2023-02-27 13:48:20Z23010028 TAMARIND ITC RELOCATE 2.27.23
  
 GENERAL:
 O PLEASE RESPOND TO ALL COMMENTS IN WRITING, AND
 INCLUDE PROJECT NAME, ADDRESS AND PERMIT NUMBER
 (Z-XXXXXXXX).
 O THE CITY OF WEST PALM BEACH HAS A NUMBER OF
 REGULATIONS AND PERMIT REQUIREMENTS WHICH DIRECTLY
 AFFECT THE DEVELOPMENT AND INSTALLATION OF WATER AND
 WASTEWATER UTILITIES WITHIN THE CITY. PLEASE SEE
 DEVELOPMENT PERMIT SUBMITTAL REQUIREMENTS AT THE LINK
 BELOW:
 A. HTTPS://WWW.WPB.ORG/HOME/SHOWPUBLISHEDDOCUMENT/3266/
 637521981284930000
 B. THIS AND OTHER RELATED ENGINEERING DOCUMENTS CAN BE
 FOUND HERE:
 HTTPS://WWW.WPB.ORG/GOVERNMENT/ENGINEERING/ENGINEERING-
 FORMS-PERMITS-AND-APPLICATIONS
 C. ALSO SEE: CODE OF ORDINANCES, CITY OF WEST PALM
 BEACH, FLORIDA, CODIFIED THROUGH ORD. NO. 4183-08,
 ADOPTED SEPT. 22, 2008. (SUPPLEMENT NO. 18)
 CHAPTER 90 UTILITIES, ARTICLE I. IN GENERAL,
 SEC. 90-7. POLICY REGARDING EXTENSION OF WATER OR SEWER
 SERVICE FACILITIES OF THE CITY.
 THE WATER AND WASTEWATER SERVICE AGREEMENTS AND THE
 CONSTRUCTION PERMITS ADDRESS RESERVATION OF CAPACITY
 BASED ON USAGE, METER SIZE AND FEES, DESIGN STANDARDS,
 BACKFLOW PREVENTION, FIRE SERVICE AND IRRIGATION.
 O AS OF DECEMBER 20, 2015, THE CITY OF WEST PALM BEACH
 CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED,
 STATING "ALL BACKFLOW DEVICES MUST BE LEAD-FREE". FOR
 MORE INFORMATION, REFER TO THE LINK BELOW:
 A. HTTPS://WWW.WPB.ORG/GOVERNMENT/PUBLIC-UTILITIES/BACK
 FLOW-PREVENTION-AND-CROSS-CONNECTION
 O PLEASE SUBMIT A FORMAL AS-BUILT REQUEST FOR ALL CITY
 OF WEST PALM BEACH-OWNED UTILITIES WITHIN THE PUBLIC
 RIGHT OF WAY FOR THE ENTIRE EXTENT OF THE LIMITS OF
 YOUR PROJECT. IDENTIFY TYPE OF UTILITY, LOCATION, PIPE
 MATERIAL, AGE AND SIZE. PLEASE CONTACT JANICE TARBILL
 IN THE WPB ENGINEERING SERVICES DEPARTMENT AT
 [email protected] OR 561-494-1079 FOR FURTHER
 ASSISTANCE. NOTE THAT FIELD RECORDS ARE FOR INFORMATION
 ONLY. FIELD VERIFY UTILITY LOCATIONS USING FIELD
 SURVEY, POT-HOLING, SOFT DIGS ETC.
 O PROVIDE EXISTING AND PROPOSED PERVIOUS AND IMPERVIOUS
 DATA.
 O PLEASE PROVIDE SEPARATE UTILITY, DRAINAGE, ETC.
 ENGINEERING PLAN SHEETS.
  
 BACKFLOW ASSEMBLY AND METERS:
 O SHOW AND LABEL ANY EXISTING OR PROPOSED WATER
 SERVICES AND WATER METERS, ALONG WITH WHAT IS HAPPENING
 TO THEM (IRRIGATION, WATER FOUNTAINS, ETC.?).
  
