Miscellaneous Information / Notes |
SITEWORK. SITE WALL, RETAINING WALL, PAVERS, SALES |
TRAILER |
|
|
|
|
|
|
|
9/1/06 PERMIT P/U BY LARISA (THE RELATED GROUP) |
AJP |
8/31/6 REV OK, CALLED CONTR, 'F' SMH |
|
8/25/06 TURNED IN NEW NOC TO INCLUDE THE TRAILERS |
SPALMER |
8/24/06 TURNED IN NEW NOC TODAY SPALMER |
8/24/06 BLDG SUBMITTAL SEW |
8/24/06 PU BY MO ABBAS SEW |
8/24/6 CORR REV, CALLED CONTR, NEEDS NEW NOC 'F' |
SMH |
8/24/06 SUB/BLDG FIRE N/C PER SAMANTHA PT |
8/24/06 SUBMITTAL/CORR. P/U BY JERRY (THE RELATED |
GROUP) |
8/24/6 CORR, CALLED CONTR, 'F' SMH |
8/18/06 UP VALUE FROM 111,000 TO 130,0OO TO |
INCLUDE TRAILER RENTAL VALUE SPALMER |
8/10/6 CORR, CALLED CONTR, 'F' SMH |
8/9/6 REV $60 SMH |
7/3/06 RAYMOND P/U PERMIT SPALMER |
7/1/06 CALL TO P/U UNDER 'M' MJACOBS. |
FEES DUE $140.00 |
6/30/06 DENIED CALL TO P/U UNDER **LARGE BINS** |
'M' MJACOBS. |
6/27/06 INFORMED CARLOS SARDINA THAT THE ORIGINAL |
PERMIT APPLICATION FORM WAS NOT RESUBMITTED. HE |
CONFIRMED THAT HE WOULD ADDRESS THIS AND ALSO |
ADVISED THAT THERE WILL A CHANGE OF CONTRACTOR |
LETTER SUBMITTED WITH AN APPLICATION FORM FROM THE |
'NEW' CONTRACTOR. RB |
6/22/06 CHANGE OF CONTRACTOR $100 SLS |
6/8/06 BLDG SUBMITTAL SEW |
5/9/06 PLANS/APP P/U BY TADENA AJP |
5/8/06 CALL FOR P/U (NEED MORE DETAILS) FILE M MM |
5/4/06 GIVEN TO ERIC S, PPLANNER 822-1435 MM |
4/24/06 NOC, RECORDED 4/7/0 6 PROVIDED BY KIRK |
AJP |
4-24-06 REV #1 $70 BLDG WL |
************************************************** |
************************************************** |
2/3/06 GIVEN TO ALAN BARATTA, 822-1435 MM |
3/10/06 CALL FOR P/U FILE M MM |
3/13/06 PERMIT P/U BY ABIGAIL AJP |