| Date |
Text |
| 2023-03-08 09:45:12 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. SURVEY IDENTIFIES THE SITE WITHIN A SPECIAL FLOOD |
| | HAZARD AREA (SFHA) WITH A BASE FLOOD ELEVATION OF 14 FT |
| | NAVD1988. STRUCTURES WITHIN A SFHA ARE TO HAVE A |
| | MINIMUM OF 2 FEET OF FREEBOARD ABOVE THE BASE FLOOD |
| | ELEVATION. |
| | |
| | 2. CONFIRM NPBCID APPROVES THE DEPTH OF THE OUTFALL |
| | INTO THE LAKE SYSTEM. THE PROVIDED DETAIL DRAWING NO. |
| | N-003 SHOWS THE TOP OF THE PIPE IS TO BE 2 FEET BELOW |
| | THE CONTROL ELEVATION OF THE LAKE. |
| | |
| | 3. COMPLETE THE SCALE BAR ON SHEET C-201. |
| | |
| | 4. ADA STRIPING DETAIL SHOULD MATCH CITY LAND |
| | DEVELOPMENT CODE SECTION 94-485. |
| | |
| | |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP |
| | CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH |
| | THE ENGINEERING PERMIT SUBMITTAL. |
| | |
| | 2. PROVIDE COPY OF SFWMD ERP PERMIT BEFORE START OF |
| | CONSTRUCTION. |
| | |
| | 3. PROVIDE COPY OF NPBCID PERMIT BEFORE START OF |
| | CONSTRUCTION. |
| | |
| | 4. PROVIDE EROSION AND SEDIMENT CONTROL PLAN WITH THE |
| | ENGINEERING PERMIT SUBMITTAL. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | [email protected] |
| | |
| | |
| |