Miscellaneous Information / Notes |
NEW CITY PLACE 16-STORY OFFICE TOWER. |
|
|
8/27/08 CERTIFICATE OF COMPLETION ISSUED. JDS |
8/26/08 REVISED ELEC. MECH. AND ENERGY CALCS, |
CALLED FOR P/U. LEFT MSG ON TRIXY'S CELL, CALLED |
BALFOUR-BEATTY, WAS PLACED ON HOLD AND NO ONE EVER |
PICKED UP. LG BIN UNDER "B" RJR |
8-15-08 (ADED 5 MORE PAGES TO ELEC REV DATED |
8-14-08 ADDTL $50 (OK PER A DARROUGH & S PALMER AS |
ELEC REVIEW WAS NOT DONE YET) WL |
8/14/08 ELEC REV $70 SPALMER |
7/28/08 ELEC/MECH/BLDG SUBMITTAL P/U BY MARCUS |
SLS |
7-25-08 BASE BUILDING ENERGY CALCS FILED UNDER |
"B" |
LARGE PLANS JW |
7/16/08 ELEC REVISION P/U BY MARCUS MM |
7/16/08 ELEC REVISIONS DENIED. UNDER "B" (LARGE |
BINS FOR PICK UP. CALLED AND SPOKE TO MIKE CARLIN |
AND SENT E-MAIL TO DAN PETROCCHI. REMINDED OF THE |
NEED FOR THE BLUE CARD TO PCIK UP PLANS. DV |
PALMER. |
|
/07/02/2008 RCVD NEW ELECTRICAL ENERGY CALCS AND |
CUSTOMER (TRIXY) TOOK OLD CALCS IN ROUTED TO DEWEY |
PALMER'S DESK MMILLER |
07/02/2008 ENERGY CALCS P/U BY TRIXY MMILLER |
7/2/08 ENERGY CALCULATIONS FROM 5/30 ARE ON HOLD |
AND WILL BE UNDER "B" (LARGE BINS) TO BE CHANGED |
OUT. NO REVIEW WAS DONE BY ANY TRADE. ROUTED BACK |
THROUGH INCOMING WIHT NEW DATE WHEN THEY ARE |
CHANGED OUT/SUBMITTED. DV PALMER. |
|
6/17/08 ELEC REV $70 SPALMER |
6-3-08 MARCUS NICELY PICKUP ELEC REV #56 (DATED |
5-8-08) WL |
6-03-08 CALLED NATHAN PLANS FILED UNDER "B" LARGE |
PLAN JW |
5/30/08 ELEC REVISION # 46 DATED 5/21/08 PULLED |
OUT OF REVIEW BY CONTRACTOR WILL HAVE $70 CREDIT |
TOWARDS NEXT REVISION PER DEWEY SLS |
5/30/08 ELECRICAL SUBMITTAL # 16000-102 NO FEE |
SLS |
5/27/08 ELEC REVISION # 50 FOR WATER FEATURE $80 |
SLS |
5/27/08 MARCUS P/U UL FIELD EVALUATION SUBMITTAL |
#16000-101 SPALMER |
5/27/08 ELEC SUBMITTAL DENIED, UNDER "B" (LARGE |
BINS) FOR PU. CALLED AND LEFT MESSAGE ON NATHAN'S |
CELL VM. DV PALMER. |
5/23/08 TEST & BALANCE REPORT SUBMITTAL #15500-101 |
(SUBMITTED 5/16/08) WAS WITHDRAWN BY CONTRACTOR |
PRIOR TO REVIEW PER EMAIL REQUEST FROM NATHAN |
DUCOTE OF BALFOUR BEATTY. P/U BY NATHAN. RJR |
5/21/08 BLDG/ZONING REV PU BY MARCUS SEW |
5/21/08 ELEC REV 46 E3.03 E3.03.1 $70 SEW |
5-19-08 NATHAN DUCOTE PICKUP SMOKE CONTROL TEST |
REPORT DATED 5-13-08 WL |
05/19/08 SMOKE CONTROL SYSTEM SUBMITTALS READY FOR |
P/U; IN LARGE BIN "B" MAW |
05-19-08 MARCUS NICELY PICKUP SKYLIGHT PROD APPROV |
WL |
05/16/08 CALLED NICK FOR SKYLIGHT LOCAL PRODUCT |
APPROVAL P/U. 'B". RB |
5/16/08 MECH SUBMITTAL TEST & BALANCE REPORT SEW |
5/16/08 MARCUS P/U FIRESTOP SUBMITTAL. RB |
5/16/08 CALLED MIKE FOR FIRESTOP SUBMITTAL P/U. |
'B'. |
RB |
5-15-08 CALLED FOR P/U OF PLUMBING REVISIONS. |
TALKED TO NATHAN D. AND INDICATED THE REVISIONS |
WERE APPROVED AND THAT THE BLUE CARD OR RECIEPT |
WAS REQUIRED TO RETRIEVE THE PLAN. "B-LARGE" |
KSTEVENS |
5/14/08 BLDG SUBMITTAL # 03450-020 P/U BY MARCUS |
SLS |
5/14/08 MECH REVISION # 47 P/U BY MARCUS SLS |
5/14/08 - BLDG REV #50 ROUTED TO "B - JW" CJH |
5/14/08 MECH REV 47 PAGE H2.01 CALLED FOR P/U. |
SPOKE TO NATHAN. SM BIN UNDER "B" RJR |
5/13/08 SUBMITTAL #15500-101 SMOKE CONTROL |
COMMISSIONING REPORT REVIEWED AND SENT TO HAROLD |
MOSER. ALSO NEEDS TO GO TO CHIEF CARSILLO FOR |
REVIEW. RJR |
5/13/08 BLDG SUBMITTAL #20000-010-R1 FIRE STOP |
ENGINEERING JUDGEMNT & FIRE PROTECTION SEW 5/13/08 |
MECH REV #47 H2.01 $60 SEW |
5/13/08 SUBMITTAL #15500-101 SMK CONTROL SYSTEM |
TEST REPORT SEW |
5/12/08 ELEC SUBMITTAL # 16000-101 NO FEE SLS |
5/12/08 BLDG REVISION # 43 P/U BY MARCUS SLS |
5-12-08 CALLED FILED UNDER "B" LARGE PLAN JW |
5/12/08 - BLDG REV #50 SENT TO ES - 5TH FLOOR |
CJH |
5/12/08 SEAN P/U SUBMITTALS SPALMER |