 WATER/WASTEWATER PLAN:
 O PROVIDE VERTICAL DATUM AND DATUM CONVERSION
 INFORMATION (NAVD 1988 AND NGVD 1929).
 O SHOW PROJECT ADDRESS ON ALL PLAN SHEETS.
 O PROVIDE LEGEND ON ALL PLAN SHEETS TO INCLUDE
 STREETLIGHT, SIGN POSTS, TRANSFORMER BOXES ETC.
 O PLANS SHALL SHOW EXISTING AND PROPOSED LOCATIONS AND
 DIMENSIONS OF ALL WATER, STORMWATER, AND SANITARY AND
 SEWER LINES AND CLEANOUTS, INCLUDING STUBS TO EACH
 PROPERTY LINE FOR WATER AND SANITARY SEWERS, THE MAKE
 AND MODEL OF ALL VALVES, POTABLE AND IRRIGATION METERS,
 BACKFLOWS, FIRE HYDRANTS AND FDCS, AND OTHER DEVICES TO
 BE INSTALLED ON THE SYSTEM, CATCH BASINS, CULVERTS,
 DITCHES INCLUDING GRADES, PIPES SIZES, MATERIALS,
 ELEVATIONS, ASSUMPTIONS, CALCULATIONS, INVERT
 ELEVATIONS FOR ALL INLETS AND MANHOLES AND PROFILES OF
 SANITARY SEWER LINES.
 O PLAN VIEW SHALL SHOW ALL EXISTING AND PROPOSED
 UNDERGROUND UTILITY LAYOUT, INCLUDING FIBER OPTIC,
 ELECTRIC, GAS, AND CABLEVISION & TELECOMMUNICATION
 FACILITIES INCLUDING PIPE SIZE AND MATERIAL LOCATED IN
 THE RIGHT-OF-WAY.
 O PROVIDE PROFILE AND CLEARANCES BETWEEN WATER, SEWER
 AND STORM LINES PER CITY OF WEST PALM BEACH STANDARD
 DETAIL GN-2 SERIES, AT ALL UTILITY CROSSINGS. PLEASE
 INCLUDE FIBER OPTIC, ELECTRIC, GAS, AND CABLEVISION &
 TELECOMMUNICATION FACILITIES INCLUDING PIPE SIZE AND
 MATERIAL LOCATED IN THE RIGHT-OF-WAY.
  
 FORMAL ENGINEERING REVIEW:
 O FOR FORMAL ENGINEERING SUBMITTAL, SFWMD ERP AND NPDES
 NOI REQUIREMENTS WILL BE ENFORCED.
 - AN NOI IS REQUIRED FOR PROJECTS THAT:
 - 1) DISTURB ONE OF MORE ACRES OF LAND OR DISTURB LESS
 THAN ON ACRE OF LAND BUT ARE PART OF A COMMON PLAN OF
 DEVELOPMENT OR SALE;
 - 2) DISCHARGE STORMWATER TO SURFACE WATERS OF THE
 STATE OR TO SURFACE WATERS OF THE STATE THROUGH A
 MUNICIPAL SEPARATE STORM SEWER SYSTEM (MS4).
 - THE SFWMD ERP CAN BE OBTAINED THROUGH A 10-2 SELF
 CERTIFICATION THROUGH FDEP OR AN ERP APPLICATION
 THROUGH SFWMD. EITHER WAY, THE DEVELOPER/ENGINEER SHALL
 SUBMIT A COPY OF THE ERP PERMIT OR FDEP ACKNOWLEDGEMENT
 OF THE 10-2 CERTIFICATION.
 O FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE
 CALCULATIONS OF PERVIOUS AND IMPERVIOUS AREAS FOR
 PROPOSED IMPROVED AREAS.
  
  