| Plan Review Notes For Project Z23060021 |
| Project Number |
Z23060021 |
|
| Review Stop |
STORM |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2023-07-13 07:39:58 | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO | | | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING | | | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. | | | | | | 1. PROVIDE CALCULATIONS DEMONSTRATING THERE IS | | | SUFFICIENT WATER QUALITY TREATMENT PER SFWMD ERP | | | CRITERIA BEING PROVIDED AND THAT THE POST-DEVELOPMENT | | | PEAK DISCHARGE RATE DOES NOT INCREASE. | | | | | | 2. PROVIDE EROSION AND SEDIMENT CONTROL PLAN WITH THE | | | ENGINEERING PERMIT SUBMITTAL. | | | | | | 3. STORMWATER MANAGEMENT CALCULATIONS WILL BE REVIEWED | | | WITH THE ENGINEERING PERMIT SUBMITTAL. | | | | | | TRACY WARD, PE | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | 561-494-1120 (O) | | | [email protected] | | | |
| |