5-12-08 CALLED CONTRACTOR FILED SUBMITTALS IN THE |
LOWER BINS SPOKE WITH SEAN JW |
5/9/08 PLBG SUBMITTAL LETTER NO FEE SLS |
5/8/08 - ZON/BLD SUBITTAL #03450-020 NOT |
APPLICABLE (NEEDS SEP. PERMIT), CALLED NATHAN TO |
P/U. FILED UNDER "B". CJH |
05/08/2008 MECHANICAL REVISION # 42 P/U BY NATHAN |
MMILLER |
05/08/2008 MECHIANCAL REVISION # 45 P/U BY NATHAN |
MMILLER |
05/08/2008 ELECTRICAL REVISION # 52 FEES $180.00 |
MMILLER |
MMILLER |
05/08/2008 PLUMBING REVISION # 51 FEES $ 90.00 |
MMILLER |
05/08/2008 BLDG REVISION #50 FEES $ 60.00 MMILLER |
5/8/08 CALLED FOR P/U "B" MRW |
5/8/08 MECH REV 45 CALLED FOR P/U. SPOKE TO |
NATHAN. SM BIN UNDER "B" RJR |
5/6/08 MECH REVISION # 45 DRWGS H1.07 & H1.09 $70 |
SLS |
5/6/08 BLDG SUBMITTAL FOR SITE SPECIFIC PRODUCT |
APPROVAL NO FEE SLS |
5/6/08 BLDG SUBMITTAL # 20000-0010 P/U BY MARCUS |
SLS |
5-6-08 MARCUS NICELY PICKUP 2 REV DATED 4-30-2008 |
BLDG RFI0474, RFI0471, & SUBMITTAL (PLUMB) DATED |
4-18-2008 #07841-005 WL |
05-08-08 CALLED CONTRACTOR PLANS FILED UNDER "B" |
SMALL PLAN FOR FIRESTOPPING DETAILS JW |
05-05-08 CALLED FILED UNDER "B" REVISIONS SMALL |
PLANS SPOKE WITH NICK JW |
5-2-08 CALLED FOR P/U AND TALKED TO NATHAN D. |
INDICATING THAT THE SUBMITTALS WERE APPROVED. TOLD |
HIM THE SUBMITTAL INDEX DID NOT REFLECT WHAT WAS |
SUBMITTED AND IF C-AJ-2110 WAS NEEDED IT COULD BE |
SUBMITTED. THE BLUE CARD WAS REQUIRED FOR P/U "B" |
KSTEVENS |
5/1/08 BLDG/ZONING/ENGINEERING REVISION # 43 $120 |
SLS |
5/1/08 BLDG SUMBITTAL FIELD EVALUATION REPORTS NO |
FEE SLS |
5/1/08 BLDG SUBMITTAL # 03450-020 MONUMENT SIGN |
CONNECTION DETAIL NO FEE SLS |
5-1-08 MARCUS NICELY PICKUP (3) BLDG SUBMITTALS |
"RFI0495" DATED 4-24-08, 07414-006/07415-007 DATED |
4-28-08, & #7552-010 DATED 4-24-08 WL 4-30-08 |
CALLED CONTRACTOR SPOKE WITH NICK REVISIONS FILED |
UNDER B SMALL PLANS JW |
4/30/08 3 BLDG REVISIONS RFI 0471 ROLLING GRILLES |
- RFI 0473 ACCESS TO SCF-2 - RFI 0474 PLATFORM |
OVER CONDENSOR WATER PIPES TOTAL $200 SLS |
4/29/08 BLDG SUBMITTAL # 20000-0010 FIRESTOP ENG |
NO FEE SLS |
4/29/08 MECH & FIRE REVISION # 42 $80 SLS |
4/28/08 BLDG SUBMITTAL # 08600-006 SKYLIGHTS NO |
FEE SLS |
4/28/08 BLDG SUBMITTAL # 07415-006 CORNICE END |
PANEL & # 07415-007 NORTH CANOPY BEAM WRAPS NO FEE |
SLS |
04/24/2008 APPROVED PLUMBING REVISION THAT WAS |
SUBMITTED ON 04/10/2008 WAS P/U BY NICK MMILLER |
|
04/24/2008 APRROVED/DENIED PLUMBING REVISION THAT |
WAS SUBMITTED ON 04/10/2008 WAS P/U BY NICK |
MMILLER |
|
04/24/2008 BLDG SUBMITTAL (#7552-010) NO FEE |
MMILLER |
|
04/24/2008 BLDG SUBMITTAL ( RFI0495 SHAFT WALLS |
@SPF-2& SCF-1) NO FEE MMILLER |
|
|
|
4-23-08 CALLED FOR P/U OF PLUMBING REVISIONS 38 & |
39 AND TALKED TO NATHAN DUCOTE INDICATING THAT |
REV. 38 ONE SHEET PASSED ONE SHEET WAS DENIED, |
REV. 39 OK. INDICATED THAT THE RECIEPT OR BLUE |
CARD WAS REQUIRED TO RETRIEVE THE REVISIONS. "B" |
KSTEVENS |
04/23/2008 RCVD LETTER FOR A REQUEST FOR A TCO |
FEES $ 500.00 SENT TO HAROLD PISKURA'S DESK |
MMILLER |
4-22-08 NICK KRARUP PICKUP BLDG SUBMITTALS |
07415-006 & 07415-007, 08960-001-R3, & 08600-006 |
DATED 3-7-08, BLDG SUBMITTALS RFI 0495 DATED |
4-18-08, RFI 0474-R3 DATED 4-16-08, RFI 0473 & RFI |
0471 DATED 3-27-08, 05510-003 DATED 3-10-08, |
7552-010 DATED 4-15-08, & 10210-009 DATED 4-4-08 |
WL |
4-21-08 CALLED REVISIONS AND SUBMITTALS FILED |
UNDER |
"B" LARGE PLAN JW |
4/18/08 BLDG SUBMITTAL # RFI-0495 SHAFT WALLS NO |
FEE SLS |
4/18/08 BLDG SUBMITTAL # 07841-005 RIGHTWAY PVC |
PIPING & FIRESTOPPING NO FEE SLS |
4/17/08 MECH REV # 40 P/U BY MARCUS SLS |
4/17/08 MECH REV 40 AND 41 TOGETHER. CALLED FOR |
P/U. LEFT MSG FOR SEAN. LG BIN UNDER "B" RJR |
4/16/08 BLDG SUBMITTAL RFI 0474-R3 PLATFORM OVER |
