| 2023-02-09 09:47:53 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. THE CITY-S OFFICIAL VERTICAL DATUM PER CITY CODE IS |
| | NGVD1929. THE NAVD1988 VERTICAL DATUM MAY BE USED IF |
| | THE CONVERSION EQUATION BETWEEN NAVD1988 AND NGVD1929 |
| | IS PROVIDED. ON EVERY SHEET WITH ELEVATION INFORMATION, |
| | LIST THE VERTICAL DATUM REFERENCE AND THE CONVERSION |
| | EQUATION TO NGVD1929 IF DIFFERENT FROM NGVD1929. STAFF |
| | COULD NOT FIND THIS INFORMATION ON SHEETS C-8, C-9, AND |
| | C-9A. |
| | |
| | 2. CONSIDER MOVING STRUCTURE D-11 AND/OR STRUCTURE D-10 |
| | TO THE WEST TO PROVIDE HORIZONTAL SEPARATION TO THE |
| | PROPOSED FPL CONDUIT. |
| | |
| | 3. STRUCTURE D-08 WILL BE A BUBBLE UP STRUCTURE. |
| | CONSIDER RAISING THE GRATE ELEVATION TO THE BOTTOM OF |
| | THE RETENTION AREA FOR BETTER ACCESS AND MAINTENANCE. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. MODIFY THE RECENTLY ISSUED SFWMD IF THERE ARE |
| | SUBSTANTIAL CHANGES IN THE IMPERVIOUS/PERVIOUS AREAS |
| | AND/OR STAGE-STORAGE RELATIONSHIP. PROVIDE A COPY OF |
| | SFWMD ERP BEFORE START OF CONSTRUCTION. |
| | |
| | 2. PROVIDE EROSION AND SEDIMENT CONTROL PLAN WITH THE |
| | ENGINEERING PERMIT SUBMITTAL. |
| | |
| | 3. OKEECHOBEE BLVD IS MAINTAINED BY FDOT OR THE PALM |
| | BEACH COUNTY. PROVIDE AGENCY APPROVAL FOR THE |
| | IMPROVEMENTS PROPOSED IN THE RIGHT OF WAY. |
| | |
| | 4. PROVIDE LWDD PERMIT FOR THE PROJECT. |
| | |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | [email protected] |
| | |
| |