| 2023-07-13 07:41:51 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. THE CITY'S OFFICIAL VERTICAL DATUM PER CITY CODE |
| | SECTION 78-9 IS NGVD1929. THE NAVD1988 VERTICAL DATUM |
| | MAY BE USED IF THE CONVERSION EQUATION BETWEEN NAVD1988 |
| | AND NGVD1929 IS PROVIDED. LIST THE CONVERSION EQUATION |
| | TO NGVD1929 ON THE SURVEY AND EVERY PLAN SHEET WITH |
| | ELEVATION INFORMATION. |
| | |
| | 2. MOVE THE CONSTRUCTION ENTRANCE OUT OF THE RIGHT OF |
| | WAY. |
| | |
| | 3. CONSTRUCT TYPE D CURB ALONG THE EDGE OF PAVEMENT |
| | ALONG THE FRONTAGE TO THE WEST DRIVEWAY OF 1320 ALPHA |
| | ST. |
| | |
| | 4. SECTION A-A (SHEET 3 OF 5) CREATE A SWALE ALONG THE |
| | BACK OF SIDEWALK/RIGHT OF WAY TO PREVENT RUNOFF FROM |
| | FLOWING DIRECTLY OVER THE SIDEWALK. |
| | |
| | 5. SECTION D-D (SHEET 3 OF 5) CREATE A SWALE ALONG THE |
| | PROPERTY LINE TO PREVENT RUNOFF FROM FLOWING DIRECTLY |
| | ONTO THE ADJACENT PROPERTY. |
| | |
| | 5. CAN THE PROPOSED BUILDING BE MOVED NORTHWARD TO |
| | PROVIDE MOVE GREEN SPACE (RETENTION AREA) FOR |
| | STORMWATER RUNOFF? THE SITE APPEARS TO SLOPE FROM NORTH |
| | TO SOUTH. PER THE FLORIDA BUILDING CODE, RUNOFF IS NOT |
| | TO FLOW ONTO ADJACENT PROPERTIES. |
| | |
| | 6. LABEL EXISTING UTILITIES (DIAMETER/MATERIAL) IN THE |
| | RIGHT OF WAY. |
| | |
| | 7. SHOW MILL AND RESURFACING LIMITS FOR THE PAVEMENT |
| | CUTS IN THE RIGHT OF WAY. |
| | |
| | 8. SHOW UTILITIES ON THE LANDSCAPE PLANS. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP |
| | CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH |
| | THE ENGINEERING PERMIT SUBMITTAL. |
| | |
| | 2. PROVIDE COPY OF SFWMD ERP AND FDEP NPDES |
| | CONSTRUCTION PERMIT BEFORE START OF CONSTRUCTION. |
| | |
| | 3. PROVIDE EROSION AND SEDIMENT CONTROL PLAN WITH THE |
| | ENGINEERING PERMIT SUBMITTAL. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | [email protected] |
| | |
| |