| 2022-11-13 09:00:41 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL | | | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION | | | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE | | | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT | | | APPLICATION PROCESSES. | | | | | | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE | | | PLAN APPROVAL: | | | | | | 1. THE CITY'S OFFICIAL VERTICAL DATUM PER CITY CODE IS | | | NGVD1929. THE NAVD1988 VERTICAL DATUM MAY BE USED IF | | | THE CONVERSION EQUATION BETWEEN NAVD1988 AND NGVD1929 | | | IS PROVIDED. LIST THE CONVERSION EQUATION ON THE | | | SURVEY. | | | | | | 2. THE SITE IS WITHIN A SPECIAL FLOOD HAZARD AREA | | | (SFHA) ACCORDING TO THE FEMA FIRM MAP. | | | | | | TRACY WARD, PE | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | 561-494-1120 (O) | | | [email protected] | | | |
| |