2015-04-09 09:59:27 | MET CONTRACTOR ON SITE WHILE DOING AN |
| "IN PROGRESS" INSPECTION. OBSERVED AND |
| DISCUSSED CONDITIONS OF ROOF IN FIELD. |
| ALSO INSPECTED WERE AC STAND BASES, |
| GOOSE NECK AND PITCHPAN WATERPROOFING, |
| AND CONDITION OF LIGHTWEIGHT CONCRETE |
| UNDER REROOF PERMIT #15030639. OBSERVED |
| WAS WATER INTRUSION AT STAND BASES, |
| PITCH PANS, AND ELECTRICAL CONDUITS IN |
| PARTICULAR. LIGHTWEIGHT CONCRETE WAS |
| CRACKED, BROKEN, AND PATCHED PREVIOUSLY. |
| BASED ON THE LIGHTWEIGHT CONCRETE |
| CONDITION OBSERVED, THE SECURE |
| ATTACHMENT OF THE BASE SHEET TO THE |
| LIGHTWEIGHT WAS QUESTIONED. AGREED WAS |
| TO DRY IN THE NORTHWEST AREA EXPOSED AT |
| THE TIME OF INSPECTION, AND HAVE THE |
| ROOFER'S ENGINEER VISIT THE SITE TO |
| INSPECT THE LIGHTWEIGHT. SUGGESTED WAS |
| THE PLAN TO HAVE A WITHDRAWL TEST DONE |
| ON THE LIGHTWEIGHT CONCRETE AND UPLIFT |
| TEST ON THE TWO PLY ROOFING ASSEMBLY. |
| THE ENGINEER WILL ULTIMATELY DECIDE AND |
| APPROVE THE ROOF ASSEMBLY THAT COULD |
| DIFFER FROM THE PRESENT ASSEMBLY. ROOFER |
| WILL PULL OFF FOR 3 DAYS WHILE THE |
| EVALUATION TESTS ARE COMPLETED. |
| |
| |