2022-12-05 14:14:41O PROVIDE VERTICAL DATUM AND DATUM CONVERSION
 INFORMATION (NAVD 1988 AND NGVD 1929).
 O SHOW PROJECT ADDRESS ON ALL PLAN SHEETS.
 O PLANS SHALL SHOW EXISTING AND PROPOSED LOCATIONS AND
 DIMENSIONS OF ALL WATER, STORMWATER, AND SANITARY AND
 SEWER LINES AND CLEANOUTS, INCLUDING STUBS TO EACH
 PROPERTY LINE FOR WATER AND SANITARY SEWERS, THE MAKE
 AND MODEL OF ALL VALVES, POTABLE AND IRRIGATION METERS,
 BACKFLOWS, FIRE HYDRANTS AND FDCS, AND OTHER DEVICES TO
 BE INSTALLED ON THE SYSTEM, CATCH BASINS, CULVERTS,
 DITCHES INCLUDING GRADES, PIPES SIZES, MATERIALS,
 ELEVATIONS, ASSUMPTIONS, CALCULATIONS, INVERT
 ELEVATIONS FOR ALL INLETS AND MANHOLES AND PROFILES OF
 SANITARY SEWER LINES.
 O GATE VALVE BOXES SHALL NOT BE INSTALLED IN CURB OR
 SIDEWALK. ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE
 PROFILE VIEW.
 O PLAN VIEW SHALL SHOW ALL EXISTING AND PROPOSED
 UNDERGROUND UTILITY LAYOUT, INCLUDING FIBER OPTIC,
 ELECTRIC, GAS, AND CABLEVISION & TELECOMMUNICATION
 FACILITIES INCLUDING PIPE SIZE AND MATERIAL LOCATED IN
 THE RIGHT-OF-WAY.
 O PROVIDE PROFILE AND CLEARANCES BETWEEN WATER, SEWER
 AND STORM LINES PER CITY OF WEST PALM BEACH STANDARD
 DETAIL GN-2 SERIES, AT ALL UTILITY CROSSINGS. PLEASE
 INCLUDE FIBER OPTIC, ELECTRIC, GAS, AND CABLEVISION &
 TELECOMMUNICATION FACILITIES INCLUDING PIPE SIZE AND
 MATERIAL LOCATED IN THE RIGHT-OF-WAY.
 O SUBMIT COMPLETED LOS ANALYSIS SUMMARY TABLE DIRECTLY
 TO ENGINEERING (SHEET 33 OF CITY OF WPB DEVELOPMENT
 APPLICATION). PROVIDE CALCULATIONS ON PLANS OF EXISTING
 AND PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE,
 MAXIMUM AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS
 SHALL BE PER FAC 64E-6 FOR SEWER AND PER FAC 64-E.008
 FOR WATER.
 O PROVIDE FIRE FLOW TEST DATA.
 O PROVIDE CCTV VIDEO OF EXISTING SANITARY SEWER
 INFRASTRUCTURE ALONG ENTIRE PROJECT FRONTAGE (CONDITION
 OF SITE PLAN APPROVAL). CLARIFY IF STORMWATER
 CONNECTION TO CITY INFRASTRUCTURE IS BEING PROPOSED;
 CCTV WOULD BE REQUIRED IF SO.
 O CUT AND CAP UTILITIES NOT IN USE AND REMOVE ANY
 ABANDONED UTILITY LINES LARGER THAN 2 INCHES FROM CITY
 ROW.
 O ADD NOTE TO PLANS SPECIFYING CITY???S DOWNSTREAM LIFT
 STATION NUMBER.
 O PROVIDE ONSITE CLEANOUTS NEAR PROPERTY LINE FOR
 PROPOSED SANITARY LATERALS.
 O CALL OUT GRAVITY SEWER WITHIN PROPERTY AS PRIVATE
 O PROVIDE DATA SHOWING HOW CITY'S SEWER SYSTEM IS
 IMPACTED BY NEW INSTALLATIONS
 O PROVIDE DATA RELATING TO THE PROPOSED PRIVATE LIFT
 STATION CAPABILITIES (PROJECT IS WITHIN LIFT STATION 11
 LIMITS)
 O PROVIDE SIZE AND MATERIAL OF PROPOSED FORCE MAIN
 CONNECTION
 O ELABORATE ON MEANS OF TIE-IN TO EXISTING FORCE MAIN
 O DENOTE POINTS OF SERVICE FOR BOTH WATER AND SEWER
 O PROVIDE PROJECT FACT SHEET
  