| Date |
Text |
| 2022-12-05 14:14:41 | O PROVIDE VERTICAL DATUM AND DATUM CONVERSION |
| | INFORMATION (NAVD 1988 AND NGVD 1929). |
| | O SHOW PROJECT ADDRESS ON ALL PLAN SHEETS. |
| | O PLANS SHALL SHOW EXISTING AND PROPOSED LOCATIONS AND |
| | DIMENSIONS OF ALL WATER, STORMWATER, AND SANITARY AND |
| | SEWER LINES AND CLEANOUTS, INCLUDING STUBS TO EACH |
| | PROPERTY LINE FOR WATER AND SANITARY SEWERS, THE MAKE |
| | AND MODEL OF ALL VALVES, POTABLE AND IRRIGATION METERS, |
| | BACKFLOWS, FIRE HYDRANTS AND FDCS, AND OTHER DEVICES TO |
| | BE INSTALLED ON THE SYSTEM, CATCH BASINS, CULVERTS, |
| | DITCHES INCLUDING GRADES, PIPES SIZES, MATERIALS, |
| | ELEVATIONS, ASSUMPTIONS, CALCULATIONS, INVERT |
| | ELEVATIONS FOR ALL INLETS AND MANHOLES AND PROFILES OF |
| | SANITARY SEWER LINES. |
| | O GATE VALVE BOXES SHALL NOT BE INSTALLED IN CURB OR |
| | SIDEWALK. ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE |
| | PROFILE VIEW. |
| | O PLAN VIEW SHALL SHOW ALL EXISTING AND PROPOSED |
| | UNDERGROUND UTILITY LAYOUT, INCLUDING FIBER OPTIC, |
| | ELECTRIC, GAS, AND CABLEVISION & TELECOMMUNICATION |
| | FACILITIES INCLUDING PIPE SIZE AND MATERIAL LOCATED IN |
| | THE RIGHT-OF-WAY. |
| | O PROVIDE PROFILE AND CLEARANCES BETWEEN WATER, SEWER |
| | AND STORM LINES PER CITY OF WEST PALM BEACH STANDARD |
| | DETAIL GN-2 SERIES, AT ALL UTILITY CROSSINGS. PLEASE |
| | INCLUDE FIBER OPTIC, ELECTRIC, GAS, AND CABLEVISION & |
| | TELECOMMUNICATION FACILITIES INCLUDING PIPE SIZE AND |
| | MATERIAL LOCATED IN THE RIGHT-OF-WAY. |
| | O SUBMIT COMPLETED LOS ANALYSIS SUMMARY TABLE DIRECTLY |
| | TO ENGINEERING (SHEET 33 OF CITY OF WPB DEVELOPMENT |
| | APPLICATION). PROVIDE CALCULATIONS ON PLANS OF EXISTING |
| | AND PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE, |
| | MAXIMUM AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS |
| | SHALL BE PER FAC 64E-6 FOR SEWER AND PER FAC 64-E.008 |
| | FOR WATER. |
| | O PROVIDE FIRE FLOW TEST DATA. |
| | O PROVIDE CCTV VIDEO OF EXISTING SANITARY SEWER |
| | INFRASTRUCTURE ALONG ENTIRE PROJECT FRONTAGE (CONDITION |
| | OF SITE PLAN APPROVAL). CLARIFY IF STORMWATER |
| | CONNECTION TO CITY INFRASTRUCTURE IS BEING PROPOSED; |
| | CCTV WOULD BE REQUIRED IF SO. |
| | O CUT AND CAP UTILITIES NOT IN USE AND REMOVE ANY |
| | ABANDONED UTILITY LINES LARGER THAN 2 INCHES FROM CITY |
| | ROW. |
| | O ADD NOTE TO PLANS SPECIFYING CITY???S DOWNSTREAM LIFT |
| | STATION NUMBER. |
| | O PROVIDE ONSITE CLEANOUTS NEAR PROPERTY LINE FOR |
| | PROPOSED SANITARY LATERALS. |
| | O CALL OUT GRAVITY SEWER WITHIN PROPERTY AS PRIVATE |
| | O PROVIDE DATA SHOWING HOW CITY'S SEWER SYSTEM IS |
| | IMPACTED BY NEW INSTALLATIONS |
| | O PROVIDE DATA RELATING TO THE PROPOSED PRIVATE LIFT |
| | STATION CAPABILITIES (PROJECT IS WITHIN LIFT STATION 11 |
| | LIMITS) |
| | O PROVIDE SIZE AND MATERIAL OF PROPOSED FORCE MAIN |
| | CONNECTION |
| | O ELABORATE ON MEANS OF TIE-IN TO EXISTING FORCE MAIN |
| | O DENOTE POINTS OF SERVICE FOR BOTH WATER AND SEWER |
| | O PROVIDE PROJECT FACT SHEET |
| | |
| |
Print |