Plan Review Notes
Plan Review Notes For Project Z22120027
Project Number Z22120027
Review Stop TRAFFIC
Sequence Number 3
Notes
Date Text
2023-03-06 13:15:04PASS, TRAFFIC COMMENTS #2, #15, #16, #17, AND #18 TO BE
 SATISFIED PRIOR TO ROW PERMIT ISSUANCE.
 SUZANNE BERGLUND
 [email protected]
  
 TRAFFIC COMMENTS
 1) SATISFIED. SETUP A METHODOLOGY MEETING TO DISCUSS
 FURTHER TRAFFIC, PEDESTRIAN CIRCULATION AND PARKING
 ANALYSES
 2) PARTIALLY SATISFIED. PROVIDE COUNTY TPS LETTER, ONCE
 RECEIVED - WILL REQUIRE WITH ROW PERMIT
 [email protected]
 3) SATISFIED. DEPENDING ON THE OUTCOME OF THE ANALYSIS,
 TRANSPORTATION DEMAND MANAGEMENT (TDM) MEASURES MAY BE
 ENCOURAGED
 SITE COMMENTS
 4) SATISFIED. PROVIDE A TRANSPORTATION SPECIFIC SITE
 PLAN FOR THE GROUND FLOOR. SHOWCASING TRANSPORTATION
 RELATED FEATURES (E.G. ROADWAY WIDTHS, DRIVING AISLES,
 PARKING STALLS, SIDEWALK, CURB, GUTTER, DRIVEWAY,
 GATES, CROSSWALKS, VISIBILITY TRIANGLE, CORNER &
 DRIVEWAY SEPARATION DISTANCES, SLOPES, ETC.) PROPERLY
 LABELED AND DIMENSIONED. THE SITE PLAN SHOULD BE NAMED
 T-1.0.
 5) SATISFIED. IN THE T-1.0 SITE PLAN, PLEASE SHOWCASE
 BASIC CURB DETAILS (E.G. DRIVEWAY, CURB CUTS, PAVEMENT
 MARKINGS, PARKING STALLS, ETC.) ON THE OPPOSITE SIDE OF
 THE ROADS SURROUNDING THE PROPOSED DEVELOPMENT. NOTE:
 EVEN THOUGH NO CHANGES TO ROADWAY AND SIDEWALK
 GEOMETRIES ARE PROPOSED, BOTH VEHICULAR AND PEDESTRIAN
 MOVEMENTS MAY BE IMPACTED OR COULD BE IMPROVED. THUS,
 THE NECESSITY OF A SITE PLAN SHOWCASING THE SIDEWALK
 AND ROADWAY AREAS
 6) SATISFIED. PROVIDE A SIGNAGE AND PAVEMENT MARKING
 PLAN. INCLUSIVE OF ALL FEATURES WITHIN THE PROPOSED
 DEVELOPMENT AND ALONG ALL ROADS FRONTING THE SITE. SUCH
 PLAN COULD BE INCLUDED IN THE TRANSPORTATION ONE. NOTE:
 EVEN THOUGH NO CHANGES TO ROADWAY AND SIDEWALK
 GEOMETRIES ARE PROPOSED, BOTH VEHICULAR AND PEDESTRIAN
 MOVEMENTS MAY BE IMPACTED OR COULD BE IMPROVED. THUS,
 THE NECESSITY OF A SITE PLAN SHOWCASING EXISTING
 SIGNAGE AND PAVEMENT MARKINGS ALONG THE SIDEWALK AND
 ROADWAY AREAS
 7) SATISFIED. PROVIDE AUTOTURN ANALYSIS FOR GARBAGE
 TRUCK AND/OR SERVICE VEHICLES DRIVING IN AND OUT OF THE
 PROPOSED DEVELOPMENT WITH VEHICLE DYNAMIC ENVELOPES AND
 WHEEL PATHS CLEARLY DISTINCT AND DEFINED IN DIFFERENT
 COLORS. PROVIDE THE ANALYSIS IN A SEPARATE SHEET.
