2023-07-10 12:31:46THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 5/26/23 SUBMITTAL.
  
 1. STAFF COULD NOT LOCATE THE NAVD1988 TO NGVD1929
 CONVERSION EQUATION ON THE SURVEY. PLEASE IDENTIFY THE
 PAGE AND QUADRANT WHERE THE INFORMATION IS LOCATED.
  
 2. PAVING, GRADING AND DRAINAGE PLAN (SHEET C-04)
 A. ADJUST LEADER ARROWS TO POINT TO THE DRAINAGE
 STRUCTURES (#1, #6).
  
 B. PROVIDE VERTICAL CLEARANCE BETWEEN OUTSIDES OF THE
 PROPOSED 15-INCH RCP FROM STRUCTURE #6 AND THE EXISTING
 12-INCH WATER MAIN.
  
 C. LABEL THE WATER MAIN (SIZE, MATERIAL) AND OTHER
 UTILITIES.
  
 D. CONFIRM THE PROPSED GUTTER ALONG THE CLEARWATER PARK
 ROAD WILL HAVE MINIMUM 0.15% (PREFERABLY 0.3%)
 LONGITUDINAL SLOPE TO PREVENT STANDING WATER.
  
 3. CROSS SECTIONS (SHEET C-05)
 A. PROVIDE FLOW ARROW FOR PROPOSED PASSENGER LOADING
 ZONE IN SECTION B-B.
  
 B. PROVIDE THE DIMENSION BETWEEN THE BACK OF VALLEY
 GUTTER AND THE BACK OF THE TYPE D CURB IN SECTION B-B.
  
 4. PAVING, GRADING AND DRAINAGE DETAILS (SHEET C-07)
 A. ACCESSIBLE PARKING SPACE - ADA COMPLIANT DETAIL
 I. LEADER LABELS CALLOUT OUT 4" DBL WHITE AND 6" DBL
 BLUE STRIPES. DOES DBL STAND FOR DOUBLE? SINGLE WHITE
 AND BLUE STRIPES MAY BE APPROPRIATE.
 II. THE ENDS OF THE STIPING SHOULD BE CONNECTED WITH
 12" LONG STRIPE AS INDICATED IN THE CITY OF WEST PALM
 BEACH PARKING STALL SIZES DETAIL.
  
 5. TRAFFIC FEATURES PLAN (SHEET T-1.0) - ANY SIGNAGE
 PROPOSED FOR THE PASSENGER LOADING ZONE?
  
 6. THE EXISTING STORM PIPE UNDER THE SWALE GOES FROM
 THE CATCH BASIN EAST OF STRUCTURE #5 TO THE CATCH BASIN
 IN THE DRIVEWAY SOUTH OF 500 DLEARWATER PARK DRIVE. THE
 DESIGN PLANS FOR THIS PIPE SHOW THE INVERT OF THE SOUTH
 END OF THE PIPE (NORTH INVERT IN THE DRIVEWAY CATCH
 BASIN) AS BEING 4.4 FEET BELOW THE GRATE ELEVATION AND
 THE INVERT OF THE NORTH END OF THE PIPE (SOUTH INVERT
 OF THE SWALE CATCH BASIN) AS BEING 2.73 FEET BELOW THE
 GRATE ELEVATION. THIS STORM PIPE MAY BE IN CONFLICT
 WITH THE PROPOSED SANITARY MH#2.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  
  
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved