/08 MECH REV $80 SPALMER |
12/12/08 BLDG REV $200 SPALMER |
11-3-08 MET W/ ERIC TO GO OVER COMMENTS. JG. |
11/03/2008 DENIED BLDG REVISION THAT WAS SUBMITTED |
ON 10/02/2008 WAS P/U BY ERIC MMILLER |
10-6-08 TAKED TO ERIC AND FAXED COMMENTS TO HIM. |
PLANS IN LARGE PLANS SHELF UNDER "W". JG. |
10/02/08 BLDG REV $80 SPALMER |
10/02/08 ERIC P/U DENIED REV SPALMER |
8-8-08 TALKED TO ERIC. PLANS UNDER *LARGE BINS* |
"W". JG. 7/31/08 BLDG/MECH REVISION $110 SOIL |
REPORTS STAIR DETAILS & REVISED ENERGY CALCS SLS |
7/31/08 PU BY ERIC SEW |
6-25-08 TALKED TO ERIC. PLANS UNDER "W". JG. |
6/11/08 BLDG/MECH REV SEE ATTACHED SHEET $110 SEW |
04/04/2008 PERMIT PLUS PLANS P/U BY ERIC |
(QUALIFIER) MMILLER |
3-13-08 LEFT MESSAGE ON ERIC'S CELL PHONE. PERMIT |
IN LARGE PLANS SHELF UNDER "W". JG. |
3/5/08 4TH RESUB W/PLANS & APPL SEW |
2/7/08 PU BY VICKIE SEW |
2-6-08 TALKED TO BILL FROM WOODLAND ENTERPRISES. |
PLANS IN LARGE PLANS SHELF UNDER "W". JG. |
2-5-08 LEFT MESSAGE TO NEYITA. PLANS ON JULIO'S |
DESK. JG. 1/28/8 SCOPE OF WORK CHANGED; ALL NEW |
PLANS SUBMITTED FOR 2 STORY NEW SFD; ROUTED TO J |
GOMEZ DESK; OK PER RB SMH |
1-16-08 MECH. PLAN ADDED TO BUILD. PLAN SENT TO |
S.HILL DESK TG. |
1-15-08 PLANS IN REVIEW ARE AT TOM G. DESK. |
1/14/08 MECH PLAN SUBMITTED PER TOM GORDON |
INSTRUCTIONS NO FEE SPALMER |
1/7/08 3RD RESUB PLANS/APP $275 SLS |
9/25/07 DENIED RESUB PLANS/APP/COMMENTS P/U BY |
VICKY (NEYITA) AJP |
9/25/07 MOVED TO LARGE PLAN BIN "W" AJP 09/25/2007 |
CALLED CUSTOMER DENIED PLANS PLUS APP READY FOR |
P/U FILED UNDER "W" MMILLER |
9/24/7 TO MM DESK SMH |
8/8/07 2ND RESUB W/PLANS & APPL SEW |
7/11/07 VICKY P/U DENIED PLANS SPALMER |
7/10/07 CORRECTIONS NEEDED CALLED SPOKE TO NEYITA |
FILED UNDER "W" LARGE BIN SLS |
7/10/7 TO SLS DESK SMH |
05/23/07 1ST RESUB NO FEE- NEW PLANS -PRODUCT |
APPROVALS- SURVEYS- CALCS- (1) OLD PLANS FG |
3/15/07 VICKY P/U DENIED PLANS SPALMER |
3-14-07 **REMINDER CALL** 3RD CALL TALKED TO CAROL |
GACHE TOLD HER THIS IS 3RD CALL & THAT SOMEONE |
NEEDS TO PICKUP DENIED PLANS LARGE BIN "W" WL |
2-9-07 2ND CALL..TOLD N LEIVA THAT DENIED PLANS |
NEED TO BE PICKED UP LARGE BIN "W" WL |
1/5/7 CORR CALLED CONTR L/M **LARGE BINS** 'W' |
SMH |
10/31/06 APP AND PLANS GIVEN BACK TO CUSTOMER NEED |
TO BE APPROVED BY FINANCE DEPT FIRST -FG |