| Date |
Text |
| 2023-04-12 18:47:20 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. NO SURVEY WAS PROVIDED. WHEN IT IS PROVIDED, IT |
| | NEEDS TO LIST THE VERTICAL DATUM AND CONVERSION |
| | EQUATION BETWEEN THE VERTICAL DATUM AND NGVD1929, THE |
| | CITY'S OFFICIAL VERTICAL DATUM PER CITY CODE. |
| | |
| | 2. HARDSCAPE PLAN AND CIVIL PLAN DO NOT MATCH. THE |
| | PARKING AREA ON THE CIVIL PLAN IS FURTHER WEST. |
| | |
| | 3. SUGGEST REPLACING THE TYPE F CURB AND GUTTER IN THE |
| | BACK OF THE PARKING AREA WITH TYPE D CURB. THE PARKING |
| | AREA SLOPES TO THE VALLEY GUTTER. |
| | |
| | 4. HARDSCAPE PLAN SHOWS THE VALLEY GUTTER UNDERNEATH |
| | PAVERS BUT THE CIVIL PLANS DO NOT SHOW THIS FOR 7TH |
| | STREET NOR ON THE PLANS FOR N. RAILROAD AVE. |
| | |
| | 5. SHOW ON THE CIVIL PLANS THE LIMITS OF PROPOSED |
| | IMPROVEMENTS TO BE APPROVED WITH THIS SITE PLAN |
| | AMENDMENT APPLICATION. |
| | |
| | 6. SHOW THE SOUTH AND WEST RIGHT OF WAY LINES FOR 7TH |
| | ST ON THE CIVIL PLANS. |
| | |
| | 7. ON THE NORTH SIDE OF 7TH ST, TWO SETS GUTTERS ARE |
| | DRAWN. |
| | |
| | 8. PROVIDE CCTV OF THE EXISTING 18-INCH RCP ON 7TH |
| | STREET IF NOT PREVIOUSLY PROVIDED. |
| | |
| | 9. SHOW THE LOCATION OF THE RAILROAD TIE ON SECTION A |
| | AND SECTION B ON SHEET C2.1. |
| | |
| | 10. NO SIDEWALK SHOWN ON THE SOUTH SIDE OF 7TH ST. IF |
| | NEEDED, CONSIDER PLACING AT THE SOUTH R/W LINE. |
| | |
| | 11. INCLUDE IN THE LEGEND ON SHEET C1.1, THE NET HATCH |
| | PATTERN (SHOWN AT THE WEST END OF 7TH ST.). |
| | |
| | 12. SHOW THE EXISTING STORM MANHOLE AND SEWER MANHOLE |
| | IN THE WEST END OF 7TH ST. |
| | |
| | 13. LABEL 6TH ST. |
| | |
| | 14. ON SHEET L4-100 THE CROSS WALK ACROSS 6TH ST DOES |
| | NOT ALIGN WITH THE ADA MAT ON THE SOUTHWEST CORNER OF |
| | 7TH ST AND 6TH ST. |
| | |
| | 15. ON SECTION A, ARE THE LEAD WALKS THE CURB RAMPS? |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP |
| | CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH |
| | THE ENGINEERING PERMIT SUBMITTAL. |
| | |
| | 2. PROVIDE COPY OF SFWMD ERP PERMIT BEFORE START OF |
| | CONSTRUCTION. |
| | |
| | 3. PROVIDE EROSION AND SEDIMENT CONTROL PLAN WITH THE |
| | ENGINEERING PERMIT SUBMITTAL. |
| | |
| | |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | [email protected] |
| | |
| |