CONDENSER WATER PIPES ON ROOF SEW |
4/15/08 MECHANICAL REVISION # 41 $80 SLS |
4/15/08 BLDG SUBMITTAL # 7332-010 ROOF LEDGE |
DETAIL NO FEE SLS |
4/15/08 PLUMBING SUBMITTAL P/U BY MARCUS SLS |
4-12-08 CALLED FOR P/U IRR REVISIONS AND LEFT A |
MESSAGE ON NATE DUCOTE'S VOICE MAIL INDICATING |
THAT THE REVISION WERE APPROVED AND THAT HE NEEDS |
THE BLUE CARD TO RETRIEVE THE REVISIONS. "B" |
KSTEVENS |
4/10/08 PLUMBING REVISION # 39 $70 SLS |
4/10/08 PLUMBING REVISION # 38 $70 SLS |
4/8/08 MARCUS P/U FIRE REV DATED 3/20/08 SPALMER |
4/8/08 MARCUS P/U BLDG SUBMITTAL SPALMER |
4/7/08 BLDG SUBMITTAL READY FOR P/U CALLED CONT |
SPOKE TO NATHAN FILED UNDER "B" *LARGE BIN* |
SLS/WL |
4/7/8 TO SLS DESK FOR PROCESSING SMH |
4/4/08 BLDG SUBMITTAL 10210-009 ALUFAB SOUTH |
CANOPY SHOP DRAWING NO FEE SPALMER |
4/2/08 BLDG SUBMITTAL RS DETAIL BINDER & CURTAIN |
SHOP DRAWINGS SIGNED & SEALED (3-BINDERS 3-ROLLS |
PLANS) SEW |
4/1/08 BUILDING SUBMITTAL PER INSPECTORS REQUEST |
NO FEE SLS |
4/1/08 PLUMBING SUBMITTAL PER INSPECTORS REQUEST |
NO FEE SLS |
4/1/08 MECHANICAL REVISION # 40 DRWG H1.06 $60 |
SLS |
3/27/08 BLDG SUBMITTAL 3 SIGNED & SEALED COPIES OF |
RFI-0473 & RFI-0471 NO FEE SLS |
3-27-05 MARCUS NICELEY PICKUP BLDG/ZONING REV |
DATED 3-20-08 WL |
3/27/08 ARCHITECTURAL REVISION #36 DENIED. CALLED |
FOR P/U. SPOKE TO NATHAN. LG BIN UNDER "B" RJR |
3/26/08 REVISIONS # 37 & # 33 P/U BY MARCUS SLS |
3/25/08 REVISION # 37 READY FOR P/U PLBG FAILED |
BUT ALL OTHER TRADES PASSED CALLED SPOKE TO NATHAN |
FILED UNDER LARGE BIN "B" SLS |
3/24/08 CALLED FOR P/U PUT OUT IN BINS UNDER "B" |
JL |
3/20/08 BLDG/ZON REV $90 SPALMER |
3/18/08 MARCUS P/U PLUMB REV DATED 2/29/08 |
SPALMER |
3-18-8 CALLED FOR P/U PLMG REVISIONS AND TALKED TO |
NATHAN D. INDICATING THAT ALL THE REVISIONS WERE |
APPROVED EXCEPT ONE SHEET AND THAT THE RECIEPT OR |
BLUE CARD WAS REQUIRED TO RETRIEVE THE REVISIONS. |
"B-LARGE" KSTEVENS |
3-11-08 MARCUS NICELEY PICKUP REV #33 MECH DATED |
2-13-2008 WL |
3/10/08 MECH REV 33 CALLED FOR P/U. LEFT MSG FOR |
NATHAN. LG BIN UNDER "B" RJR |
3/10/08 BLDG SUBMITTAL # 05510-003 NET STAIRS S/S |
SHOP DRWGS & CALCULATIONS NO FEE SLS |
3/10/08 ELEC REVISION P/U BY MARCUS SLS |
3/10/08 ELEC REVISION UNDER "B"**LARGE BIN**WRT/WL |
03/07/2008 BLDG SUBMITTAL NO FEE (07415-006- |
STRUCTURAL EXTERIOR COMP CORNICE END PANELS |
SUBMITTIAL# 07415-007 STRUCTURAL CALCS EXTERIOR |
COMP PANELS PORTE BEAM WRAP PANEL) MMILLER |
|
|
03/07/2008 BLDG SUBMITTAL (08600-006 SKYLIGHTS |
PRODUCT EVALUATION REPORT) MMILLER |
|
|
03/07/2008 BLDG SUBMITTAL NO FEE (0890-001-R3 |
SLOPED GLAZING SYSTEMS SHOPS DRAWINGS & REVISED |
NOA#)MMILLER |
3/3/08 SUBMITTAL FROM 2/8/08 PICKED UP BY NICK |
KRARUP ADARROUGH |
3-3-08 NICK KRARUP PICKUP ELEC REV #36, 3 |
SUBMITTAL PKGS DATED 2-8-08 #10210-007 ALUFAB |
LOUVERS, #03450-019 ARCH. PRECAST CONCRETE, & |
#08960-008,08960-009,08960-002-R2, &08960-006 WL |
3/33/08 CP NEEDS TO SUBMIT PLANS TO P&Z PRIOR TO |
P&Z APPROVAL OF PERMIT FOR ARCH-LANDSCAPE-CIVIL |
REVISION #37 ES |
2/29/08 CURTAIL WALL SHOP DRWGS & CALCS SUBMITTAL |
P/U BY MARCUS SLS |
2/29/08 ARCH-LANDSCAPE-CIVIL REVISION # 37 $340 |
SLS |
2/29/08 ELECTRICAL REVISION # 37 $150 SLS |
2-29-08 CALLED CONTRACTOR FILED UNDER |
"B" BOTTOM BINS SPOKE WITH SEAN'S VOICE MAIL JW |
2-27-08 CALLED CONTRACTOR SUBMITTALS FILED UNDER |
SMALL PLANS LEFT MESSAGE FOR NICK JW |
2/27/08 PUT OUT FRONT IN BIG BINS FOR P/U UNDER |
"B" CALLED NAT FOR P/U JLEAHY |
2/26/08 FIRE REVISION #33 & #32 AND |
BUILDING/ZONING REVISION #33 P/U BY MARCUS SLS |
02/26/08 REVISED FP (ONE ROLL) AND FA SHEETS (ONE |
ROLL) READY FOR P/U; IN LARGE BIN "B" MAW/FIRE |
