| 2023-03-23 09:13:05 | THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE |
| | 2/3/2023 SUBMITTAL: |
| | |
| | 1. [SATISFIED] THE CITY???S OFFICIAL VERTICAL DATUM PER |
| | CITY CODE IS NGVD1929. THE NAVD1988 VERTICAL DATUM MAY |
| | BE USED IF THE CONVERSION EQUATION BETWEEN NAVD1988 AND |
| | NGVD1929 IS PROVIDED. PROVIDE THE CONVERSION EQUATION |
| | ON THE SURVEY AND ENGINEERING PLAN. |
| | |
| | 2. [SATISFIED] S. DIXIE HIGHWAY IS MAINTAINED BY FDOT. |
| | ALL IMPROVEMENTS WITHIN THE R/W ARE TO BE APPROVED BY |
| | FDOT. |
| | |
| | 3. [SATISFIED] REMOVE THE CURB CROSSING THE SIDEWALK ON |
| | THE SOUTH SIDE OF THE DRIVEWAY APRON. |
| | |
| | 4. [SATISFIED] PROVIDE A CROSS SECTION AT THE DRIVEWAY |
| | FROM THE CENTERLINE OF S. DIXIE TO THE FIVE FEET INTO |
| | THE EXISTING PARKING LOT. SHOW BREAKPOINTS, R/W, |
| | GUTTERS, WIDTH OF ADA PORTION OF SIDEWALK, GENERAL |
| | SURFACE SLOPES. |
| | |
| | 5. [SATISFIED] PROVIDE ARROWS ON THE CONCEPTUAL |
| | ENGINEERING PLAN SHOWING STOMWATER RUNOFF FLOW |
| | DIRECTION. |
| | |
| | 6. [NOT SATISFIED] IF DUMPSTER DRIVEWAY CAN REMAIN, |
| | REPLACE TYPE F CURB AND GUTTER WITH DROP CURB ACROSS |
| | THE DRIVEWAY. ADDITIONAL COMMENT: SHOW THE PROPOSED |
| | IMPROVEMENTS/CHANGES WITHIN THE PARK PARCEL TO |
| | ACCOMMODATE THIS PROJECT. |
| | |
| | 7. [PARTIALLY SATISFIED] SHOW AND LABEL UTILITIES |
| | (SIZE, MATERIAL) ON THE ENGINEERING PLANS. SHOW ON THE |
| | GRADING AND DRAINAGE PLAN. |
| | |
| | 8. [PARTIALLY SATISFIED] SHOW THE TREES AND THE |
| | EXISTING CATCH BASIN BETWEEN THE PARK'S DRIVEWAY AND |
| | THE NORTH PROPERTY LINE OF THE SITE. |
| | |
| | 9. [PARTIALLY SATISFIED] THERE APPEAR TO BE A UTILITY |
| | GATE VALVE BOX AND A LIGHT POLE IN THE SIDEWALK THAT |
| | ARE NOT SHOWN ON THE SURVEY. ADDITIONAL COMMENT: VALVE |
| | IS NOT SHOWN. |
| | |
| | 10. [SATISFIED] SHOW UTILITIES ON THE LANDSCAPE PLANS. |
| | |
| | 11. [SATISFIED] SHOW WHEEL STOPS FOR THE PARKING SPACES |
| | FACING THE BUILDING. |
| | |
| | |
| | NEW COMMENTS (2/3/2023 SUBMITTAL) |
| | |
| | 12. REVIEW THE PLACEMENT OF THE TRENCH DRAIN ACROSS THE |
| | DRIVEWAY AT THE BACK OF SIDEWALK. IT IS SHOWN AT A HIGH |
| | POINT OF THE DRIVEWAY CROSS SECTION. |
| | |
| | 13. DRIVEWAY APRON TO BE CONCRETE WITHIN THE S. DIXIE |
| | RIGHT OF WAY UNLESS FDOT APPROVES ASPHALT. |
| | |
| | 14. SHOW THE REPLACEMENT OF THE EXISTING DRIVEWAYS AND |
| | DROP CURB WITH TYPE F CURB AND GUTTER AND CONCRETE |
| | SIDEWALK AT MAX. 2% CROSS SLOPE. |
| | |
| | 15. SHOW WHERE THE LIGHT POLE NORTH OF THE EXISTING |
| | DRIVEWAY (AND WITHIN THE PROPOSED DRIVEWAY) WILL BE |
| | LOCATED. TAKE INTO CONSIDERATION THE TREE CANOPY. |
| | |
| | 16. CONSTRUCTING THE DRIVEWAY AND TRENCHING THE WATER |
| | SERVICE LINE SO CLOSE TO THE EXISTING TREES MAY LEAVE |
| | THE TREES UNSTABLE AFTER THE ROOTS ARE PRUNED.. |
| | |
| | 17. REVIEW STRIPING CALLOUTS IN THE PARKING LOT, IN |
| | PARTICULAR THE STOP BAR AND DOUBLE YELLOW STRIPING. |
| | |
| | 18. SECTION A - SHOW THE PROPOSED BACK OF WALK AT THE |
| | EXISTING GRADE AND CREATE A DRIVEWAY TRANSITION BETWEEN |
| | THE FRONT OF SIDEWALK AND THE BACK OF VALLEY GUTTER. |
| | SEE FDOT STANDARD PLAN #522-003. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | [email protected] |
| | |
| | |
| |