Miscellaneous Information / Notes |
TWO CITY PLAZA, 20-STORY, 467 UNIT RESIDENTIAL |
CONDO. PARKG/CONDOS ON LOWER 4 FLRS. 5TH FLR |
LANAI. |
|
|
|
|
|
1/15/09 6TH TCO ISSUED JDS |
1/15/09 LETTER SUBMITTED FOR 6TH TCO $500 ROUTED |
GSMITH SEW |
12/2/08 5TH TCO ISSUED JDS |
11/26/2008 RCVD LETTER FOR A REQUEST FOR AN |
EXTENSION TCO FEES $ 500.00 ROUTED TO KEN CONRAD'S |
DESK MMILLER |
11/05/2008 TCO P/U BY JENNIEFER |
11/3/08 LETTER SUBMITTED FOR 4TH TCO $500 ROUTED |
TO GSMITH SEW |
11/3/08 PERMIT WAS CLOSED IN ERROR AND HAS BEEN |
REOPENED. INSPECTION RESULT FOR 8/13/08 WAS |
ACCIDENTALLY CHANGED FROM "FAIL" TO "PASS" BY |
MFLISS ACCORDING TO AUDIT TRAIL. INSPECTION RESULT |
HAS BEEN CORRECTED TO KEEP PERMIT OPEN. RJR |
10/16/08 CBAA CASE #1361 HAS GRANTED A 60 DAY |
EXTENSION FOR TCO. RJR |
10-8-08 GIVEN TO JERALD TM |
10/2/08 3RD TCO LETTER RECEIVED GAVE TO KEN SLS |
9-16-08 JENNIFER LESLIE PICKUP LANDSCAPE REV |
(DATED 6-24-08) WL |
9/11/08 REVISION UNDER "K" LARGE BINS, CALLED AND |
LEFT MESSAGE ON MIKE'S CELL VM. REMINDED OF BLUE |
CARD. DV PALMER. |
09/08/08 2ND TCO ISSUED JDS |
09/03/2008 REQUEST FOR AN EXTENSION FOR A TCO FEES |
$500.00 SENT TO KEN CONRAD'S DESK MMILLLER |
8-26-08 JENNIFER LESLIE PICKUP MECH/PLUMB REV |
DATED 7-16-08 OR "P TRAP" & SUBMITTED REVISED TCO |
LETTER (REVISED TCO LETTER ROUTED TO JERALD SMITH |
PER JENNIFER THIS IS A NO FEE TCO LTR) WL |
8-15-8 CALLED FOR P/U OF PLUMBING REVISION |
SUBMITTED 7-16-8 & SPOKE TO MIKE N. INDICATING |
THAT THE REVISIONS WERE APPROVED AND THAT THE BLUE |
CARD OR REVISION WAS REQUIRED TO RETRIEVE THE |
REVISIONS. "K" KSTEVENS |
8/14/08 ELEVATION CERTIFICATE SUBMITTED ROUTED TO |
GSMITH SEW |
8/13/08 REVISED TCO ISSUED JDS |
8/12/08 MIKE P/U REVIIONS JREYES |
08/11/08 RESIDENT EMERGENCY PROCEDURES & |
EVACUATION PLAN READY FOR P/U IN LARGE BIN "K" |
MAW/FIRE |
08/08/08 ISSUED TCO: SEE NOTES.GIVEN TO BOB.KC |
8/5/08 MECH REVISION P/U BY KRISTA SLS |
08/04/08 MECH REV #27 CALLED FOR P/U SPOKE TO |
PHIL. LG BIN UNDER "K" RJR |
07/25/08 RECEIVED OVERTIME MECHANICAL INSPECTION |
LETTER FOR 64 HOURS GAVE TO HAROLD SLS |
07/24/2008 BLDG SUBMITTAL NO FEE (TWO CITY PLAZA |
RESIDENT EMERGENCY PROCEDURES EVACUATION PLAN) |
MMILLER |
07/24/2008 LANDSCAPE REVISION # 01 FEES $210.00 |
MMILLER |
7/22/08 RECEIVED OVERTIME WEEK-NIGHT LETTER FOR |
ELECTRICAL INSPECTIONS 3 NIGHTS 2 HOURS $450 SLS |
7-16-08 JENNIFER LESLIE SUBMITTED ADDTL BACKUP |
PAPERWORK FOR TCO REQUEST SUBMITTED EARLIER TODAY |
(ROUTED TO DIANE FULCHER) WL |
7/16/08 JENNIFER P/U MECH REV #26 SPALMER |
7/16/08 REQUEST FOR TEMP CO $500 SPALMER |
7/16/08 MECH REV PRIMED PTRAP $90 SPALMER |
7/15/08 MECH REV #26 CALLED FOR P/U. SPOKE TO |
PHIL. LG BIN UNDER "K" RJR |
7/14/08 MECH REV #27 ADDRESSING COMMENTS FOR AS |
BUILT |
SEW |
7/14/08 MECH SUBMITTAL PU BY JENNIFER SEW |
7/11/08 CALLED MIKE NETHERCOTE (KAST CONSTR) AND |
TOLD HIM THAT THE 8-1/2" X 11" PLANS SUBMITTED |
WITH THE ALTERNATE MATERIALS AND METHODS REQUEST |
MUST BE SUBMITTED AS A REVISION WITH ENGINEER'S |
TITLE BLOCK (INCL. PRINTED NAME, LICENSE NUMBER |
AND ENGINEERING BUSINESS/COA NUMBER OF THE FIRM), |
AND NAME AND ADDRESS OF THE PROJECT. |
ALTERNATIVELY THE SAME REVISIONS CAN BE SHOWN ON |
THE PERMITTED PLANS INSTEAD. 'K'. RB |
7/3/08 ALTERNATE MATERIALS AND METHODS REQUEST |
LETTER: CALLED J.M. ENGINEERING AND KAST |
CONSTRUCTION TO TELL THEM THAT SUBMITTED LETTER |
WAS NOT A SIGNED ORIGINAL. THEY WILL SEND A SIGNED |
LETTER. RECOMMEND GRANTING OF REQUEST ONCE THE |
SIGNED LETTER IS RECEIVED. PACKET IS WITH ROBERT |
BROWN UNTIL THEN. RB |
6/25/08 MECH SUBMITTAL ALTERNATE MEANS & METHODS |
PER CITY WPB REQUIREMENTS SEW |
06/24/2008 MECHANICAL REVISION #38 FEES $100.00 |
MMILLE |
6-3-08 CALLED FOR PLMG SUBMITTAL P/U AND LEFT A |
MESSAGE WITH MIKE INDICATING THE SUBMITTAL WAS |
APPROVED AND THE BLUE CARD WAS REQUIRED TO |
RETRIEVE THE SUBMITTAL. "K" KSTEVENS |
6-3-08 MADDIE PULIDO PICKUP SUBMITTAL 08810-06 |
"DOOR AT STEAM ROOM" WL |
5-30-08 CALL TO P/U SUBMITTAL #08810.06 UNDER 'K' |
MJ |
5/22/08 MECH REV # 25, UPPER ROOF PLAN, AND |
SUBMITTAL # 15051.01.01, STARTERS FOR HVAC PUMPS, |
PICKED UP BY MADDIE AJP |
5/21/08 MECH REV.25 AND SUBMITTAL # 15051.01.01 |
TOGETHER. CALLED FOR P/U. SPOKE TO PHIL. LG BIN |
UNDER "K". RJR |
5/16/08 SUBMITTAL #08810.06 DOOR AT STEAM ROOM NO |
FEE SPALMER |
5/16/08 SUBMITTAL #15450.06 AIR GAP FITTING NO FEE |
SPALMER |
5-16-08 MADDIE PULIDO PICKUP BLDG SUBMITTAL |
05500.07 WL |
5-16-08 CALL TO P/U SUBMITAL #05500.07 UNDER 'K' |
MJ |
5/9/08 ELEC REV #19 $70 SEW |
5/6/08 BLDG SUBMITTAL #15051.01.01 STARTERS FOR |
HVAC PUMPS NO FEE SPALMER |
5/1/08 BLDG SUBMITTAL #055 00.07 GARAGE PIPE |
PROTECTION SEW |
5/1/08 MECH REV 25 UPPER ROOF PLAN $130 SEW |
4-30-08 MADDIE PULIDO PICKUP BLDG REV DATED 4-4-08 |
"CIVIL REVISION #24" WL |
4-30-08 CALL TO P/U UNDER 'K' MJACOBS. |
4-25-08 MADDIE PULIDO PICKUP REV #23 MECH WL |
4/24/08 MECH SUBMITTAL #23, ORIGINALLY REVIEWED BY |
H MOSER ON 3/20/08. CALLED FOR P/U. SPOKE TO |
MADDIE. LG BIN UNDER "K" RJR |
4/22/08 PU BY MADDIE SEW |
4-21-08 CALLED FOR P/U PLMG REV AND TALKED TO PHIL |
INDICATING THE REV WAS APPROVED AND THAT THE BLUE |
CARD OR RECIEPT WAS REQUIRED. "K" KSTEVENS |
4/16/08 - BLDG. REV. ROUTED TO "B - MJ" CJH |
4/10/08 - BLDG. REV. SENT TO AA - 5TH FLOOR. CJH |
4/4/08 PLUMB REV $60 SPALMER |
4/4/08 BLDG REV $60 SPALMER |
3-25-08 MADDIE PULIDO PICKUP 2 SUBMITTALS DATED |
3-13-09 (MECH 15930.01 & 15762.02.05) WL |
3/21/08 TWO SUBMITTALS UNDER "K" FOR PU(SMALL), |
SPOKE TO ANDY. NO FEES, DV PALMER |
3/19/08 MADDIE P/U ELEC REV #21 SPALMER |
3/17/08 PUT OUT FRONT FOR P/U UNDER "K" CALLED FOR |
P/U JL |
3-14-08 MADDIE PULIDO PICKUP SUBMITTAL #16000.18 |
WL |
3/14/08 CALLED FOR P/U SUBMITTAL "K" LARGE BIN |
MRW |
3/13/08 MECH SUBMITTAL #15930.01 STATIC PRESSURE |
SENSORS NO FEE SPALMER |
3/13/08 MECH SUBMITTAL #15762.02.05 TRANE |
HPU-UR-1,2,&3 NO FEE SPALMER |
3/12/08 MECH SUBMITTAL # 23 SUBMITTED $160 SLS |
3/12/08 MECH REVISION # 22 P/U BY MADDIE SLS |
3/10/08 REV #22 OUT FRONT FOR P/U IN BIG BINS |
UNDER "K" CALLED CONT. JL |
3/10/08 PUT OUT FRONT IN BIG BINS FOR P/U UNDER |
"K" CALLED CONT. JL |
03/05/2008 FIRE SUBMITTAL (SMOKE CONTROL) NO FEE |
MMILLER |
3-5-08 MADDIE PULIDO PICKUP SUBMITTAL #15815.13.01 |
WL |
3-4-08 CALLED FOR P/U LEFT MESSAGE SUBMITTALS IN |
BOX K HM. |
3-4-08 MADDIE PULIDO PICKUP MECH REVSIONS #20 & |
#22 WL |
3/4/08 CALLED FOR P/U MECH REV #20 AND MECH REV |
#22. SPOKE TO RODOLFO. 2 ROLLS LARGE BIN UNDER "K" |
RJR |
2/19/08 MECH REV #22 SEW |
2/19/08 ELEC REV #21 $160 SEW |
2/19/08 2 BLDG SUBMITTALS 15430.11 EMAX FLOW & |
15815.13.01 BROAN WALL CAPS SEW |
2/19/08 SUBMITTAL PU BY MADELINE 15815.02 |
158181.02 15122.02 15181.03 15075.0115400.02 |
16000.10 02400.06 15100.01.01 15122.03 05100.02 |
05100.02 SHORING & POUR #13 SEW |
2-15-08 DENIED SUBMITTAL #05100.02 CALL TO P/ |
UNDER 'K' **LARGE BIN W/OLD KOLTER PICKUP** |
MJACOBS. |
2/13/08 E-MAILED HECTOR FOR ENERFOAM SUBMITTAL |
P/U. 'K'.**LARGE BIN WITH OLD KOLTER PICKUPS** RB |
2/8/08 MADDIE PICKED UP THE FOLOWING REV'S: |
14410.04(EXPANSION VALVE), 15410.04(RECIRC. PUMP), |
EL. REV. # 19,;BLDG REV. # 15050.01(PRO-SET |
INSERTS FOR THREADED RD);1540.01 (VARIABLE AIR |
VOL. );1506.02 PIPE HANGERS;15141.01.01HEAT |
PUMP;15141.01.02.05 |
INSULATION;1581514.4;15733.01.01;15181.06M;15181.0 |
5M;055500.01M;15745.01.03;15815.19;15815;15815.16; |
15815.16;15670.01.02(HEAT |
EXCHANGER);15181.01.02(EXPTANKS/SEPARATORS);15815. |
01(TANKS,DUCTWORK);15815.03(DIFFUSERS,REGISTERS, |
ETC.);1580.01(INSULATORS)AJP A15 08 CALLED FOR |
ELEC REV 19 P/U LARGE BIN "K" MAW |
02-06-08 CALLED FOR P/U AND TALKED TO MADELINE AND |
INDICATED THE SUBMITTALS 15450.03 & 15450.04 WERE |
APPROVED AND READY TO BE RETRIEVED. INDICATED THAT |
THE BLUE CARD WAS REQUIRED. "K" KSTEVENS |
2/5/08 LEFT MESSAGE FOR P/U SUBMITTLES IN BOX K |
LARGE BIN HM. |
2/5/08 BLDG SUBMITTAL TRUSS DETAIL CONN ENG NO FEE |
SLS |
2-1-08 CALL TO P/U UMDER 'K' MJACOBS. |
1/30/08 CALLED FOR P/U LEFT MESSAGE SUBMITTLES IN |
BOX K HM. |
1-30-08 2 SUBMITTALS (DATED 4-4-06 & 2-1-07) IN |
LARGE BIN "K" FOR PICKUP CALLED BY D PALMER, K |
STEVENS, H MOSER WL |
01/29/2008 BLDG SUBMITTAL NO FEE (ENERFOAM TO THE |
ATTENTION OF ROBERT BROWNN) MMILLER |
1/28/08 PLBG SUBMITTAL P/U BY MADDIE SLS |
1-25-08 CALLED FOR P/U PLMG SUBMITTALS TALKED TO |
MIKE AND INDICATED THAT THE SUBMITTALS WERE |
APPROVED AND THAT HE NEEDS THE BLUE CARD TO |
RETRIEVE THE SUBMITTALS. "K" KSTEVENS |
1/24/08 CALLED FOR P/U LEFT MESSAGE SUMMITTAL IN |
BOX K HM. |
1/24/08 REVISIONS P/U BY MADDIE SLS |
1/23/08 ELEC, MECH, FIRE REVS FROM 12/21 UNDER "K" |
(LARGE BINS) FOR PU. CALLED SPOKE TO PHIL, |
REMINDED OF BLUE CARD TO PICK UP PLANS. DV |
PALMER. |
1/22/08 MECH SUBMITTALS 15181.08 AND 16000.16 P/U |
BY MADELINE. RJR |
1/22/08 BLDG SUBMITTAL #15450.05 AQUASTAT & |
#15450.04 EXPANSION VALVE NO FEE SLS |
1/18/08 MECH REVISION $110 SLS |
1/18/08 ELEC REV $110 SPALMER |
1/14/08 BLDG SUBMITTAL #05100.01.01 TRUSS SPALMER |
1/14/08 ELEC SUBMITTAL #16000.16 SILENCER FOR |
EMERGENCY GENERATOR SPALMER |
1/14/08 BLDG SUBMITTAL #15450.03 WTR HEATER RE |
CIRCULATING PUMP SPALMER |
1/7/08 DENIED BLDG SUBMITTAL #05100.02.01, AND |
APPROVED EL/PARTIALLY DENIED PLBG--2 SHTS/APPROVED |
FIRE REV. P/U BY MADELINE AJP |
1-4-08 DENIED CALL TO P/U UNDER 'K' LARGE BIN |
MJACOBS |
12/28/07 CALLED FOR RVSD PLANS P/U UNDER "K" MAW |
12/21/07 ELEC & MECH REVISION $270 SLS |
12/19/2007 BLDG SUBMITTAL NO FEE (#05100.02.01) |
MMILLER 12-17-07 MADDIE PULIDO PICKUP SUBMITTALS |
#03100.31 & 10536.01 WL |
12/15/07 CALL TO P/U UNDER 'K' MJACOBS. |
12/10/07 BLDG SUBMITTAL # 03100.31 HIGH ROOF |
SHORING/RE-SHORING SEW |
12/3/07 APPROVED BLDG/EL SUBMITTALA #13032.01, |
SAUNA/STEAM ROOM, P/U BY MADDIE AJP |
12/3/07 MOVED TO LARGE PLLAN BIN "K" AJP |
12/3/07 ELEC/BLDG SUBMITTAL FROM 11/15 UNDER "K" |
FOR PU. CALLED AND SPOKE TO ANDY. DV PALMER. |
12/3/07 BLDG SUBMITTAL AWNINGS NO FEE SLS |
12/3/07 BLDG SUBMITTAL P/U BY MADDIE SLS |
12/1/07 CALL TO P/U UNDER 'K' MJACOBS. |
11/28/07 ELEC & PLBG REVISION POOL DECK BAR |
LIGHTING & PLUMBING $140 SLS |
11/27/07 APPROVED MECH. SUBMITTALS #13 & #17 P/U |
BY MADDY AJP |
11/27/07 DENIED SUBMITTAL # 03460.10-MAIN ENTRY |
STONE P/U BY MADDY AJP |
11/24/07 MECH REVS 13 AND 17 CALLED FOR P/U. LEFT |
MSG FOR MIKE. LG BIN UNDER "K" RJR |
11-16-07 DENIED CALL TO P/U UNDER "K' MJACOBS |
11/15/07 (2) BLDG SUBMITTALS # 03460.09 2NDFL & # |
13032.01 SUANA & STEAM ROOM SEW |
11/15/07 MECH REV # 17 SEW |
11/9/07 BLDG SUBMITTAL #03460.10 SEW |
11/7/07 SUBMITTAL #09100.07, ACOUSTICAL CEILING |
PLAN & DETAILS AJP |
11-5-07 CALL TO P/U UNDER 'K' MJACOBS. |
11/02/07 MECH REV $110 SPALMER |
10-30-07 NO FEE BLDG SUBMITTAL #15181.08 ROOF TOP |
PIPING NIPPLES" WL |
10/29/07 SUBMITTAL #09100.07 ACOUSTICAL CEILING |
PLAN & DETAILS SPALMER |
10/26/07 MADDIE P/U MECH REV.'S # 14, 15, & 16, |
EACH OF WHICH REQUIRES CORRECTIONS., AND THE |
FOLLOWING SUBMITTALS, ALL APPROVED: 07551.01.01 |
(ROOFING);07551.02 (HEAT WLEDED TORCH DOWN |
MODIFIED BITUMEN ROOFING SYSTEM); 05520.07.01 |
SPIRAL STAIRS LAYOUT;05520.08.02 (STRAIGHTSTAIRS |
LAYOUT); AND 05520.09.02 (STAIR ENGINEERING) |
10/25/07 MECH REVISIONS 14,15 AND 16 ARE READY FOR |
PICK UP. THEY ARE IN ONE PACKAGE. CALLED AND SPOKE |
TO MIKE. LG BIN UNDER "K" RJR |
10/25/07 THREE GROUPS OF SUBMITTALS MOVED TO LARGE |
PLAN BIN "K" AJP |
10/25/07 CALL TO P/U UNDER 'K' MJACOBS. |
10/24/07 MADDIE PICKED UP THE FOLLOWING APPROVED |
SUBMITTALS:05520.07.02;05520.08.02;05520.09.02;032 |
00.53(HIGH ROOF &MACHINE ROOF REBAR);03100.30 |
(POOL DECK SHORING);15430.10(ACCESS |
DOORS);05100.04(GAZEBO AND AIR SHAFT |
SIGNED/SEALED);05100.03(4TH FL. MANSARD TRUSSES |
FINAL SIGNED/SEALED);05100.05 (EXHAUST SHAFT |
SIGNED/SEALED) AJP |
10/24/07 MADDIE PICKED UP THE FOLLWOING DENIED |
SUBMITTAL: 05100.02, DETAIL CONNECTIONS-FINAL |
SIGN/SEALED AJP |
10/19/07 DENIED CALL TO P/U UNDER 'K' MJACOBS. |
10/19/07 CALL TO P/U UNDER 'K' MJACOBS. |
10/18/07 BLDG SUBMITTAL |
05520.07.02/05520.08.02/05520.09.02 |
10-18-07 REV #24 MECH PER COMMENTS REV #16 MECH |
FLOORS 16TH-21ST" WL |
10/15/07 SUBMITTAL 03460.02, DECK DRAINS, P/U BY |
MADELINE AJP |
10/15/07 BLDG SUBMITTAL TORCH DOWN ROOF SYSTEM NO |
FEE SLS |
10/15/07 EXTERIOR POOL SOWER FIXTURE SUBMITTAL # |
1543.07 P/U BY MADELINE AJP |
10-15-7 CALLED FOR P/U OF POOL SHOWER SUBMITTAL. |
TALKED TO MIKE AND I INDICATED THE SUBMITTAL FOR |
THE POOL SHOWER FIXTURE WAS APPROVED AND THAT HE |
COULD RETRIEVE THE SUBMITTAL BY BRINGING THE BLUE |
CARD. "K" KSTEVENS |
10/15/07 BLDG SUBMITTAL ACCESS DOORS NO FEE SLS |
10/13/07 CALL TO P/U UNDER 'K' MJACOBS. |
10-13-07 CALLED FOR P/U DECK DRAIN SUBMITTAL AND |
LEFT A MESSAGE WITH MIKE'S ANSWERING MACHINE. |
INDICATED SUBMITTAL WAS APPROVED AND READY FOR |
PICK UP AND THAT HE NEEDED HIS BLUE CARD TO |
RETRIEVE THE SUBMITTAL. "K" KSTEVENS |
10/11/07 APPROVED BLDG REV # 07212.04.01 |
POLYISOCYONNURATE BOARD INSULATEION PU BY MADELINE |
AJP |
10/9/07 MECH REV $300 SPALMER |
10/9/07 SUBMITTAL ROOFING NO FEE SPALMER |
10/9/07 SUBMITTAL POOL DECK SHORING NO FEE |
SPALMER |
10/02 07 REV'S #10 & 11, 6 ROLLS /COMMENTS P/U BY |
MAADELINE AJP |
10/2/07 (5)BLDG SUBMITTALS #05100.04 #05100.03 |
#05100.05 #05100.02 #03200.53 SEW |
9/24/07 SUBMITTAL #07212.04.01 POLYISOCOYANURATE |
BOARD INSULATION SPALMER |
9/24/07 SUBMITTAL # 08330.01, APPROVED, OVERHEAD |
ROLLING FIRE DOOR P/U BY MADELINE AJP |
9/21/07 CALL TO P/U #08330.01 UNDER 'K' MJACOBS. |
9/19/07 LETTER SUBMITTED FOR MECH OVERTIME INSP |
FOR SATURDAY 9/22/07 (STARTING @ 8AM) $300 SEW |
9/18/07 MECH REV #14 $260 SEW |
9/18/07 MADELINE PICKED UP THE FOLLOWING |
BLDG SUBMITTALS AND/OR REVISIONS: |
03460.04,03460.06,13152.07.02,10526.01(DENIED),042 |
20.09,03200.52,03200.42, AND 11011.03. EXCEPT AS |
INDICATED ALL WERE APPROVED. AJP |
9/18/07 SUBMITTAL #15430.07 EXTERIOR POOL SHOWER |
FIXTURE SPALMER |
9/17/07 OVERTIME INSPECTION FOR MECH INSPECTION |
DONE ON 9/15/07 4HRS SPALMER |
9/12/07 MADELINE PICKED UP ONE DENIED BLDG |
REV,#03200.47),AND THE FOLLOWING EIGHT APPROVED |
REVISIONS: |
03200.51,05520.11,05520.04.02,10552.01.01,07830.04 |
,03200.49,03200.50,AND MECH. REV. #13R. AJP |
9/11/07 MECH REV M2.22 CALLED FOR P/U LEFT |
MESSAGE. LG BIN UNDER "K" RJR |
9/11/07 MOVED TO LARGE PLAN BIN "K" AJP |
9/6/07 BLDG SUMITTAL NO FEE AWNINGS/OVERHEAD |
ROLLING FIRE DOOR/VERTICAL REMEDIAL @ BLOCK |
WALLS/POOL & FOUNTAIN WATER PROOFING/WINDOW |
CLEANING MAINT SYSTEM/HIGH ROOF BEAMS ARCH BEAMS |
SLABS SPALMER |
9/5/07 BLDG SUBMITTAL WINDOW SILL AT LANAI LEVEL & |
WEST ELEVATION SICKER BAND PRECAST NO FEE SLS |
8/28/07 THE FOLLOWING ITEMS P/U BY MADDY: REV. |
#10(ROLL OF PLANS, PLUMBING), SUBMITTALS 1600.15, |
03200.48,1600.14 AJP |
8-28-07 3 NO FEE BLDG SUBMITTALS #03200.51 POUR E: |
AMENITY DECK/WALLS REBAR, #03200.50 POUR D:AMENITY |
DECK/WALLS REBAR, & #03200.42 MAIN ROOF POUR B" WL |
8/26/07 ELEC SUBMITTAL OK FOR PU, CALLED AND LEFT |
MESSAGE ON MIKE'S VM. *DOES NOT NEED BLUE CARD. |
DVP. |
8-25-7 FAXED A MSG TO JOHN BOEHM TO LET HIM KNOW |
THE PLUMBING REVISIONS ARE READY FOR PICK UP. |
INDICATED THAT ALL BUT 4 SHEETS WERE APPROVED. |
INFORMED HIM THAT HE NEEDED A RECIEPT AND/OR THE |
BLUE CARD TO RETRIEVE THE REVISIONS. "K-LARGE" |
KSTEVENS |
8/25/07 BLDG SUBMITTAL MAIL-BOX SHOPS/REBAR POUR C |
POWDER COAT PRODUCT DATA/TRELLIS DETAIL@ POOL DECK |
ANDCONDUIT & METALLIC PIPE PENETRATIONS NO FEE |
SLS |
8/24/07 MECH REVISION 13 R CALCULATION $60 SLS |
8/24/07 MANY SUBMITTALS/REVISIONS P/U BY KATHLEEN, |
TO WIT: |
REV 13 R1 WITH COMMENTS; |
REV 12 R;SHORING LETTERS # 125 & 126;; REV # |
03100.29 METAL DECK PLANTER LOCATIONS;SUBMITTAL |
03200.43;03365.17.03;03100.28;03200.46;03200.45;03 |
200.44; AND MECH REV #12 AJ |
8/24/07 TWO SUBMITTALS MOVED T LARGE PLAN BIN "K" |
AJP |
8/24/07 CALL TO P/U UNDER 'K' MJACOBS. |
8/17/07 MECH REV (12R AND 13R) CALLED FOR P/U |
SPOKE TO MADELINE AND LEFT MSG FOR PHIL LONGO. TWO |
PKGS BANDED TOGETHER. LG BIN UNDER "K" RJR 8/15/07 |
OVERTIME INSPECTION 4HRS FOR SATURDAY AUG 18, 2007 |
$300 SPALMER |
8/15/07 MECH REV LOBBY DUCT WORK $60 SPALMER |
8/15/07 SUBMITTAL POOL DECK POUT REBAR NO FEE |
SPALMER |
8/13/07 BLDG SUBMITTAL LOW PROFILE AA FIXTURE & |
DECK DRAINS NO FEE SLS |
8/9/07 BLDG SUBMITTAL SHORING LTR POUR #126 NO FEE |
SLS |
8/9/07 BLDG SUBMITTAL 22ND FLR ROOF CALCS NO FEE |
SLS |
8/9/07 BLDG SUBMITTAL ROOF WALLS COLUMNS & POOL |
DECK SLABS NO FEE SLS |
8/9/07 BLDG SUBMITTAL MAIN ROOF POUR E NO FEE SLS |
8/9/07 BLDG SUBMITTAL MAIN ROOF SHORING NO FEE |
SLS |
8/3/07 MECH REV #13R1 SEW |
8/3/07 PU BY KRISTA SEW |
8/3/07 (3) ELEC SUBMITTALS, UNDER "K" FOR PU. |
DVP. |
8/2/07 (1) BLDG SUBMITTAL SHORING/GC LETTER POUR |
#125 SEW |
8/2/07 (3) BLDG SUBMITTAL #03100.29 #03200.43 |
#03200.44 SEW |
8/2/07 MOVED TO LARGE PLAN BIN "K" AJP |
7/26/07 BLDG SUBMITTAL ROOF LEVEL # 22 RESHORING & |
SHORING INSP LETTERS SEW |
7/26/07 PU BY RAY SEW |
7/25/07 MOVED TO LARGE PLAN BIN "K" AJP |
7/25/07 CALLED CUSTOMER NEEDS TO RESUBMIT UNDER FA |
PERMIT "K" MRW |
7/24/07 MECH REVISION $110 SLS |
7/23/07 MECH REV. ROLL PL/U BY KATHLEEN(OUR BLUE |
CARD SHOWED IST AS REV. #21, THEY THINK IT IS REV. |
22) AJP ALSO P/U SHORING LETTERS--CARD HAD REV # |
820 AND REV. 10,BELIEVE FOR POUR # 122. AJP |
7/23/07 MECH REVS CALLED FOR P/U, SPOKE TO RAY. LG |
BIN UNDER "K" RJR |
7/20/07 CALL TO P/U UNDER 'K' MJACOBS. |
7/19/07 MECH AFTER HRS INSPECTION LETTER RCD $300 |
GIVEN TO HAROLD MOSER SLS |
7/19/07 2 BLDG SUBMITTALS ROOF DECK POUR A & MAIN |
ROOF RESHORING NO FEE SLS |
7-13-07 REV #21 MECH $330 "ROLLED PLANS..REVISED |
PER CLOUDS & TRIANGLES"..1 ROLL CONTAINING 3 SETS |
OF PLANS WL |
07/12/2007 BLDG SUBMITTAL NO FEE (POUR # 122) |
MMILLER |
7/12/07 BARBARA P/U SHORING LTR POUR 121 |
7/12/07 BARBARA P/U SHORING LTR MAIN ROOF DATED |
6/6/07 |
7/12/07 BARBARA P/U SUBMITTAL ARCH FOR SHEET |
DENIED ON REV 9 DATED 6/5/07 SPALMER |
07/12/07 CALL TO P/U UNDER 'K' MJACOBS. |
07/11/07 OVERTIME INSPECTION $1200 FEE- 8HRS FOR |
MECHANICAL 8HRS FOR ELECTRICAL ROUTED TO |
INSPECTORS DESK FG |
07/11/07 REV $180 FEE- REV 11 STRUCTURAL FG |
07/07/07 SUBMITTAL NO FEE #16000.14 FIRE ALARM |
EQUIPMENT FG |
07/07/07 SUBMITTAL NO FEE- #03300.29 300 PSI FG |
07/07/07 SUBMITTAL NO FEE- #03100.25 MAIN ROOF |
SHORING & RESHORING FG |
07/07/07 BLDG/ELEC/PLUMB/ REV $2300 FEE FG |
7/3/07 BARBARA P/U MECH REV DATED 6/27/07 SPALMER |
7/3/07 BARBARA P/U BLDG SUBMITTAL DATED 6/15, |
6/19,6/21,6/28,6/26 |
7/2/07 MECH REV M2.21-M2.26 CALLED FOR P/U SPOKE |
TO JOHN. LG BIN UNDER "K" RJR |
7/2/07 BLDG SUBMITTAL SHORING & GC LETTER POUR |
#121 SEW |
7/1/07 LEFT A MESSAGE FOR JOHN TO P/U REVISION. |
LARGE BINS. 'K'. RB |
6/30/07 CALL TO P/U **LARGE BINS** 'K' MJACOBS. |
06/28/07 BLDG SUBMITTAL NO FEE- SHORING & GC |
LETTER POUR 120 FG |
6/28/07 MECH REVISION $110 SLS |
06/26/07 SUBMITTAL NO FEE- #11011.02 PROBEL SHOP |
DRAWING FG |
06/26/07SUBMITTAL NO FEE- # 03100.24 TOWER LEVEL |
17-21 SHORING SHOPS FG |
06/26/07 SUBMITTAL NO FEE- SHORING & GC LETTER |
POUR 119 FG |
6/25/07 PHIL P/U ENG CALC DATED 5/30/07 6/5/07 |
LTRS DATED 6/19/07 EXTERIOR SYNERGY FORM PKG DATED |
6/1/07 SPALMER |
6/25/07 PHIL P/U DENIED MECH REV DATED 6/19/07 |
SPALMER |
6/25/07 MECH REV 2.21 THRU 2.26 DENIED. CALLED FOR |
P/U. SPOKE TO JOHN. LG BIN UNDER "K" RJR |
6/24/07 CALLED JOHN FOR SUBMITTAL P/U. LARGE BINS. |
'K'. RB |
06/21/07 BLDG SUBMITTAL NO FEE- # 03365.16- 21ST |
FLOOR CALCS FG |
06/21/07 BLDG SUBMITTAL NO FEE- # 03300.29 3000 |
PSI W/HRWR & FIBER FG |
06/21/07 BLDG SUBMITTAL NO FEE- SHORING & GC |
LETTER POUR # 118 FG |
6-19-07 BARBARA COREY PICKUP 2 SUBMITTALS (SHORING |
& GC LTR POUR 115 & SUBMITTAL #05100.02 STEEL |
TRUSSES) & 1 MECH REV WL |
6-19-074 REV # 13 MECH $110 UNIT DUCTWORK FLOORS |
6-14 WL |
06/19/07 BLDG SUBMITTAL NO FEE- ATTN : R BROWN |
FG |
06/19/07 BLDG SUBMITTA NO FEE- SHORING & GC LETTER |
POUR # 117 FG |
6/19/07 BLDG SUBMITTAL NO FEE- #032200.40 TWR |
COLUMN LEVEL 20 MAIN ROOF FG |
06/19/07 BLDG SUBMITTAL NO FEE- # 03200.41 |
SHEARWALL TOWER 21 TO ROOF FG |
06/19/07 BLDG SUBMITTAL NO FEE- # 03460.01 PRE |
CAST SHOP DRAWINGS FG |
6/18/07 2 BLDG SUBMITTALS READY FOR P/U "LARGE |
BINS** "K" SPALMER |
6/18/07 MECH REVISION M2.21 THRU M2.26 CALLED FOR |
P/U. LG BIN UNDER "K" RJR |
6-15-07 BARBARA COREY PICKUP 18 SUBMITTALS, {6-5-7 |
SHORING & GC LTR, (6 SUBMITTALS POURS #107-112), |
SUBMITTALS #0930014, #08820.01, #09300.11, |
#09250.05, #03200.38, #03200.39, #15815.12.01, |
#15904, #15904.01, #15815.14, & #15141.03} WL |
6-15-07 NO FEE BLDG SUBMITTAL "SHORING & GC LETTER |
POUR #116 WL |
6/14/07 BLDG SUBMITTAL SHORING/GC LETTER POUR #115 |
SEW |
6/13/07 CALLED LEFT A MESSAGE FOR P/U PLANS IN BOX |
K HM. |
6/12/07 MECH SUBMITTAL # 15641 COOLING POWER WATER |
& DRAIN CONNECTION SEW |
6/12/07 BLDG SUB SHORING/GC LETTER POUR #114 SEW |
6/9/07 CALL TO P/U 12 SUBMITTALS POUR LETTERS |
107-111 **LARGE BINS** 'K' MJACOBS. |
6-8-07 REV #12 $110 MECH "TCP 6TH - 14" PLANS ARE |
ROLLED WL |
6/7/07 BLDG SUBMITTAL EXHAUST THIMBLES @ EMERG |
GENERATOR NO FEE SLS |
6/7/07 BLDG SUBMITTAL SHORING & GC LETTER POUR # |
113 NO FEE SLS |
6/6/07 OVERTIME INSPECTION LETTER RECD FOR |
SATURDAY 6/8/07 FEES ALREADY PAID AND LETTER GIVEN |
TO HAROLD M SLS |
6/6/07 BLDG SUBMITTAL GAP CALCS & RESPOND TO GCI |
INSP ROUTED TO PLAN REVIEW JDS |
6/5/07 (3) BLDG SUBMITTALS SHORING/GC LETTER POUR |
112 SUBMITTAL #16000.13 & SUBMITTAL #16000.12 LT |
FIXT COMMON AREA SEW |
6/5/07 BLDG SUBMITTAL GAP CALCS & RESPOND TO GCI |
INSP ROUTED TO JSMITH SEW |
6/5/07 BLDG SUBMITTAL COMMENTS FROM ARCHITECTS FOR |
SHEET DENIED ON REV #9 SEW |
6/5/07 ANDY P/U 3 MECH REV DATED 5/31/07 SPALMER |
6/4/07 CALLED ANDY FOR P/U PLANS IN BOX K HM. |
6/1/07 EXTERIOR SYNERGY FOAM PKG SUBMITTAL PER |
ROBERT BROWN NO FEE SLS |
05/31/2007 MECHANICAL REVISION # 11 FEES $80.00 |
(M401-4.03) MMILLER |
05/31/2007 MECHANICAL REVISION #10 FEES $110.00 |
(4TH FLOOR DUCT DRAWINGS "UNITS") MMILLER |
05/31/2007 MECHANICAL REVISION #9 FEES ( RVISED |
DUCT RISER) $110.00 MMILLER |
5/31/07 BLDG SUBMITTAL ENGINEER CALCS ROUTED TO |
PLAN REVIEW JDS |
5/30/07 BLDG SUBMITTAL SHORING/GC LETTER POUR 111 |
SEW |
5/30/07 BLDG SUBMITTAL ENGINEER CALCS ROUTED TO |
JSMITH SEW |
5/29/07 (4) BLDG SUBMITTALS SHORING/GC LETTER POUR |
#110 SUBMITTAL 09250.05/09300.14/09300.11 SEW |
5/29/07 (3) MECH SUBMITTALS REVISED DUCT RISERS |
M4.01/M4.03 & LANAI LEVEL & 2ND-4TH LEVEL ROUTED |
TO HMOSER SEW |
5/24/07 BLDG SUBMITTAL SHORING/GC LETTER POUR 109 |
SEW |
5/23/07 BLDG SUBMITTAL #05100.02 STEEL TRUSSES |
SEW |
5/23/07 LETTER SUBMITTED FOR SATURDAY 5/26/07 INSP |
$300 ROUTED TO DBOWMAN SEW |
5-22-07 2 BLDG SUBMITTALS #08820.01 "UNIT MIRROR |
PROD SPECS & SHORING & GC LTR POUR # 108 WL |
5-22-07 BARBARA COREY PICKUP SHORING LTRS 99-106 |
WL |
5/21/07 CALL TO P/U SHORING LETTERS 99-106 UNDER |
'K' MJACOBS. |
5/18/07 BLDG SUBMITTAL SHORING/GC LETTER POUR 107 |
SEW |
5/16/07 BLDG SUBMITTAL SHORING/GC LETTER POUR 106 |
SEW |
5/16/07 BARBARA P/U REV #9 SPALMER |
5/15/07 BARBARA P/U 2 SUBMITTALS FOR FIRE PROT |
PLAN UNIT 513 & FIRE HOSE CABINETS SPALMER |
5/15/07 CALLED FOR P/U "K" MRW |
5/14/07 BLDG SUBMITTAL SHORING/GC LETTER POUR 105 |
SEW |
5/9/07 MECH SUBMITTAL P/U BY BARBARA SLS |
5/9/07 CALLED FOR P/U PLANS IN BOX K HM. |
5/8/07 BLDG SUBMITTAL SHORING/GC LETTER POUR #103 |
SEW |
05/07/07 BLDG SUBMITTAL NO FEE- SUBMITTAL # |
03200.38- TOWER 17TH - 20TH POUR A-B-C-D & E |
FG |
05/07/07 BLDG SUBMITTAL NO FEE- SUBMITTAL # |
03200.39 21ST FL STEEL SHOP DRAWINGS FG |
05/07/07 BLDG SUBMITTAL NO FEE- SHORING & GC |
LETTER POUR 102 |
5/3/07 MECH SUBMITTAL 5TH-15THFL FLEX DUCT & |
2ND-4THFL FLEX DUCT SEW |
5/3/07 BLDG SUBMITTAL SHORING/GC LETTER POUR 101 |
SEW |
5/1/07 CALLED FOR REV #9 P/U. LARGE ROLLS. 'K'. |
RB |
04/30/07 BLDG SUBMITTAL NO FEE- SHORING AND GC |
LETTER FG |
04/30/07 FIRE SUBMITTALS NO FEE- FIRE HOSE |
CABINETS FG |
4-27-07 BLDG SUBMITTAL SHORING & GC LTR POUR #99 |
WL |
4-27-07 SHERI FRITZ PICKUP 5 BLDG SUBMITTALS & 1 |
ELEC REV (SUBMITTAL #03200.27,09200.08,SHORING & |
GC LTR POUR #95,POUR #97, POUR # 98, & 1 MECH |
SUBMITTAL FOR UNIT #21 BALCONY VENT, 2ND -4TH FL |
FLEX DUCTS WL |
04/24/07 BLDG SUBITTAL NO FEE- SHORING & GC |
LETTERS FG |
4/24/07 CALLED FOR P/U PLANS IN BOX K HM. |
4/23/07 3 SUBMITTALS READY FOR P/U **LARGE BINS** |
"K" SPALMER |
4/20/07 PLUMBING SUBMITTAL 029000101 IRRIG PUMP |
SEW |
4/20/07 BLDG SUBMITTAL SHORING/GC LETTER POUR #97 |
SEW |
4/20/07 ELEC REV UNDER "K" FOR PU,OWES $80 |
(INVOICE ATTACHED) FOR REV FEE, TOLD OFFICE WHEN |
CALLED FOR PU. *LARGE BIN* DV PALMER. |
4/18/07 CALL TO P/U UNDER 'K' MJACOBS. |
04/18/07 SUBMITTAL NO FEE- SHORING & GC LETTER |
POUR # 96 ROUTED TO M JACOBS DESK FG |
4/17/07 MECH BLDG UNIT 21 CHANGES 2ND THRU 4TH |
BALCONY VENT CLARIFICATION & LETTERS 2ND TO 4TH |
USE OF FLEX DUCT IN LIEU OF FIBERBOARD DUCT ROUTED |
TO HMOSER SEW |
4-16-07 5 SUBMITTALS (2 BLDG 1 FIRE 2 ELEC) FIRE |
PROTECTION PLAN UNIT 513, SHORING & GC LETTER POUR |
95, SUBITTAL 03200.27 16TH FL POUR # 95 & 96 REBAR |
SHOP DRAWINGS,ELEC PLAN UNIT 513, & ELEC PLAN UNIT |
#817 WL |
4-16-07 SUBMITTAL #09200.08 EXTERIOR EIFS SENERGY |
SYS ROUTED TO MYRON WL |
4/16/07 BARBARA P/U SOUND CONTRL CORK/EXT ACCESS |
PANEL DOOR/SHORING LTR POUR 93/SHORING LTR POUR 92 |
SPALMER |
4/12/07 BLDG SUBMITTAL SHORING/GC LTR POUR #94 |
SEW |
4/12/07 CALL TO P/U SUBMITTALS UNDER 'K' MJACOBS. |
4-10-07 5 TOTAL SUBMITTALS 3 BLDG #09300.10 SOUND |
CONTROL CORK,#09200.07 EXT. ACCESS PANEL DOOR, |
SHORING & GC LTR POUR #93 2 MECH #15904 CONTROLS, |
15904.01 THERMOSTATS WL |
4-6-07 BARBARA COREY PICKUP 8 SUBMITTALS (5) BLDG |
DATED 4-2-07 1 BLDG DATED 4-4-07, (2) PLUMBING 1 |
DATED 3-15-07 & 1 DATED 3-27-07 WL |
04/06/07 SUBMITTAL NO FEE-SHORING AND GC LETTER |
POUR #92 - ROUTED TO MYRON JACOBS DESK FG |
4-4-7 CALLED FOR P/U PLMG REV/SUBMITTAL "K" & |
"K-LARGE" KSTEVENS |
4/4/07 BLDG SUBMITTAL SHORING/GC LETTER POUR # 91 |
SEW |
04/02/2007 BLDG SUBMITTAL #03200.35 SHEARWALL SHOP |
LEVEL 17-20 P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITALL RFI #517 SECONDARY SLAB |
@ MAIN ELECTRICAL ROOF P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL #03100.24 SHORING SHOP |
DRAWING FOR FLOORS 17-21 P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL #07830.03 45 DEGREE |
ASSEMBLY COUPLING THRU WALL ASSEMBLY P/U BY |
BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL SHORING & GC FORMWORK |
PUR #87 P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL SHORING &GC LETTER POUR |
#86 P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL SHORING & GC LEETER POUR |
#85 P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL SHORING & GC LETTER PUR |
#84 P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL #09100.05 METTAL FRAMING |
SHOP DRAWINGS P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL FFLOORS 16-20 COLUMN |
REBAR SHOPS P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL (SHORING &GC LETTER PUR |
#89 P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL #03900.02 VYNL CONCRETE |
PATCHER P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL (#030900.03 BONSAL |
POLY-MOD CONCRETE REAPAIR) P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMMITAL (SHORING &GC LETTER POUR |
#88) P/U BY BARBARA MMILLER |
04/02/2007 BLG SUBMITTAL (CECO DOOR PRODUCTS) P/U |
BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL (TRUSSTEAL COLD FORNIED |
STEEL TRUSSES P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL (#03365.15 FLLORS 17-20 |
PT SHOPS & CALCS)P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL (#03365.16 21ST FL PT |
CABLE & CALCS) P/U BY BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL (16TH FLOOR PT CABLE |
SHOPS) P/U BY BABBARA MMILLER |
04/02/2007 BLDG SUBMITTAL #03900.01 THIN TOP |
SUPREME P/U BARBARA MMILLER |
04/02/2007 BLDG SUBMITTAL NO FEE (#1101.01 WINDOW |
WASHING EQUIPMENT MMILLER |
04/02/2007 BLDG SUBMITTAL NO FEE (#09350.01 |
CULTURED MARBLE PRODUCT DATA) MMILLER |
04/02/2007 BLDG SUBMITTAL NO FEE (#05100.25 |
EXHAAUST SHAFT TRUSSES) MMILLER |
04/02/2007 BLDG SUBMITTAL NO FEE (#07212.03 |
-INSULATION #09100.06 FRAMING ␢.04 |
DRYWATT)MMILLER |
04/02/2007 BLDG SUBMITTAL NO FEE (#09200.05 |
[email protected] MMILLER |
04/02/2007 BLDG SUBMITTAL NO FEE (SHORIN & GC |
LETTER PUOR #90 MMILLER |
03/29/07 SUBMITTAL NO FEE-# 03365.16 21ST FL PT |
CABLE AND CALCS FG |
03/29/07 SUBMITTAL NO FEE- SHORING & GC LETTER |
POUR # 89 FG |
3/29/07 CALL TO P/U LETTERS FOR FIRE DOORS AND |
WINDOWS FROM CECO. UNDER 'K' MJACOBS. |
03/27/07 BLDG SUBMITTAL NO FEE- FLOORS 17-20 PT |
SHOPS AND CALCS FG |
03/27/07 BLDG SUBMITTAL NO FEE- THIN TOP SUPREME |
FG |
03/27/07 BLDG SUBMITTAL NO FEE- VINYL CONCRETE |
PATCHER FG |
03/27/07 BLDG SUBMITTAL NO FEE- BONSAL POLY MOD |
CONCRETE REPAIR MOTOR FG |
03/27/07 BLDG SUBMITTAL NO FEE- SHORING AND GC |
LETTER FG |
03/27/07 PLUMBING SUBMITTAL NO FEE- SHOWER PAN |
DRAINS FG |
03/23/07 SUBMITTAL NO FEE- # 03200.35- SHEARWALL |
SHOP LEVEL 17-20 FG |
03/23/07 SUBMITTAL NO FEE- SHORING & GC FORMWORK |
POUR # 87 FG |
3-21-07 3 BLDG SUBMITTALS SHORING & GC LTR POUR |
#86, SUBMITTAL #09100.05 METAL FRAMING SHOP |
DRAWINGS, & SUBMITTAL #05100.02 TRUSSTEAL COLD |
FORMED STEEL TRUSSES WL |
3-21-07 BARBARA CORY PICKUP 4 BLDG SUBMITTALS |
POURS # 80,81,82,83 WL |
LDG SUBMITTALS POUR #85 RFI #517 CECO DOOR |
PRODUCTS & #0320036(FLOORS 16-20) SEW |
3/16/07 CALL FOR P/U UNDER 'K' 4 SUBMITTALS POUR |
#80 - #83.MJ. |
03/15/2007 BLDG REVISION FEES #120.00 MMILLER |
03/15/2007 BLDG SUBMITTAL NO FEE MMILLER |
03/15/2007 BLDG SUBMITTAL NO FEE MMILLER |
03/15/2007 BLDG SUBMITTAL NO FEE MMILLER |
03/15/2007 BLDG SUBMITTAL NO FEE MMILLER |
3-13-07 NO FEE BLDG SUBMITTAL POUR #83 WL |
3/13/07 BARBARA P/U LARGE BINS SUBMITTALS SPALMER |
3/13/07 BARBARA P/U 8 SUBMITTALS SPALMER |
3/9/07 CALLED FOR P/U OF REVISED MEP PLANS (REV |
#6). NO SUBMITTAL FORM. LARGE BINS.'K'. RB |
3/9/07 1 BLDG SUBMITTAL POUR # 82 SEW |
3-7-07 1 BLDG SUBMITTAL POUR # 81 WL |
3-7-07 4 BARBARA COREY PICKUP PLUMBING SUBMITTALS |
WL |
3-6-7 CALLED FOR P/U "K" KSTEVENS |
3/5/07 BLDG SUBMITTAL SHORING/GC LTR POUR #80 SEW |
3/1/07 BLDG SUBMITTAL SHORING/GC LTR POUR #79 |
SEW |
2-26-07 4 BLDG NO FEE SUBMITTALS DATED SHORING & |
GC LTR POUR #78, TREMPROOF 201/222 #07120.12, |
#09200.04 SILICONE SEALANTS, PROPOSED SECONDARY |
SLAB FOR MAIN ELEC RM WL |
2-26-07 BARBARA COREY PICKUP REV #9 & 4 NO FEE |
SUBMITTALS WL |
2-23-07 CALLED FOR P/U "K-LARGE" KSTEVENS |
2/23/07 BLDG SUBMITTAL SHORING/GC LTR POUR #77 |
SEW |
02/21/07 BLDG SUBMITTAL NO FEE- SHORING AND GC |
LETTER POUR # 76 FG |
