Miscellaneous Information / Notes |
CONSTRUCTION OF ROWHOUSE BLDG 7C UNITS 1-6 |
3 STORIES |
|
|
|
|
|
|
|
6/10/04 1ST RESUB NO FEE PSMITH |
3/10/05 2ND RESUB PLANS (ORIGINAL APP NOT |
INCLUDED) PT |
3/22/05 DENIED/CALLED/UNDER "W" RM |
3-22-05 BRIAN P/U PLANS NFL |
3/22/05 3RD RESUB $834.26 SPALMER |
3/25/05 CALLED/ROOFERS WORKERS COMP. EXPIRED/OWES |
FEES/ UNDER 'W' RM |
3/30/05 DAISY P/U PERMIT SPALMER |
|
4/18/05 SOIL DENSITY TEST REPORT OK/UNDER 'W' RM |
5/18/5 REV $60 FEE FG |
5/24/05 REV OK UNDER 'W' RM |
5/25/5 REV P/U BY BRIAN FG |
6/6/5 PLUMB REV $60 FEE FG |
6/25/05 PLBG REV READY TO P/U UNDER W JHL |
6/29/5 REV P/U BY BRIAN FG |
9-15-05 REV (MECH) DA |
9/21/5 BLDG REV $60 FEE FG |
9/26/5 REV $80 FEE FG |
9.28.05 MECH REV CALLED FOR P/U UNDER 'W' RJR |
9/29/05 BRIAN P/U REV SPALMER |
10-4-5 REV $70 - KAM |
10/7/05 BRIAN P/U REV SPALMER |
10/7/05 PLUMBING REV READY UNDER "W" JHL |
10/18/05 BRIAN P/U REV SPALMER |
11/17/05 REV OK/UNDER 'W' RM |
12/08/05 REV P/U BY BRIAN AJP |
12/16/05 INSPECTION FEE $100 FG |