| Plan Review Notes For Project Z22120027 |
| Project Number |
Z22120027 |
|
| Review Stop |
STORM |
| Sequence Number |
2 |
|
| Notes |
| Date |
Text |
| 2023-02-22 12:00:52 | CONDITIONS FOR SITE PLAN APPROVAL: | | | | | | 1. ALL POOL DISCHARGE MUST BE DECHLORINATED PRIOR TO | | | ENTERING THE CITY'S STORMWATER DRAINAGE SYSTEM. NO POOL | | | DISCHARGE MAY ENTER THE CITY'S SANITARY SEWER SYSTEM. | | | | | | 2. NEW AND EXISTING ROOF DRAIN LEADERS ARE TO BE | | | DIRECTLY CONNECTED TO THE DRAINAGE SYSTEM IN THE ALLEY. | | | NO OPEN CONNECTIONS TO THE ALLEY SURFACE. | | | | | | 3. ANY WORK WITHIN THE PUBLIC RIGHT OF WAY (ALLEY, | | | CLEMATIS ST) WILL REQUIRE AN ENGINEERING PERMIT. | | | | | | | | | TRACY WARD, PE | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | 561-494-1120 (O) | | | [email protected] |
| |
Print |
|