2022-10-13 00:01:50THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. INCORPORATE THE IMPROVEMENTS MADE TO NOTTINGHAM
 BLVD. THE R/W MAY NEED TO BE RE-SURVEYED TO SHOW THE
 TYPE F CURB AND GUTTER AND NARROWED ASPHALT PAVEMENT.
 UTILITY AS-BUILT DRAWINGS MAY BE AVAILABLE TO DETERMINE
 IF THE PROPOSED SEWER MAIN CAN CROSS THE NEW WATER
 MAIN.
  
 2. PROVIDE CROSS SECTIONS FOR EACH OF THE DRIVEWAYS.
 EXTEND FROM THE CENTERLINE OF NOTTINGHAM TO 5 FEET PAST
 THE HIGH POINT OF THE DRIVEWAY. LABEL THE R/W NAME, R/W
 LINE, DISTANCES FROM THE R/W TO BACK OF CURB, TO FRONT
 AND BACK OF SIDEWALK, TO CENTERLINE, TO HIGH POINT OF
 DRIVEWAY, ETC. SHOW GENERAL SURFACE SLOPES.
  
 3, PROVIDE CROSS SECTIONS AT EACH OF THE OTHER THREE
 PROPERTY LINES. DEMONSTRATE THAT THE SURFACE RUNOFF
 WILL NOT FLOW ONTO THE ADJACENT PROPERTY.
  
 4. WHAT IS THE PURPOSE OF THE TRENCH DRAINS? THEY
 APPEAR TO BE LOCATED AT THE HIGH POINT OF THE
 DRIVEWAYS.
  
 5. IF TOWNHOUSE UNITS ARE INDIVIDUALLY OWNED
 PROPERTIES, THERE WILL NEED TO BE A HOMEOWNERS
 ASSOCIATION FORMED TO BE RESPONSIBLE FOR MAINTAINING
 THE STORMWATER MANAGEMENT SYSTEM. DRAINAGE EASEMENTS OF
 SUFFICIENT WIDTH WILL BE NEEDED OVER THE DRAINAGE
 SYSTEM TO ALLOW THE EXFILTRATION TRENCHES TO BE
 REPLACED IN THE FUTURE WHEN THEY NO LONGER ARE
 FUNCTIONING AS DESIGNED.
  
 6. LABEL ALL UTILITIES (SIZE, MATERIAL).
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP
 CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH
 THE ENGINEERING PERMIT SUBMITTAL.
  
 2. PROVIDE COPY OF SFWMD ERP PERMIT BEFORE START OF
 CONSTRUCTION.
  
 3. PROVIDE EROSION AND SEDIMENT CONTROL PLAN WITH THE
 ENGINEERING PERMIT SUBMITTAL.
  
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 [email protected]
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved