Miscellaneous Information / Notes |
NSFR LOT 88 |
|
|
|
|
10-23-06 MECH REV P/U BY CHARLIE PHK |
9/19/06 MECH REV SEW |
6/28/06 ELEC REV $60 SLS |
4/24/06 EL. REV. P/U BY BOB AJP |
4/21/06 ELEC REV 1OF 4, UNDER"A"./WRT |
4/10/06 ELEC REV $60 SPALMER |
4/5/06 EL. REV. P/U BY CHARLIE AJP |
4/4/06 ELEC REV OK,CALLED, UNDER "A" FOR PU. DVP. |
4-3-06 P MECH/REV. LEFT MSG. P/U "A" TG. |
3/31/06 MECH REV FEE $60 TA |
************************************************* |
3/31/06 ELEC REV FEE $60 TA |
************************************************* |
8/31/04 UP FRONT 'A' CALLED CONTRACTOR FAILED ELEC |
MECH & BLDG. LS |
9/14/04 DENIED PLAN/APP P/U PETER PSMITH |
FEES STILL OWED |
12/21/04 1ST RESUB/NC PLANS + APP PT |
1/11/05 UP FRONT 'A' CALLED CONTRACTOR LS |
01/14/05 DEBBIE P/U DENIED PLANS SPALMER |
01/27/05 RESUB 2ND SPALMER |
1/31/05 UP FRONT 'A' CALLED CONTRACTOR LS |
2-4-5 PLANS PU/DEBBIE - KAM |
2/18/05 3RD RESUB $415.05 SPALMER |
2/22/05 UP FRONT 'A' CALLED CONTRACTOR BAL DUE |
415.05 LS |
2-23-05 CHARLIE P/U PERMIT NFL |
10-6-05 REV $60 NFL |
10-13-05 P MECH. REV. CALLED CHARLIE P/U "A" TG |
10/14/05 CHARLIE P/U REV SPALMER |
11/10/05 ELEC REV $70 FEE FG. |
11/23/05 ELEC REV UNDER "A"./WRT. |
11/28/05 ELEC REV PICKED UP BY CHARLIE./WRT. |
12/07/05 REV $60 FEE/ROUTED TO B TROBAUGH DESK FG |
12/7/05 ELEC REV UNDER "A"./WRT. |
12/12/05 DUP. PERMIT $25 AJP |