02/20/08 BLDG SUBMITTALS CURTAIN WALL SHOP DRWGS & |
CALCULATIONS NO FEE SLS |
02/19/08 DURING FILING OF REVISED PLANS, FIRE |
ALARM REVISION # 6 WAS FOUND TO BE WITHOUT |
SIGNATURE AND SEAL. FILE COPY HAS SENT TO MIKE |
WILLIAMS FOR INFORMATION, WITH INSTRUCTION TO |
RETURN TO R BROWN. AN E-MAIL WAS SENT TO THE |
ENGINEER REQUESTING THAT SIGNED AND SEALED COPIES |
BE BROUGHT IN AS A NO FEE SUBMITTAL.RB |
02/13/2008 ELECTRICAL REVISION # 36 FEES $ 110.00 |
MMILLER |
02/13/2008 MECHANICAL REVISION # 35 FEES $ 200.00 |
MMILLER |
02/13/2008 PLUBMING REVISION # 34 FEES $140.00 |
MMILLER |
02/13/2008 FIRE (PROTECTION) REVISION #33 FEES |
$90.00 |
02/13/2008 FIRE REVISION # 32 FEES 160.00 MMILLER |
2-13-08 CALLED CONTRACTOR FILED LARGE REVISION |
LOWER BINS SPOKE WITH NATHAN JW |
2/12/08 BLDG SUBMITTAL GARAGE INT WIND LOADS PU BY |
MARCUS SEW |
2/12/08 BLDG SUBMITTAL 15TH/16TH FL CONNECTIONS PU |
BY MARCUS SEW |
2/12/08 BLDG SUBMITTAL CURTAIN WALL 14TH FL PU BY |
MARCUS SEW |
2/12/08 BLDG SUBMITTAL STOREFRONT & SHOP DRAWING |
PU BY MARCUS SEW |
2/12/08 PLUMBING REV PU BY MARCUS SEW |
2-12-08 CALLED FOR P/U & TALKED TO NATHAN DUCOTE |
INDICATING THAT THE PLUMBING REVISION WAS APPROVED |
FOR ONE SHEET AND DENIED FOR THE OTHER. TOLD HIM |
THAT HE NEEDED EITHER THE RECIEPT OR THE BLUE CARD |
TO RETRIEVE THE REVISIONS. "B-LARGE" KSTEVENS |
2/8/08 4 BLDG SUBMITTALS NO FEE SLS |
2/8/08 BLDG SUBMITTAL ALUM LOUVERS #10210-007 SLS |
2/8/08 BLDG SUBMITTAL PRECAST CONCRETE #03450-019 |
SLS |
2/8/07 BLDG SUBMITTAL SOUTH CANOPY #10210-005 SLS |
1-31-08 CALLED CONTRACTOR SPOKE WITH SEAN VOICE |
MAIL FILED UNDER "B" LARGE PLANS JW |
1/30/08 BLDG SUBMITTALS GARAGE INT WIND LOADS & |
CURTAIN WALL-REV HEAD DETAIL NO FEE SLS |
01/28/2008 BLDG SUBMITTAL NO FEE (COURTESY COPIES |
OF CALCS AND SHOP DRAWINGS FOR RADIUS CURTAIN WALL |
15TH/16TH FLOOR REVISED CONNECTIONS) MMILLER |
01/28/2008 BLDG SUBMITTAL NO FEE (PUNCH WINDOW & |
STOREFRONT SHOP DRAWINGS AND CALCS) MMILLER |
1-24-08 CALLED SPOKE WITH SEAN SUBMITTALS ARE |
FILED UNDER "B" LARGE PLANS JW |
1/22/08 PLUMBING REVISION $70 SLS |
01/22/2008 BLDG SUBMITTAL NO FEE ( SUBMITTAL |
#07552-007-R1 ROOF EDGE DETAIL &CORNICE DRIP EDGE |
& WOOD BLOCKING ATTACHEMENT SIGNED & SEALED) |
MMILLER |
1/9/08 BLDG/ZONING REV #33 ARCHITECTURAL CIVIL & |
LANDSCAPING SEW |
1/9/08 FIRE REV PU BY MARCUS SEW |
1/9/08 MECH REV #32 PU BY MARCUS SEW |
1/9/08 CALLED FOR P/U "B" LARGE BIN MRW |
1/7/08 MECH REV #32 CALLED FOR P/U. LG BIN UNDER |
"B" SPOKE TO NATHAN. RJR |
12-28-07 NICK KRARUP PICKUP 2 SUBMITTALS OVERHEAD |
ROLLUP DOOR SUBMITTALS DATED 11-27-07 7 LIGHT |
GAUGE FRAMING DATED 12-3-07 WL |
12-28-07 CALLED CONTRACTOR SPOKE WITH NICK FILED |
UNDER "B" *LARGE BIN* JW |
12-26-07 NICK KRARUP PICKUP REV # 31 ELEC WL |
12/25/07 ELEC REV OK,CALLED AND LEFT MESSAGE ON |
NATHANS'S VM.PLANS UNDER "B" (LARGE BINS). |
REMINDED TO BRING BLUE CARD. DV PALMER. |
|
12/21/07 NATHAN FROM BALFOUR BEATTY PICKED UP |
WATER FEATURE SUBMITTAL JW |
12/21/2007 APPROVED MECHANICAL REVISION THAT WAS |
SUBMITTED ON 11/28/2007 WHICH IS REVISION # 24 P/U |
BY NICK MMILLER |
|
12/21/2007 MECHANICAL REVISION # 29 MMILLER |
|
12/20/07 MECH REV.29 CALLED FOR P/U. SPOKE TO |
NATHAN. LG BIN UNDER "B" RJR |
12/20/07 SUBMITTAL 11010-003 & 11010-004 WINDOW |
WASHING EQUIP SPALMER |
12/20/07 ELEC REV#31 $110 SPALMER |
12/20/07 SUBMITTAL 03450-018 ARCH PRECAST CONCRETE |
SHOP DRAWINGS SPALMER |
12/17/07 CALLED FOR P/U AND LEFT A MESSAGE ON |
NATHAN DUCOTE'S VOICE MAIL INDICATING THAT THERE |
WERE COMMENTS TO BE ADDRESSED ON THE PLUMBING |
REVISION AND THAT THE RECIEPT OR BLUE CARD WAS |
REQUIRED TO RETRIEVE THE REVISIONS. "B" KSTEVENS |