2/20/07 BLDG SUBMITTAL POUR #75 NO FEE SEW |
2-15-07 NO FEE BLDG SUBMITTAL POUR #74 WL 02/14/07 |
BARBARA P/U REV #9 W/ ARCH/STRUC- OK PER R BROWN |
FG |
2/13/07 3 BLDG SUBMITTALS #154000401 #154000201 & |
SHORING/GC LETTER POUR #73 SEW |
2-13-07 BARBARA COREY PICKUP 4 BLDG SUBMITTALS WL |
2/12/07 SUBMITTALS OUT FRONT FOR P/U UNDER 'K' |
2/11/07 REVISED STRUCTURAL PLANS (REV #9, |
SUBMITTED ON 1/11/07) PUT OUT FRONT TOGETHER WITH |
ARCHITECTURAL/STRUCTURAL REVISED PLANS (REV #6). |
WILL CALL FOR P/U AND INCLUDE REV #6 MEP'S WHEN |
FIRE HAS REVIEWED THE FP PLANS FOR REV #6. LARGE |
BINS.'K'. RB |
2/9/07 BLDG SUBMITTAL SHORING/GC LTR POUR #72 SEW |
2/7/07 BLDG SUBMITTAL SHORING/GC LTR POUR #71 SEW |
2-5-07 (3) BLDG SUBMITTALS NO FEE WL |
2-5-07 BARBARO COREY PICKUP (14) BLDG SUBMITTALS |
WL |
2/1/07 (4) BLDG SUBMITTALS #1080001 #15444 |
#1600010/SHORING/GC LTR POUR #69 |
**LARGE BINS**"K" SEW |
01/30/07 SUBMITTAL # 07830.01 ROUTED TO M JACOBS |
DESK NO FEE FG |
01/30/07 SUBMITTAL # 09900.02 AIR PLENOM CONCRETE |
SEALER ROUTED TO M JACOBS DESK FG |
01/30/07 SUBMITTAL NO FEE(SHORING & GC LETTER POUR |
# 68- ROUTED TO M JACOBS DESK FG |
1/26/07 3 BLDG SUBMITTALS #0721201 RFI #468 & POUR |
#67 SEW |
1/24/07 3 BLDG SUBMITTALS #032002901 #0881501 & |
POUR #66 & SUBMITTED NOC SEW |
1-22-07 5 SUBMITTALS 3 BLDG, 1 PLUMB, & 1 MECH |
WL |
1-22-07 BARBARA COREY PICKUP HYDRAULIC CALCS, AND |
THREE BLDGS SUBMITTALS DATED 1 DATED 1-12-07 & 2 |
DATED 1-16-07 WL |
01/19/07 HYDRAULIC CALCULATION SUBMITTALS READY |
FOR P/U; IN LARGE BIN "K" MAW/FIRE 1-18-07 2 BLDG |
SUBMITTALS DATED 1-18-07 WL |
1-18-07 BARBARA COREY PICKUP 4 BLDG SUBMITTALS |
DATED 11-21-06, 12-31-06, 2 DATED 1-10-2007 WL |
1/18/07 CALL TO P/U **LARGE BINS** 'K' MJACOBS. |
1-16-07 3 BLDG SUBMITTALS DATED 1-16-07 WL |
1/12/07 BLDG SUBMITTAL SHORING/GC LETTER POUR # 62 |
SEW |
1/11/07 REVISON # 9 (PER BARBARA) ARCHITECTUAL ID6 |
STRUCTURAL MEP DRWGS $2730 SLS |
1/10/06 (2) BLDG SUBMITTALS SHORING/GC LETTER POUR |
#61 & SUB #0422005 EXPOXY PROD DATA SEW |
1/10/07 (13) BLDG SUBMITTALS PU BY BARBARA SEW |
1/9/07 CALL TO P/U SUBMITTALS UNDER 'K' MJACOBS. |
1-5-07 BARBARA COREY PICKUP BLDG/MECH SUBMITAL |
DATED 11-3-07 & MECH SUBMITTAL DATED 11-21-06 WL |
1-5-07 NO FEE BLDG SUBMITTAL POUR #60 DATED 1-5-07 |
WL |
01/04/07 BLDG LETTERS SUBMITTALS NO FEES MMILLER |
01/04/07 BLDG LETTERS SUBMITTAL NO FEES MMILLER |
1-2-07 5 BLDG 1 FIRE SUBMITTAL DATED 1-2-07 WL |
1-2-07 BARBARA COREY PICKUP MECH SUBMITAAL DATED |
11-3-06 WL |
|
1-2-07 SUBMITTAL #15060.03 & 15815.13 CALLED FOR |
P/U UNDER K PHK |
|
12-28-06 SUBMTAL #15815.17 CALLED FOR P/U **LARGE |
BINS** "K" PHK |
12-27-06 SHERRY FRITZ PICKUP ELEC SUBMITTAL DATED |
6-15-06 #16001.01.01, ELEC SUBMITTAL 06000.02 |
DATED 7-13-06, 6 BLDG SUBMITTALS DATED 12-12-06 |
WL |
12-27-06 NO FEE BLDG SUBMITTAL # 57 WL |
12/22/06 PUT OUT FRONT UNDR "K" CALLED JL 12/20/06 |
BLDG SUBMITTAL POUR # 56 DIDN'T P/U 12/16 |
SUBMITTAL SEW |
LARGE BINS. |
12/16/06 CALL TO P/U SUBMITTALS UNDER 'K' |
MJACOBS. |
12/14/06 BLDG SUBMITTAL NO FEE- FIRE CAULKAT TOP |
OF CMV WALLS IN GARAGE- ROUTED TO J SMITH FG |
12/13/06 SUBMITTAL NO FEE- 09200.02 LATH STUCCO |
AND EXT FRAMING FG |
12/13/03 SUBMITTAL NO FEE # 08810.02- SEALANT |
PRIMER CEROUT AND TAPCONS FOR FENESTRATIONS |
PRODUCT DATA FG |
12/13/06 SUBMITTAL NO FEE- # 09900.01 PAINT |
SUBMITTAL FG |
12/13/06 SUBMITTAL NO FEE # 08210.04 WOOD DOORS |
FG |
12/13/06 BLDG SUBMITTAL NO FEE & GC LETTER POUR # |
55 FG |
12/12/06 7 BLDG SUBMITTALS #0925003 #0925002 |
#0910003 #0910002 #0336512 #0336513 & SHORING |
FORMWORK/GC LETTER POUR #54 SEW |
12/12/06 16 SUBMITTALS PU BY BARBARA SEW |
BIG BINS. |
12/7/06 CALL TO P/U SUBMITTALS UNDER 'K' MJ. |
12/06/06 BARBARA P/U 4 PLUMB SUBMITTALS FG |
12/06/06 BLDG SUBMITTAL NO FEE- # 03200.32 LEVEL |
8-11 FG |
12/06/06 BLDG SUBMITTAL NO FEE- # 09100.01- |
BALCONY FRAMING @ LEVELS 1-4 AND WEST ELECVATION |
FRAMING FG |
12/06/06 BLDG SUBMITTAL NO FEE- SHORING & FORMWORK |
GC LETTER POUR # 53 FG |
12-6-6 CALLED FOR P/U PLMG SUBM. (11/21) "K" |
KSTEVENS |
12/04/06 BARBARA P/U 15 SUBMITTAL FG/SP |
** POOL/SPA/FOUNTAIN IS UNDER SEPARATE PERMITS. |
12/4/06 SUBMITAL #03200.30 8TH FL COLUMN SHOPS. NO |
FEE TA |
12/4/06 BLDG SUBMITTAL OF SHORING FORMWORK & GC |
LTR POUR#50 NO FEE TA |
12/3/06 E-MAILED MATT STILL TO P/U DOOR/WINDOW |
SUBMITTAL. LARGE BINS.'K'. RB |
11/28/06 SHORING & FORMWORK GC LETTER POUR 51 NO |
FEE SLS |
11/28/06 BLDG SUBMITTAL # 03300.26 NO FEE SLS |
11/28/06 BARBARA P/U SUBMITTAL DATED 8/18/06 |
SPALMER |
11/27/06 BLDG SUBMITTAL NO FEE- SHORING FORMWORK & |
GC LETTER FG |
11/21/06 BLDG SUBMITTAL (#03400.01.04) NO FEE TA |
11/21/06 BLDG SUBMITTAL (03200.29) NO FEE TA |
11/21/06 BLDG SUBMITTAL (#05520.09.01) |
CALCULATIONS. NO FEE TA |
11/21/06 BLDG SUBMITTAL (#05520.07.01) SPIRAL |
STAIRS. NO FEE |
11/21/06 BLDG SUBMITTAL (#05520.08.01) NO FEE TA |
11/21/06 BLDG SUBMITTAL (TEMP WATER PROFFING |
IMPLEMENTATION PLAN) NO FEE. TA |
11/21/06 BLDG SUBMITTAL (#07830.01) NO FEE TA |
11/21/06 BLDG SUBMITTAL (POUR 49) SHORING & |
FORMWORK & GC LTR. NO FEE TA |
11/21/06 PLUMB SUBMITTAL (#15400.01.01) PORTABLE |
WATER EXP TANK. NO FEE |
11/21/06 PLUMB SUBMITTAL (#15430.01) NO FEE TA |
11/21/06 PLUMB SUBMITTAL (#15410.05) NO FEE. TA |
11/21/06 PLUMB SUBMITTAL (#15450.03) NO FEE. TA |
11/21/06 MECH SUB (#15815.13 BOX WALL CAPS) NO FEE |
TA |
11/13/06 CALLED FOR P/U SUBMITTALS IN BOX K HM. |
11/13/06 BLDG SUBMITTAL (SHORING FROMWORK & GC LTR |
POUR #48) NO FEE TA |
11/6/06 MECH SUBMITTAL NO FEE TA |
11/3/06 (2) MECH SUBMITTALS #1506003/#1581517 (6) |
BLDG SUBMITTALS |
#0336511/#031002001/#0310021/#0310022/#033651001/ |
SHORING FORMWORK & GC LETTER SEW |
11/1/06 BLDG SUBMITTAL (POUR #46) NO FEE TA |
11-1-06 BARBARA COREY PICKUP (5) PLUMBING |
SUBMITTALS DATED (2)4-4-06, 9-28-06, 9-12-06, |
10-12-06 WL |
10-30-6 CALLED FOR P/U OF VARIOUS PLUMBING |
SUBMITTALS "K" KSTEVENS |
10/27/06 SPEC SHEETS FOR FIRE EXTINGUISHER AND |
FIRE PUMP CONTROLLER READY FOR P/U UNDER "K" MAW |
10/26/06 DENIED CALL TO P/U UNDER 'K' MJACOBS. |
10/17/06 THE THRESHOLD INSPECTOR CHANGED FROM |
ARDAMAN TO OMN&J SEE NOTES HHP |
10/25/06 SUB/BLDG SHORING FORMWORK & GC LETTER |
POUR # 45 SEW |
10/25/06 SUB/BLDG SUBMITTAL #0320028 PT |
10/25/06 SUB/MECH SUBMITTAL #158151101 PT |
10/25/06 BARBARA P/U PLUMBING REV SPALMER |
10-23-6 CALLED FOR P/U REV #8 "K" ABOVE THE LARGE |
PLANS KSTEVENS |
10/20/06 MECH SUBMITTAL # 15141.03 BLDG SUBMITTAL |
# 02520.01 AND BLDG SUBMITTAL RFI#398 FOR CMU |
WALLS AT PARKING GARAGE SLS |
10/19/06 BLDG SUBMITTAL (POUR #44) SHORING |
FORMWORK & GC LTR. NO FEE TA |
10/18/06 BARBARA P/U 25 SUBMITTALS SPALMER |
10/12/06 TWO ELEC SUBMITTIALS **LARGE BINS** "K" |
FOR PU,CALLED, SPOKE TO MATT. DV PALMER. |
10/12/06 MECH SUBMITTAL (15815.18) NO FEE. TA |
10/12/06 MECH SUBMITTAL (SUBMITTAL 15815.15) NO |
FEE. TA |
|
10/12/06 MECH SUBMITTAL (GROUND FL DUCK 15815.01) |
NO FEE TA |
10/12/06 MECH SUBMITTAL (PARKING LVL #7 15815.16) |
NO FEE TA |
10/12/06 MECH SUBMITTAL (PARKING LEVEL *2 |
SUBMITTAL # 15815.19) NO FEE TA |
10/12/06 FIRE SUBMITTAL (10520.01) NO FEE TA |
10/12/06 PLUMB SUBMITTAL (IRRIGATION PRODUCT DATA) |
NO FEE. TA |
10/12/06 BLDG SUBMITTAL (POUR 43) NO FEE TA |
10/06/06 BARBARA P/U SUBMITTALS SPALMER |
10/05/06 REV # 5 P/U BY BARBARA FG |
10/05/06 SUBMITTAL NO FEE- SHORING FORMAT & GC |
LETTER POUR # 42 FG |
10/04/06 CALLED FOR P/U PLANS IN BIG BOX K HM. |
9/29/06 (6)SUBMITTALS - (1) ELEC LT POLE WIND |
DESIGN (1) PLUMBING DECO DRAIN PRODUCT DATA (1) |
MECH SUPPLY & EXHASUT FANS (3) BLDGS SHORING |
FORMWORK POUR #41/LOUVERS & GRILLS & PARKING LEVEL |
9 SEW |
9/27/06 BARBARA P/U REVS SPALMER |
9/22/06 ELEC REV FROM 8/4 UNDER "K", LARGE ROLL ON |
FLR. CALLED, LEFT MESSAGE WIHT MATT'S VM. DV |
PALMER |
9/19/06 SHORING LETTER TO RB.KC |
9/18/06 SUBITTAL OF SHORING FORMWORK & GC |
LETTER...POUR #39. NO FEE TA |
9/15/06 BLDG SUBMITTAL NO FEE- SHORING AND GC |
LETTER POUR# 38- ROUTED TO K CONRAD FG |
9-12-06 BARBARA COREY PICKUP SUBMITTAL #15410.06 |
(PLUMB..CHARLOTTE NO HUB CAST IRON PIPING) WL |
9/12/06 PLUMB REV $850. VERIFIED WITH CONTRACTOR |
THAT THEY WERE REV 80 SHEETS. TA |
9/12/06 PLUMB SUBMITTAL (BACK FLOW PREVENTERS) NO |
FEE TA. |
9/12/06 BLDG SUBMITTAL (LANAI PT CABLE SHOPS) NO |
FEE TA |
9/12/06 BLDG SUBMITTAL (SHORING FORMWORK & GC LTR) |
NO FEE. TA |
9/12/06 BLDG SUBMITTAL (SHORIP SHOPS&CALCULATIONS) |
TA. |
9/12/06 BLDG SUBMITTAL (LANAI REBAR SHOPS) NO FEE |
TA |
9/12/06 SHORING LETTERS TO LUIS M.FOR REVIEW.KC |
9/8/06 BLDG SUBMITTAL-SHORING FORMWORK & GC LETTER |
POUR 36- NO FEE- LETTERS FORWARD TO K CONRAD/H |
PISKURA FG |
9/7/06 PLBG SUBMITAL OK UNDER "K" JHL |
9/5/06 DOOR/WINDOW SUBMITTAL PACKAGE. SEW |
9-3-06 CALLED MATT TO P/U REV. LARGE BINS 'K'. RB |
9/1/06 BLDG SUBMITTAL SHORING FORMWORK/GC LETTER |
POUR #35 SEW |
8/31/06 5 BLDG SUBMITTALS 1 PLUMBING SUBMITTAL AND |
2 MECHANICAL SUBMITTALS NO FEE SLS |
8/25/06 BLDG SUBMITTAL SHORING/FORMWORK/GC LETTER |
POUR # 34 SEW |
8/24/06 16 PLUMBING SUBMITTALS (15 APPROVED, ONE |
DENIED) P/U BY BARBARA AJP |
8/24/06 16 SUBMITTALS PACKAGED TOGETHER AND MOVED |
TO LARGE PLAN IN "K" AJP |
8/24/06 CALLED FOR P/U PLMG SUBMITTAL "K" MRPERSON |
8/23/06 CALLED FOR P/U PLMG SUBMITTAL "K" MRPERSON |
8/22/06 SUBMITTAL NO FEE -SHORING FORMWORK AND GC |
LETTER POUR 33 FG |
8/18/06 BLDG SUBMITTAL CABLE PROCEDURE SET-UP SEW |
8/17/06 BLDG SUBMITTAL OF SHORING FORMWORK & GC |
LTR POOR # 3. NO FEE. TA |
8-17-6 CALLED FOR P/U PLMG SUBMITTAL "K" KSTEVENS |
8/10/06 BLDG SUBMITTAL OF SHORING FORMWORK & GC |
LTR/POUR # 32. TA |
8/4/06 SUBMITTAL OF SHORING FORMWORK &GC LTR POUR |
#30. NO FEE. TA |
8/2/06 THE FOLLOWING SUBMITTALS P/U BY BARBARA: |
APPROVED PLUMBING |
15410.02,15484.02,15420.01,15450.02,15400.03;DENIE |
5410.02,15484.02,15420.01,15450.02,15400.03;DENIED |
PLUMBING 15400.01, 15450.03. AJP |
8/2/06 (3) BLDG SUBMITTALS #0930002 SHOP DRAWINGS |
#0320023 LEVEL 4 SHOP DRAWINGS SHORING FORM WORK & |
GC LETTER POUR # 29 SEW |
7/31/06 5 APP. PLMG SUB.& 2 DENIED SUB. CALLED FOR |
P/U UNDER "K" MRPERSON |
7/28/06 BLDG SUBMITTAL SHORING/FORMWORK POUR #28 |
SEW |
7/27/06 BLDG SUBMITTAL NO FEE- PARKING LEVEL 8- |
TOWER LEVEL 4 REBAR FG |
7/27/06 BLDG SUBMITTAL NO FEE- TIE COLUMNS -TIE |
BEAMS AND MASONARY REBAR SHOPS FLOOR 3-4 FG |
7/27/06 BLDG SUBMITTAL NO FEE- PARKING LEVEL # 7 |
DECK REBAR BEAMS FG |
7/27/06 PLUMBING SUBMITTAL NO FEE- NO HUB CAST |
IRON PIPING FG |
7/27/06 BLDG SUBMITTAL NO FEE- HARD ROCK FG |
7/27/06 BLDG SUBMITTAL NO FEE- SUBMITTAL # |
03100.18- SONOGROUT 10K FG |
7/27/060 BLDG SUBMITTAL NO FEE- SHORING FORMWORK |
AND GC LETTER |
7/25/06 BLDG SUBMITTAL SHORING FORMWORK & GC |
LETTERS POUR #26 SEW |
7/25/06 THREE SUBMITTALS --#15444.01.01, DOMESTIC |
BOOSTER PUMS, AND #15430.01, PLUMBING FIXTUE |
PAKAGE, #15455.01.01, GARAGE SUMP PUMP--P/U BY |
BARBARA AJP |
7/25/06 SUBMITTAL # 15685.02 COOLING TOWER |
FILTRATION SYSTEM P/U BY BARBARA AJP |
7/24/06 SUBMITTAL #15444.01.01 MOVED TO LARGE PLAN |
BIN "K" AJP |
7/21/06 SHORING FORMWORK AND GC LETTER POUR 25 SLS |
7-17-06 NO FEE BLDG SUBMITTAL SHORING FORMWORK & |
6C LETTER POOR #24 WL |
7-13-06 BARBARA PICKUP PLUMBING REVISIONS FROM L |
MARTINEZ WL |
7/13/06 (7) BLDG SUBMITTALS #0550005 #154550101 |
#1600002 #154440101 #1543001 #0320019 & SHORING |
FORMWORK/GC LETTER POUR # 23 SEW |
7/5/06 SUBMITTAL NO FEE- SHORING-FORMWORK AND GC |
LETTER POOR # 21 FG |
7-3-6 CALLED FOR P/U (PLMG) "K" (LG. PLAN) |
KSTEVENS |
6/28/06 PROPRESS RIDGID SYSTEM SUBMITTAL SLS |
6/28/06 COMMON AREA & UNIT HEAT PUMP SUBMITTAL SLS |
6/28/06 DUCTILE IRON PIPE & FITTINGS SUBMITTAL SLS |
6/28/06 CPVC PIPE & FITTINGS SUBMITTAL SLS |
6/28/06 SUBMIT SHORING FORMWORK & GC LETTER SLS |
6/27/06 LEE P/U SUBMITTAL SPALMER |
6-27-06 CALLED P/U "F" PLBG SUBMITTAL. PES 6/26/06 |
PLUMBING SUBMITTAL FOR DWV ROUTED TO PSCHMITZ SEW |
6/22/06 REVISION PGS 6 AND 6A- ARCH'S- STRUCTURE- |
MEP |
6/22/06 BLDG SUBMITTAL NO FEE- SHORING FORMWORK |
AND GC LETTER FOR POUR # 20 FG |
6/21/06 BLDG SUBMITTAL NO FEE -SHEAR WALL |
REBARSHOPS P8-TOWER LEVEL 9 FG |
6/21/06 SUBMITTAL NO FEE -PARKING LEVEL 5 POOR 17 |
BEAMS BOTTOMS MISC FG |
6/21/06 MECAHNICAL SUBMITTAL ACCESS PANELS NO FEE |
FG |
6/21/06 BLDG SUBMITTAL NO FEE- CHUTE FEILD |
