| 2022-11-13 09:08:34 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. PORTION OF PROPOSED FORCE MAIN APPEARS TO BE MISSING |
| | ON THE CONCEPTUAL PAVING, DRAINAGE, WATER AND |
| | WASTEWATER PLAN. |
| | |
| | 2. PROVIDE THE FINISHED FLOOR ELEVATION. |
| | |
| | 3. PORTION OF THE SITE IS LOCATED WITHIN A SPECIAL |
| | FLOOD HAZARD AREA (SFHA) WITH A BASE FLOOD ELEVATION |
| | (BFE) OF 12.7 FT NAVD. STRUCTURES WITHIN A SFHA ARE TO |
| | HAVE A MINIMUM TWO FEET OF FREEBOARD ABOVE THE BFE. |
| | |
| | 4. AUSTRALIAN AVENUE IS MAINTAINED BY PALM BEACH |
| | COUNTY. ANY IMPROVEMENTS WITHINTHE R/W TO BE APPROVED |
| | BY THE COUNTY. |
| | |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP |
| | CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH |
| | THE ENGINEERING PERMIT SUBMITTAL. |
| | |
| | 2. PROVIDE COPY OF SFWMD ERP PERMIT MODIFICATION BEFORE |
| | START OF CONSTRUCTION. |
| | |
| | 3. PROVIDE EROSION AND SEDIMENT CONTROL PLAN WITH THE |
| | ENGINEERING PERMIT SUBMITTAL. |
| | |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | [email protected] |
| | |
| |