12/14/07 EL. REV (APPROVED) # 26 P/U BY NATHAN |
AJP |
12/11/07 ELECTRICAL REV'S OK,CALLED SPOKE TO |
NATHAN TOLD TO BRING IN BLUE CARD FOR ELEC REV'S |
DATED 11/28, PLANS UNDER "B" (LARGE BINS) FOR PU. |
DV PALMER |
12/10/07 PLUMBING REV'S #13 AND #18 P/U BY NATHAN |
AJP |
12/10/07 PLUMB REV $70 SPALMER |
12-06-07 CALLED FOR P/U AND TALKED TO NATHAN AND |
TOLD HIM THE PLUMBING REVISIONS FROM 8-31 & 10-05 |
WERE READY AND HAD PASSED REVIEW. INDICATED THAT |
HE NEEDS THE RECIEPT OR BLUE CARD TO RETRIEVE THE |
REVISIONS. "B-LARGE" KSTEVENS |
12-6-07 NO FEE BLDG/ELEC/PLUMB "SUBMITTAL |
#02430-001-R4-WATER FEATURE DRAWINGS" WL |
12/6/07 THE FOLLOWING APPROVED SUBMITTALS P/U BY |
NICK: 09111-017, LIGHT GAUGE METAL STUD FRAMING, |
FASCIA @ EAST RAMP ENTRY;#09222-016 LIGHT, GAUGE |
METAL STUD FRAMING; #089112-010 NOA-DOORS 601A, |
1501A,1501B; 08411-006,NOA DOORS 107B, 108 A & B, |
110 A & B, 127B, 206A,L 208A, 306A, 406A, 506A, |
100A, 400A, 500A, 600A. AJP |
12/4/07 BLDG SUBMITTAL CLADDING SYSTEMS NO FEE |
SLS |
12/4/07 BLDG SUBMITTAL LIGHT GAUGE FRAMING NO FEE |
SLS |
11/28/2007 ELECTRICAL REVISION #26 FEES $ 100.00 |
MMILLER |
11/28/2007 FIRE REVISION # 25 FEES $ 70.00 |
MMILLER |
11/28/2007 MECHANICAL REVISION #24 FEES 190.00 |
MMILLER |
11/27/07 BLDG SUBMITTAL OVERHEAD ROLLUP DOORS NO |
FEE SLS |
11-20-07 CALLED CONTRACTOR SUBMITTALS FILED UNDER |
"B" SMALL PLAN JW |
11/16/2007 BLDG SUBMITTAL NO FEE (#10200-007 |
REVISION 15 LOUVER SHOP DRAWIWNGS & NOA) MMILLER |
11/16/2007 BLDG SUBMITTAL NO FEE |
(#09111I-017-LIGHT GAUGE METAL STUD FRAMING FASCIA |
@EAST RAMP ENTRY) MMILLER |
11/14/07 APPROVED FIRE REV #23(SHTS FA0/01,FA1.15; |
EL REV # 23 SHTS E1.17,E3.02, E3.65; AND MECH REV |
S #23, SHTS H0.02, H1.16, H1.17, H2.04 P/U BY NICK |
AJP |
11/10/07 MECH REV 23 CALLED FOR P/U LEFT MSG FOR |
NATHAN. LG BIN UNDER "B" RJR |
11/9/07 REVISION P/U BY SASCHA AJP |
11-07-07 CALLED FILED UNDER "B" LARGE PLAN JW |
11/01/07 RVSD F/A SHEETS READY FOR P/U UNDER "B" |
MAW |
10/30/07 BLDG SUBMITTAL # 09111-016 METAL STUD |
FRAMING # 08912-010 DOORS NOA # 08411-006 DOORS |
NOA NO FEE SLS |
10/30/07 NICK P/U THE FOLLOWING SUBMITTALS: |
05120-402 (STRUCT. STEEL AS-BUILTS);05120-401 (ST. |
STEEL CALCS);09111-014 (SOFFIT CLADDING |
LETTER);03450-016 (GATE LETTER);SIGNED/SEALED STR. |
STEEL CALCS & MODS;FIRE REV. #16, AND FIRE REV. |
#15 AJP |
10-30-07 CALLED FILED UNDER "B"LAARGE PLAN JW |
10/27/07 ELEC REV FROM 10/22 OUTFRONT UNDER "B" |
(SMALL) READY FOR PU. CALLED AND LEFT MESSGAE ON |
NATHAN'S CELL VM TOLD TO BRING IN BLUE CARD. DV |
PALMER. |
10/25/07 RVSD FA/FP SHEETS READY IN LARGE BIN "B" |
MAW |
10/23/07 SUBMITTALS MOVED TO LARGE PLAN BIN "B" |
AJP |
10-25-07 CALLED CONT SUBMITTALS FILED UNDER "B" |
SMALL PLAN JW |
10/22/07 ZONING REV #20 P/U BY MARCUS AJP 10/22/07 |
MECHANICAL REVISION $90 SLS |
10/22/07 FIRE ALARM REVISION $70 SLS |
10/22/07 ELECTRICAL REVISION $80 SLS |
10/22/07 BLDG SUBMITTAL LOUVER SHOP DRWGS NO FEE |
SLS |
10/22/07 CALLED,LEFT MESSAGE,FOR P/U DENIED PLANS, |
LARGE BIN"B",RVC |
10/16/07 THE FOLLOWING SUBMITTALS P/U BY NICK: |
#08600-001, SKYLIGHTS SHOP DRAWINGS;#08600-002, |
SKYLIGHTS CALC;09111-001 LIGHT GAUGE MET.STUDS; |
#09111-010 LIGHT GAUGE METAL STUDS;#09111-011 |
GARAGE PARAPET-METAL STUDS;#09111-012, SOFFIT |
METAL STUD FRAMING;#05120-402, STRUCTURAL STEEL |
AS-BUILTS;#3450-004 SIGNED/SEALED PRE-CAST |
STRUCTURAL DESIGN CALCS;#07552-006, NORTH ELEVTOR |
TOWER CALCS AND PRODUCT APPPROVALS;#05511-003 |
PREFAB METAL PAN STAIRS CALCS & SHOP DRAWINGS |
SIGNED & SELED. AJP |
10/16/07 BLDG SUBMITTAL STRUCTURAL STEEL & DESIGN |
CALCULATIONS FOR ALL CONNECTIONS NO FEE SLS |
10/16/07 BLDG SUBMITTAL SIGNED & SEALED ENGINEERED |
CALCS IN RESPONSE TO ONM&J NO FEE SLS |
10/16/07 BLDG SUBMITTAL INFILL FRAMING @ COLUMN |
LINE B-9 & ELEV SOFFIT FRAMING NO FEE SLS |
10/16/07 BLDG SUBMITTAL GATE LTR RESPONSE TO ONM&J |
INSPECTION REPORT NO FEE SLS |
10/16/07 BLDG SUBMITTAL DRIVE THRU CLADDING LTR NO |
FEE SLS |
10-15-07 CALLED CONTRACTOR LEFT MESSAGE ON SEANS' |
ANSWER MACHINE FILED UNDER "B" LARGE PLAN JW |
10-12-07 CALLED FILED UNDER "B" LARGE PLAN JW |
10/11/07 MECH REV. #14 P/U BY MARCUS (NOTE: |
BLUE CARD PROVIDED WAS FOR MECH REV #15) AJP |
10/11/07 - SENT TO ES - 5TH FLOOR CJH |
10/11/07 MECH REV #21 PASSED WITH PROVISO. CALLED |
FOR P/U SPOKE TO NATHAN. LG BIN UNDER "B" RJR |
10/10/2007 ZONING REVISION # 20 FEES $100.00 |
MMILLER |
10/10/20097 BLDG REV #19 FEES $ MMILLER |
|
10/10/2007 BLDG SUBMITTAL NO FEE (#0511-003 |
PREFABRICATED METAL PAN STAIRS BY AMERICAN STAIR |
CORP INC CALCS & SHOP DRAWINGS SIGNED & SEALED) |
MMILLER |
10/09/07 SUBMITTAL NO FEE- STRUCTUAL STEEL AS |
BUILTS FG |
|
10/03/2007 PLUMBING REVISION #18 FEES $80.00 |
MMILLER |
10/01/07 NICK P/U THE FOLLOWING SUBMITTALS: |
AMERICAN STAIRS SPECS, FRAMING SHOP DRWINGS, |
STRKUCTKURAL STEEL SHOP DRAWINGS, PRECAST DRAWINGS |
AJP |
10-1-07 NO FEE BLDG SUBMITTAL #03450-004 SIGNED & |
SEALED PRECAST STRUCTURAL DESIGN CALCULATIONS WL |
10-1-07 NO FEE BLDG "SUBMITTALS #09111-001 LIGHT |
GAUGE MTL STUD FRAMING, #09111-010 LIGHT GAUGE MTL |
STUD FRAMING, #09111-011 GARAGE PARAPET LIGHT |
GAUGE MTLS STUD FRAMING, & #09111-012 SOFFIT MTL |
STUD FRAMING WL |
10-1-07 NO FEE SUBMITTAL BLDG " SUBMITTAL |
#08600-001 SKYLIGHTS SHOP DRAWINGS & SUBMITTAL |
#08600-003 SKYLIGHTS CALCULATIONS WL |
9/28/07 MOVED TO LARGE PLAN BIN "B" AJP |
9-28-07 CALLED FILED UNDER "B' SMALL PLAN JW |
9-26-07 CALLED NICK & SEAN MORE SUBMITTALS TO BE |
PICKED UP JW FILED UNDER "B" LARGE PLAN |
9-25-07 NICK PICKED UP SUBMITTALS JW |
09/24/07 BLDG SUBMITTAL NO FEE- -TRACTEL WINDOW |
WASHING CALCS- TRACTEL WINDOW WASHING SHOP |
DRAWINGS FG |
9/21/07 SUBMITTAL NO FEE- SHOP DRAWING FG 9/17/07 |
THE FOLLOWING SUBMITTALS PICKED UP BY NICK: REV |
#16(BLDG), REV 21/19 (ELEC.), SUBMITTALS |
05722-003,05722-004,REV, #15,SUBMITTAL # |
09111-005; PLUMBING REV(NOT NUMBERED),SUBMITTAL |
TITLED ROD SHOP DRAWING AND CALCS (NO |
3),SUBMITAL # 09111-004; BLDG SUBMITTAL TITLED |
SIGNED & SEALED WIND LOAD LETR(NO |
3), SUBMITTAL # 07811-001,002,003,009; 5 ROLLS OF |
PLANS INCLUDINAG COMMENTS FROM ARCHITECT OF RECORD |
(3 SETS), 1 LET OF 97REVISED SHEETS MARKED AS |
VOIDED, 3 SETS OF ARCH, STRUCT, MECH, ELEC, SITE, |
LANDSCAPE, FIRE PROT., AND FIRE ALARM DRAWINGS. |
AJP |
09/17/2007 BLDG SUBMITTAL NO FEE (ACTNA FRAMING |
SHOP DRAWINGS 09111-006 09111-007 09111-008 |
09111-009 & 09220-004) MMILLER |
|
09/17/2007 BLDG SUBMITTAL NO FEE (GATE PRECAST) |
SUBMITTAL # 03450-004 SIGNED & SEALED PRECAST |
STRUCTURAL DESIGNS CALCS SUBMITTAL # 03450-015 |
SIGNED PRECAST SHOP DRAWINGS) MMILLER |
|
09/17/2007 BLDG SUBMITTAL NO FEE (HARMON PUNCH |
WINDOWS SUBMITTAL # 08800-005 SIGEND & SEALED |
PUNCH WINDOW CLACS 08800-004 SIGNED & SEALED PUNCH |
WINDOW SHOP DRAWINGS) MMILLER |
|
09/17/2007 BLDG SUBMITTAL NO FEE (HARMON |
STOREFRONT SHOP DRAWINGS & CALCS 08912-007-008) |
MMILLER |
|
|
09/17/2007 BLDG SUBMITTAL NO FEE (AMERICAN STAIR |
PREFABRICATED STEEL PLAN STAIRS SUBMITTAL 0511-003 |
SIGNED & SEALD CALC & SHOPS DRAWINGS SUBMITTAL |
05511004 SIGNED & SEALED CORRECTION DETAIL A/22 |
ATTACHED TO BACK OF APPLICATION) MMILLER |
|
|
9-17-07 CALLED CONTRACTOR SPOKE TO SEANS'S ANSWER |
MACHINE SUBMITTALS FILED UNDER "B" LARGE PLANSJW |
09/13/2007 MECH REVISION THAT WAS # 14 ACCORDING |
TO CUSTOMER HE EXPLAINED THAT FEES WERE ALREADY |
