2023-03-02 16:33:20FROM: RAY CARANCI, SENIOR LANDSCAPE PLANNER
 561-822-1462
 PROJECT: FPL COMMAND CENTER DSI Z23020038
 MARCH 2, 2023
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. CORRECT THE MITIGATION CHART ON SHEET LA-1 FOR THE
 FOLLOWING:
 ??? MITIGATION DUE FOR TREES 2301 AND 2300 IS 300 SQ FT
 EACH FOR A CATEGORY 1 TREE LESS THAN 20 FEET IN CANOPY
 DIAMETER.
 ??? TOTAL MITIGATION DUE IS 914 SQ FT.
 ??? IF PAYMENT IN LIEU IS JUSTIFIED, 300 SQ FT CANOPY
 IS $500.00, AND THE TOTAL WOULD BE $1523.33 FOR 901 SQ
 FT. REVISE PLAN TO REFLECT THIS.
  
 2. CORRECT THE JUSTIFICATION STATEMENT TO REMOVE ANY
 REFERENCE TO STAFF APPROVAL PRIOR TO SUBMITTAL OF AN
 APPLICATION FOR REVIEW, AS THIS IS INCORRECT.
  
 3. PROVIDE EXPLAIN IN THE JUSTIFICATION STATEMENT ON
 WHY REPLACEMENT, RELOCATION OR INSTALLATION IT IS NOT
 FEASIBLE DUE TO SITE CONSTRAINTS ALLOWING THE PAYMENT
 IN LIEU OPTION. (SECTION 94-448 E. 2.)
  