 8) SATISFIED. IDENTIFY AND DESIGNATE AN EASILY
 ACCESSIBLE MICRO-MOBILITY STATION AREA (MINIMUM 8 X 20
 FEET) AND PROVIDE BASIC ELECTRIFICATION READINESS WITH
 THE FOLLOWING SPECS: A CONDUIT (2-INCH SCHEDULE 40 PVC)
 TO THE POWER SOURCE WITH AN ELECTRICAL PULL BOX (240V /
 10,000W CIRCUIT)
 9) SATISFIED. PROVIDE A PARKING TABLE SHOWCASING THE
 NUMBER OF REQUIRED AND PROVIDED PARKING SPACES,
 INCLUSIVE OF ADA AND BICYCLE ONES
 10) SATISFIED. IN THE PAVEMENT, MARKING & SIGN PLAN,
 PROVIDE A TABLE SHOWCASING THE NUMBER OF EXISTING AND
 PROPOSED ON-STREET PARKING STALLS. PROVIDE THE NUMBER
 OF METERED STALLS THAT ARE BEING REMOVED OR RELOCATED,
 IF ANY
 11) SATISFIED. ARE THERE ANY GATES PROPOSED? IF SO,
 CLEARLY SHOWCASE THE REQUIRED 20 FEET SETBACK DISTANCE
 FROM THE BACK OF THE SIDEWALK
 12) SATISFIED. IS VALET SERVICE PROPOSED? IF SO,
 PROVIDE A THOROUGH OPERATIONAL ANALYSIS. DETAILS OF THE
 ANALYSIS SHOULD BE DISCUSSED DURING THE METHODOLOGY
 MEETING
 13) SATISFIED. ARE THERE ANY BUS OR TRANSIT STOPS BEING
 IMPACTED?
 14) SATISFIED. IS THE PROPOSED DEVELOPMENT IMPACTING AN
 EXISTING BICYCLE FACILITY?
 15) TO BE SATISFIED AT BUILDING PERMIT. PROVIDE A
 CONSTRUCTION MANAGEMENT PLAN. PLEASE REFER TO CITY CODE
 86-246 FOR DETAILS WILL REQUIRE WITH ROW PERMIT
 [email protected]
 16) THE PROPOSED ACCESS TO THE CONSTRUCTION SITE
 THROUGH OLIVE MAY NOT BE FEASIBLE NOR SAFE FOR EXIT
 PURPOSES, DUE TO THE PROPOSED BACK-OUT MANEUVER OF THE
 TRUCKS. THUS, PROVIDE AN ALTERNATIVE MOT THAT HAS
 TRUCKS ENTERING FROM OLIVE AND EXITING ON DIXIE; SUCH
 PLAN WOULD BE IMPLEMENTED IN THE CASE UNSAFE TRAFFIC
 OPERATIONS ARE FOUND DURING CONSTRUCTION WILL REQUIRE
 WITH ROW PERMIT [email protected]
 17) COORDINATE WITH PARKING DEPARTMENT, AND COPY
 ENGINEERING IN THE CORRESPONDENCE, WITH RESPECT TO THE
 IMPACTED PARKING STALLS WITHIN THE 300 BLOCK. PROVIDE A
 NARRATIVE PERTAINING THE USE OF SUCH STALLS IN THE CASE
 THEY ARE BAGGED WILL REQUIRE WITH ROW PERMIT
 [email protected]
 18) COORDINATE AND PROVIDE A NARRATIVE ON HOW LOCAL
 BUSINESSES VEHICULAR ACCESS TO THE BLOCK WILL BE
 HANDLED, SUCH AS JIMMY JOHN DELIVERY DRIVERS OR ANY
 OTHER ENTITY/OPERATIONS BEING SIGNIFICANTLY AND
 NEGATIVELY IMPACTED BY THE ROAD CLOSURE WILL REQUIRE
 WITH ROW PERMIT [email protected]
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER
 561-494-1092
 [email protected]
  