PAID ON 08/31/2007 AND THE MECHANICAL REVISION |
WERE NEVER REVIEWED AT THAT TIME, HOWEVER I |
(MIRELLE MILLER) EXPLIANED TO THE CUSTOMER THAT |
ONCE PLANS EXAMINER RCVD THE PLANS THERE MAY FEES |
INVOLVED MMILLER |
9-10-7 CALLED FOR P/U & TALKED TO NATHAN, |
INDICATED THAT THERE WERE COMMENTS ON 2 SHTS AND 8 |
SHTS APPROVED. INDICATED THAT HE NEEDED THE |
RECIEPT AND/OR THE BLUE CARD TO RETRIEVE HIS |
REVISIONS. "B-LARGE" KSTEVENS |
9/9/07 ELEC REV OK, CALLED AND LEFT MESSAGE ON |
NATHAN'S CELL VM. TOLD TO BRING IN BLUE |
CARD/RECEIPT. PLANS ARE UNDER "B" (LARGE BINS) FOR |
PU. DV PALMER |
09/06/07 CALLED FOR PLAN P/U; ON FLOOR #58 MAW |
09/05/07-MECH REV PULLED FROM REVIEW BY CONTRACTOR |
ADARROUGH |
08/31/2007 ELECTRICAL REVISION #16 FEES $210.00 |
MMILLER |
|
08/31/2007 FIRE REVISION #16 FEES $90.00 MMILLER |
|
08/31/2007 FIRE REVISION #15 FEES $90.00 MMILLER |
|
08/31/2007 MECH REVISION #14 FEES $200.00 MMILLER |
|
08/31/2007 PLUMBING REVISIONS #13 FEES $90.00 |
MMILLER |
|
8-30-07 BLDG SUBMITTAL "STRUCTURAL STEEL SHOP |
DRAWINGS (E-1 - E-25) APPROVED BY STRUCTURAL |
ENGINEER OF RECORD, MCNAMARA/SALVIA, INC" WL |
|
|
08/29/07 BLDG SUBMITTAL NO FEE- SHOP DRAWINGS FOR |
J WITMER-SUBMITTAL # 05722-003 BARRIER CABLE |
RAILINGS SIGNED & SEALED - SUBMITTAL # 05722-004 |
BARRIER CABEL RAILINGS SIGNED & SEALED FG |
8/28/07 SUBMITTAL ROOF SHOP DRAWINGS & CALCS NO |
FEE SPALMER |
8/28/07 SEAN P/U MISC METALS ELEVATOR SUBMITTAL |
SPALMER |
8-26-07 CALLED CONTRACTOR FILED UNDER "B" LARGE |
PLAN SUBMITTAL JW |
8-23-7 IRRIGATION PERMIT REQUIRED - KSTEVENS |
08/22/2007 APPROVED PLANS DATED 08/09/2007 P/U BY |
NICK MMILLER |
08/22/2007 APPROVED SUBMITTAL DATED 08/20/2007 P/U |
BY NICK MMILLER |
08/22/2007 BLDG SUBMITTAL NO FEE (0550-002 MISC |
METALS ELEVATOR SUMP PIT COVERS, ELEVATOR SILL |
ANGLES ELVATOR HOIST BEAMS CLIPANGLES STAIR |
HANDRAINS FOR STAIR & ROOF ACCESS LADDERS & |
LOADING DOCK) MMILLER |
08/22/2007 BLDG SUBMITTAL NO FEE (#07811-011 SPRAY |
FIREROFING MATERIAL-MONOCOTE #07811-002 SPRAY |
FIREROOFING SHOP DRAWINGS 07811-003 EDGE CONDITION |
FOR PROOFING & 2000-009 UL SYSTEM FOR SLAB EDGE AT |
CURTAIN WALL) MMILLER |
08/22/2007 BLDG SUBMITTAL (#09111-005 LIGHT GAUGE |
METAL STUD FRAMING) NO FEE MMILELR |
8-22-07 CALLED CONTRACTOR SPOKE TO SEAN'S ANSWER |
MACHINE SUBMITTALS FILED UNDER "C"CENTEX LARGE |
PLAN JW |
8-20-07 CALLED CONTRACTOR SUBMITTAL FILED UNDER |
"B" SMALL PLAN JW.SPOKE WITH SHAWN |
|
8/13/07 EL. AND FIRE ALARM REV.'S P/U BY NICK |
AJP |
|
08/13/07 FIRE ALRM REVISIONS OK; LARGE BIN "B" |
MAW |
08/12/07 ELEC REVISIONS OK, UNDER "B" (LARGE BINS) |
FOR PICK UP. CALLED SPOKE TO NATHAN DECOTE. DV |
PALMER |
*** CUSTOMER DROPPED (NICK) BLUE CARDS FOR BLDG |
SUBMITTALS THAT WAS DATED 08/09/2007 BLUE CARDS |
WILL BE AT MY DESK MMILLER*** |
08/09/2007 BLDG SUBMITTAL NO FEE (SIGNED & SEALED |
CALS &SHOP DRAWINGS FOR CURTAIN WALL |
(08912-4,08912-005))MMILLER |
08/09/2007 BUILDING SUBMITTAL NO FEE (SIGNED & |
SEALED "WIND LOAD LETTER" DATED JULY |
23,2007)MMILLER |
08/09/2007 BLDG SUBMITTAL NO FEE (SHOP DRAWINGS |
AND CALC FOR EXT LIGHT GUAGE FRAMING |
(FILE#09111-004) |
8/2/07 MECH. REV. P/U BY NATHAN AJP |
7/31/07 MECH REVISION W/ SMOKE CONTROL ANALYSIS |
READY FOR P/U. SPOKE TO NATHAN. LG BIN UNDER "B" |
RJR |
7/19/07 FIRE ALARM REVISION $110 SLS |
7/19/07 MECHANICAL REVISION $210 SLS |
7/19/07 ELECTRICAL REVISION $340 SLS |
7/19/07 PLUMBING REVISION $150 SLS |
06/20/07 REV $1020 FEE - COMMENTS FROM ARCHITECT |
OF RECORD- 1 SET OF 97 REVISED SHEETS- 3 SETS OF |
ARCH-STRUCT-MECH-ELEC LANDSCAP-FIRE PROTE-FIRE |
ALARM DRAINGS FG |
6/18/07 NICK P/U REV FOR OUTSOLATION SYSTEM |
SPALMER |
