| 2022-12-27 08:48:52 | PLEASE PROVIDE WRITTEN RESPONSES TO THE FOLLOWING: | | | -FDC PIPING SHOULD BE CONNECTED TO FIRELINE PIPE RATHER | | | THAN DOMESTIC PLUMBING. | | | -NOTE 11 ON CIVIL PLAN DOES NOT SEEM TO APPLY SINCE | | | GREASE TRAP HAS BEEN ADDED. PLEASE REFER TO RESPONSE | | | LETTER FOR CLARIFICATION. | | | -AT ENGINEERING DEVELOPMENT SUBMITTAL, REMINDER TO | | | FOLLOWUP ON REVIEW COMMENTS 4, 5, 6, 7, 10, 11, AND 13 | | | FROM DEC2022 RESPONSE LETTER. | | | -THERE IS A MONUMENT SIGN PROPOSED IN UTILITY EASEMENT. | | | IF THERE ARE EXISTING UTILITIES AT THAT LOCATION, SIGN | | | MAY NEED TO BE RELOCATED. | | | -RELOCATED FIRE HYDRANT IS LIKELY CONNECTED TO EXISTING | | | FIRELINE WATER SERVICE AND SHOULD REMAIN PRIVATELY | | | OWNED AND DOWNSTREAM OF A DCDA. | | | RESPECTFULLY, | | | MARK HURLEY [email protected] |
| |