COMPACTORS FG |
6-20-06 BARBARA COREY PICKUP LANDSCAPE PLANS WL |
6/20/06 SHORING FORMWORK AND GC LETTERS SUBMITTED |
SLS |
6/15/06 (26) SUBMITTALS 0712006 0712005 0712008 |
0712009 1548403 1518101 1549901 1545502 1543007 |
1543008 1540004 1541004 1541005 1504701 1548401 |
1545503 0712004 160010101 1642501 1581506 1581505 |
1581508 1581509 1581507 ALSO SUBMITTAL SHORING |
FORWORK & GC LETTERS |
6/13/06 SUBMITTAL P/U BARBARA SPALMER |
6-12-06 CALLED MATT FOR LANDSCAPE PLAN P/U 1 ROLL. |
'K'. RB |
6/12/06 BLDG SUBMITTAL NO FEE - SHORING FORMWORK |
AND GC LETTER FG |
6-11-06 CALLED MATT FOR PLAN P/U. 13 ROLLS.'K'. RB |
6-10-6 CALLED FOR P/U "K" KSTEVENS |
6/8/06 PLUMBING SUBMITTAL NO FEE- # 1540.03- HOT |
WATER CIRCUBATING PUMP FG |
6/8/06 PLUMBING SUBMITTAL NO FEE - # 15484.02- |
STEEL PIPE FG |
6/8/06 PLUMBING SUBMITTAL NO FEE- # 15420.01- |
NIBCO BALL- CHECK AND GATE VALVES FG |
6/8/06 PLUMBING SUBMITTAL NO FEE #15400.01-THERMAL |
EXPANSION TANK FG |
6/8/06 BLDG SUBMIUTTAL NO FEE - # |
154450.02-VICTAULIC COPPER SYSTEM FG |
6/8/06 BLDG SUBMITTAL NO FEE -15400.03-WATER |
METER FOR COOLING TOWER MAKE UP WATER FG |
6/8/06 BLDG SUBMITTAL NO FEE-#15410.02- COPPER |
TUBE & FITTING TYPE-L DWV FG |
6/8/06 BLDG SUBMITTAL NO FEE- #03365.05-PARKING |
LEVEL P5&57 FG |
6/8/06 BLDG SUBMITTAL NO FEE- #07120.03-FLUID |
APPLIED WATERPROOFING MEMBRANE FG |
6/8/06 BLDG SUBMITTAL # 07120.07- VULKEM |
3501351-SLIP RESISTANT -PEDESTRIAN WATERPROOFING |
SYSTEM FG |
06/08/06 BLDG SUBMITTAL # 05520.01.01- ALUMINUM |
RAILING @ BALCONIES FG |
6/8/0 BLDG SUBMITTAL NO FEE- #05500.02.02= |
STRUCTURAL STEEL STAIRS SHOPS AND CALCS FG |
6/8/06 BLDG SUBMITTAL NO FEE-# 03200.16-OE SHINY |
GALV FG |
6/8/06 BLDG SUBMITTAL NO FEE-# 08110.01.02 DOOR |
SCHEDULE & HARDWARE SCHEDULE FG |
6/8/06 BLDG SUBMITTAL NO FEE- SHORING FORMWORK &6C |
LETTERS FG |
6/5/06 SUBMITTED SHORING & FORMWORK GC LTRS. NO |
FEE. TA |
6-2-06 P MECH/SUBMITTAL CALLED MATT P/U "K" TG. |
5/31/06 SHORING LTRS SUBMITTED NO FEE SLS |
5/31/06 SUBMITTAL NO FEE FG |
5/23/06 SUBMITTAL P/U BY BARBARA. TA |
5/23/06 SUBMITTAL P/U BY BARBARA. TA |
5/19/06 SHORING LTRS SUBMITTED. NO FEE TA 5-16-06 |
SUBMTL CALLED FOR P/U UNDER K PHK 5/16/06 |
SUBMITTAL NO FEE -PARKING LEVEL #4 THRU 9/TOWER |
LEVEL # 2 THRU 4 FG |
5/16/06SUBMITTAL NO FEE -HIHI DATA SHEET FG |
5/16/06 EXPANISION JOINT MATERIAL PRODUCT DATA FG |
5/16/06SUBMITTAL NO FEE -VAPRO BARRIER FOR SLAB ON |
GRADE FG |
5/16/06 SUBMITTAL NO FEE- HARD ROCK VERTIPATCH |
(CONCRETE VERTICLE /OVERHEAD REPAIR) FG |
5/16/06 SUBMITTAL NO FEE FOAM DATA SHEETS FG |
5/16/06 SUBMITTAL NO FEE CODING TOWER FILTRATION |
SYSTEM FG |
5/16/06 SUBMITTAL NO FEE -FORMWORK AND INSPECTION |
-POUR 12 FG |
5/11/06 SUBMITTAL NO FEE- GC SHORING AND FORMWORK |
INSPECTION LETTERS FG |
5/9/06 PLUMB SUBMITTAL #15430.06 ALTERNATE COMMON |
& UNIT WATER HEATER SEW |
5/9/06 BLDG SUBMITTAL #03100.13 DOVETAIL SLOTS SEW |
5/9/06 BLDG SUBMITTAL SHORING & FORMWORK GC INSP |
LETTERS SEW |
5/9/06 BLDG SUBMITTAL #03365.04 SEW |
5/9/06 BLDG SUBMITTAL #03200.11.01 SEW |
5/9/06 BLDG REV SEW |
5/1/06 SHORING/GC LETTER LEVEL TWO POUR B SEW |
4/28/06 ELEC/PLUMB/MECH/FIRE REV TA |
4/28/06 BLDG SUBMITTAL 03100.15 LETTERS & DRAWINGS |
NO FEE SEW |
4/28/06 SUBMITTAL SHORING ENGINEER/GC INSPCTIONS |
POUR # 7 NO FEE SEW |
4-25-06 SUBMITTAL NO FEE BLDG SHORING INSPECTIONS |
& GC LETTERS WL |
4/18/06 SUB/BLDG (POURS 5&6 SHORING SHOPS) SEW |
4/18/06 SUB/BLDG (ENGINEER & SHORING LETTER) SEW |
4/14/06 ONE ROLL OF PLANS (NOT SIGNED AND SEALED) |
AND THREE SHORING LETTERS P/U BY BARBARA AJP |
4/14/06 SUB/BLDG (ENGINEER & SHORING INSPECTION) |
PT |
4/12/06 SUBMITTAL NO FEE CONCRETE MIX 6000 & |
TYPICAL STAIR FORMING DETAIL & TOWER & PK6 COLUMNS |
P5 TO P9 TA |
************************************************* |
4/12/06 SUBMITTAL NO FEE SHORING LETTERS/ROUTED TO |
HPISKURA SEW |
4/6/06 SUBMITTAL NO FEE SHORING LETTERS/ROUTED TO |
HPISKURA SEW |
4/6/06 SUBMITTAL NO FEE 1 ELECTRICAL- 10 |
MECHANICAL- 31 BLDG ROUTED TO L MARTINEZ FG 4/5/06 |
BLDG SUBMITTAL NO FEE SEW |
4/3/06 SUBMITTAL NO FEE SHORING LETTERS/ROUTED TO |
H PISKURA FG |
4/3/06 (40) SUBMITTALS NO FEE SEW |
3/24/06 SUBMITTAL NO FEE/RTOUTED YTO H PISKURA |
DESK FG |
************************************************* |
************************************************* |
VALUE CALC: |
1.04((84+1.75)X897,891 + (39+1.75)X280,199 + |
7X41,000) = $92,247,232 |
1-28-05 CALLED RYAN THOMAS FOR P/U.'K'(BIG ROLL)RB |
1-31-05 LEROY P/U PLANS NFL |
2/23/05 APPLICATION SUBMITTED FOR PERMITTING PT |
2/23/05 PD 30% OF PERMIT FEES IN THE AMOUNT OF |
$333,166.50 PT |
2/23/05 ORIGINAL PAPERWORK SUBMITTED FOR PROJECT |
BILLING WAS NOT INCLUDED/WILL BE BROUGHT IN |
TOMORROW PT |
3/4/05 PLANS TAKEN OUT OF REVIEW PROCESS PER RYAN |
THOMAS ON 3/1/05. NEW SHEETS ARE TO BE BROUGHT IN |
BEFORE REVIEWS START. WHEN PLANS COME IN, NEW |
RESUB DATE WILL APPLY. DV PALMER. |
3/10/05 APPLICATION WITH PLANS ON BACK SHELF LM |
3/11/05 WAS ON HOLD AWAITING ADDITIONAL PLANS THAT |
CAME IN TODAY. ADARROUGH 4/20-05 DENIED. CALLED |
RYAN THOMAS FOR P/U.'S'.RB 6/14/5 CHANGE OF CONTR |
$100 FEE FG |
8/3/5 1ST RESUB NO FEE FG |
9-1-05 NO FEE SUBMITTAL 1 COMPLETE SET OF VOIDED |
SHEETS (PLANS) TOTAL OF 4 ROLLS WL |
09/16/5 CHANGE OF CONTRACT $ 100 FEE FG |
10-18-05 SUBMITTAL OF LANDSCAPE PLANS TO BE |
INSERTED PR A APONTE OK BY L MARTINEZ NFL |
11-14-05 CALLED MATT STILL FOR RESUB P/U. 'K'. RB |
11-15-2005 BARBARA COREY PICKED UP ALL ROLLS |
11-21-05 CALLED MATT STILL TO P/U. ADD'L PLANS |
'K'. RB |
11/22/05 DENIED PLANS P/U BY BARBRA COREY. |
11/28/05 2ND RESUB $100050 SPALMER |
01/31/06 SUBMITTAL ROUTED TO AISHA TO BE PLACED |
WITH PLANS FG |
02/01/06 SUBMITTAL ROUTED TO AISHA TO BE PLACED |
WITH PLANS FG |
02/01/06 SUBMITTAL NO FEE ROUTED TO INCOMING FG |
2/17/06 *****AT TIME OF NEXT RESUBMITTAL MUST PAY |
$1,200,599.99 (I.E. 4X PLAN REVIEW FEE). RB***** |
2/24/06 CC TO KAST FEE $100 TA |
2-26-06 DENIED. CALLED RYAN THOMAS FOR P/U.'K'. RB |
2/27/06 BARBARA P/U DENIED PLANS SPALMER |
3/7/06 BLDG/PLUMB/MECH RESUB TA |
3-15-06 MECH/SUBMITTAL LETTER GIVEN TO DIANE FOR |
NEIL PHK |