6/18/07 REV FOR OUTSOLATION SYSTEM DATED 4/27/07 |
SPALMER |
6/18/07 NICK P/U REV TEMP DRY IN SPALMER |
6/15/07 BLDG SUBMITTAL PRODUCT DATA FOR ENHANCED |
DRYWALL BOARD IN MECH RM PRIOR TO DRYIN ROUTED TO |
HPISKURA SEW |
06/08/07 NICK P/U REV FG |
06-08-07 PLBG REV. CALLED P/U "C" PES |
05/31/07 PLUMBIMG & ENGINEERING REV $210 FEE- |
PLEASE FORWARD TO P SCHMITZ AND R BROWN FG 5-21-07 |
NICK KRAUP PICKUP BLDG REV WL |
5/17/07 WHOLE BLDG REVISION (4 ROLLS) CALLED |
CLINTON, LEFT MSG FOR P/U. FLOOR IN FRONT OF 'C' |
RJR |
5/9/07 MECH & PLBG REVISION P/U BY VICKY SLS |
05/09/07 BLDG SUBMITTAL NO FEE- LETTERS FG 5-8-07 |
DENIED CALLED NEYITA P/U "B" PES |
5-08-07 CALLED FILED UNDER "C" JW |
05/02/07 REV $270 FEE- MECHANICAL & PLUMBING |
CHANGES TO RELEASE CONDENSATE RED TAG FOR PLUMBING |
PER R BROWN- ATTN PAUL SCHMITZ & R REGUEIRO FG |
04/27/07 SUBMITTAL NO FEE- ROUTED TO INCOMING FG |
3/22/07 DUANE P/U WIND STUDY REPORT SPALMER |
3-19-07 CALLED FILED UNDER "C" JW |
3/12/07 BLDG/PLUMBING/ELEC/MECH REV SEW |
3/9/07 DUANE P/U DENIED REV DATED 1/25/07 SPALMER |
3-08-07 CALLED FILED UNDER "C" JW |
03/02/07 BLDG SUBMITTAL NO FEE MMILLER |
3/2/07 DUANE P/U 3 SUBMITTALS SPALMER |
3-01-07 CALLED FILED UNDER "C" JW |
2/20/07 TEMPORARY DRY-IN LETTER SUBMITTED FOR |
HAROLD PISKURA NO FEE SLS |
2/12/07 4 BLDG SUBMITTALS FOR JIM NO FEE SLS |
1/25/07 BLDG/ELEC/PLUM/MECH REV SIGNED & SEALED |
DRAWINGS SEW |
1/25/07 2 BLDG SUBMITTALS & 1 BLDG/ELEC/PLUMB/MECH |
REV PU BY DUANE SEW |
1-19-07 CALLED FILED UNDER "C" JW |
1/12/07 BLDG SUBMITTAL KETTER CERTIFYING |
AUGER-CAST PILES SEW |
1/12/07 DUANE P/U REV SPALMER |
1/11/07 REVIONS FROM 11/29/06 ARE IN LARGE BINS |
UNDER "C" FOR PU, SPOKE TO DUANE TOLD TO BRING |
BLUE CARD/RECEIPT FOR THE $490.00 WHICH WAS |
ASSESSED AS THESE WERE REVSIONS. DV PALMER |
12-04-06 PICKED UP BY DUANE F. JW |
12-04-06 CALLED FILED UNDER "C" JW |
**11/29/06 PLANS WHICH CAME IN ON 11/16 AS |
SUBMITTIALS TO LUIS M, ARE REVISIONS, CALLED SPOKE |
TO DUANE, OWES $490.00 . A COPY OF THE REV COVER |
SHEET AND TWO RECEIPTS ARE UNDER "C" FOR PU AND TO |
BE PAID. PLEASE NOTIFY DV PALMER WHEN DONE. DV |
PALMER. |
11/29/06 BLDG SUBMITTAL FOR PROVISO #4 NO FEE |
ROUTED TO JIM WHITMER SLS |
11-15-06 CALED FILED UNDER "C" JW |
11/15/06 NATHAN P/U PLANS SPALMER |
11-8-06 CALLED TO PICK UP PERMIT SET FILED UP |
FRONT UNDERNEATH OVERSIZED BIN ALANGE |
11/3/06 SUBMITTAL FOR JWHITMER NO FEE ROUTED TO |
JWHITMER SEW |
11/02/06 SUBMITTAL FOR JWITMER..NO FEE..ROUTED TO |
JWITMER DESK. TA |
10/30/06**** NOTE **** |
VALUATION FOR FOUNDATION PERMIT AND STRUCTURE-ONLY |
PERMIT IS $1,450,000 AND $3,000,000, |
RESPECTIVELY. |
THIS BUILDING PERMIT VALUATION HAS BEEN REDUCED BY |
THAT AMOUNT, AND THE OUTSTANDING FEES |
RE-CALCULATED ACCORDINGLY. RB |
9-26-06 2ND RESUB $46,300 CONTR PD $51,841.00 WL |
9/25/06 PLANS PICKED UP BY GREGG, ONE ROLL OF A |
FULL SET RETAINED AND ONE ROLL OF "M" SHEET |
RETAINED. DV PALMER. |
9/25/06 PLANS UNSAT, CALLED SPOKE TO NATHAN |
DECOTE, NEEDS TO BRING RECEIPT AS NO BLUE CARD WAS |
ISSUED AT THAT TIME OF SUBMITTIAL. PLANS ARE UNDER |
"C" (LARGE BINS) HOWEVER THEY ARE ON THE FLOOR. DV |
PALMER. |
6/29/06 1ST RESUB NO FEE SEW |
6/19/06 PLANS WERE PICKED UP BY CONTRACTOR LM. |
6/15/06 ******** NOTE ********** |
AS DIRECTED BY NEIL MELICK BUILDING OFFICAL: MS. |
LYNN HARRIS REPRESENTING CITY PLACE OFFICE LLC HAS |
REQUESTED PLANS TO BE REMOVED FROM THE PLAN REVIEW |
PROCESS. |
WHEN PLANS COME BACK IN FOR REVIEW, IT WILL BE 1ST |
RESUB NO FEE. CALLED CENTEX CONSTRUCTION, SPOKE TO |
STACEY, PLANS WILL BE UNDER "C" FOR PU.DV PALMER. |
|
4/24/06 PD PARTIAL PAYMENT IN THE AMOUNT OF |
$154,345.50 PT |