Miscellaneous Information / Notes |
15 STORY FOUNDATION ONLY, PILINGS, PILE CAPS AND |
GRADE BEAMS. |
ORIG REVIEW FOR BLDG UNDER 02040459 |
CALLED FOR PU, UNDER "K" 01-23-03 MRA |
P/U 1/23/03 BY STEPHEN BURJAN LS |
3-12-03 CHANGE OF CONTRACTOR BZ 220491 $100 NFL |
PLANS LEFT ON SHELF BY CONFERENCE ROOM - LM WILL |
NOTIFY CONTRACTOR. 3-19-3 KSTEVENS |
3/20/03 PLANS + APP P/U BY STEPHAN PT |
3-20-03 1ST RESUB NO FEE TJ |
PLANS PU/STEPHAN/CALCULATE IMPACT FEES 3-27-03 KAM |
4/7/03 PAID IMPACT FEE & BZ# 222433 PD 10867.35 |
SUBMITTING FOR PERMIT/FEE OWING FOR FIRE FEE |
$1603.50 MM |
BALANCE PD $1603.50 BZ#222144 4-8-03 KAM |
5-21-03 REV FOR BUILD BZ225236 TJ |
5-27-03 REV PU TJ |
NO FEE SUBMITTALS DATED 6-5-03 PER H PISKURA & |
DEAN RUNNELS IF THERE ARE ANY FEES DUE THEY WILL |
LET CONTR KNOW 6-5-03 WL |
6/9/03 PLANS P/U BY STEPHEN PT |
7/24/03 FOUNDATION PILES REPORT TO DON NEELY |
FOUND REVISIONS FOR CRANE 1 & 2 DATED 4/14/03 AND |
5/15/03 OWES $170 CONT CALLED 6/10/03 FILED "S" HP |
BZ 226231 PER HHP |
6-27-03 SHOP DRAWINGS NO FEE |
7-3-03 SUBMITTAL SHORING PLANS AND INSPECTIONS |
TO DON NEELY |
REV # 2 BLDG $380 BZ 227195 7-3-03 WL |
7-9-03 BEN P/U SUBMITTALS NFL |
7-9-03 SUBMITTALS NFL |
NO FEE SUBMITTAL SHORING PLAN/INSP LTR 7-18-03 WL |
PER DEAN RUNNELS BEN AUSTIN IS TO SHOW PAID BZ |
226231 $170 WRITTEN BY HAROLD PISKURA ON 6-10-03 |
BEFORE POSTING FEE (ADDED FEE AS CODE 0803 AS WE |
NO LONGER HAD PAPERWORK) 7-18-03 WL |
`EN AUSTIN PICK UP NO FEE SUBMITTALS DATED 7-9-03, |
7-3-03,7-9-03, AND 6-5-03 ON 7-18-03 WL |
SUBMITTALS 03365-2, 11175-1, 03000-17, 03000-16, |
03100-18 NO FEE CHGD 8-21-03 WL |
ABOVE SUBMITTALS 8/25/03 CALLED, FILED "S" HHP |
SUBMITTALS PU BARRY 0300217 0300016 0310018 |
033652 111751 8/27/03 PSMITH |
9-30-03 4 SUBMITTALS - NO FEE KAM |
10/6/03 BLD REV PU LEROY PSMITH |
09/30/5 OVERTIME INSPECTION FEE $200/ OK PER J |
LEAHY FG |
11/16/05 OVERTIME INSPECTION $200 FOR 3 HOURS |
LETTER GIVEN TO J LEAHY FG |