Plan Review Notes
Plan Review Notes For Project Z22090018
Project Number Z22090018
Review Stop ENG - PPRC
Sequence Number 2
Notes
Date Text
2023-04-11 09:03:36NO RESPONSE LETTER WAS PROVIDED.
  
 O PLEASE RESPOND TO ALL COMMENTS IN WRITING, AND
 INCLUDE PROJECT NAME, ADDRESS AND PERMIT NUMBER
 (Z-XXXXXXXX).
 O PLEASE SUBMIT A FORMAL AS-BUILT REQUEST FOR ALL CITY
 OF WEST PALM BEACH-OWNED UTILITIES WITHIN THE PUBLIC
 RIGHT OF WAY FOR THE ENTIRE EXTENT OF THE LIMITS OF
 YOUR PROJECT. IDENTIFY TYPE OF UTILITY, LOCATION, PIPE
 MATERIAL, AGE AND SIZE. PLEASE CONTACT JANICE TARBILL
 IN THE WPB ENGINEERING SERVICES DEPARTMENT AT
 [email protected] OR 561-494-1079 FOR FURTHER
 ASSISTANCE. NOTE THAT FIELD RECORDS ARE FOR INFORMATION
 ONLY. FIELD VERIFY UTILITY LOCATIONS USING FIELD
 SURVEY, POT-HOLING, SOFT DIGS ETC.
 O PROVIDE EXISTING AND PROPOSED PERVIOUS AND IMPERVIOUS
 DATA.
  
 BACKFLOW ASSEMBLY AND METERS:
 O SHOW AND LABEL ANY EXISTING OR PROPOSED WATER
 SERVICES AND WATER METERS, ALONG WITH WHAT IS HAPPENING
 TO THEM.
 O SHOW EXISTING AND PROPOSED DEDICATED UTILITY
 EASEMENTS TO ALLOW ACCESS FOR CITY PERSONNEL TO
 PROPOSED UTILITY WATER METERS. VERIFY THAT THERE ARE NO
 STRUCTURES WITHIN EASEMENT.
 O PROVIDE ENLARGED VIEW ON PLANS OF PROPOSED LOCATION
 OF WATER METER AND BACKFLOW PREVENTION.
  
 WATER/WASTEWATER PLAN:
 O PLANS SHALL SHOW EXISTING AND PROPOSED LOCATIONS AND
 DIMENSIONS OF ALL WATER, STORMWATER, AND SANITARY AND
 SEWER LINES AND CLEANOUTS, INCLUDING STUBS TO EACH
 PROPERTY LINE FOR WATER AND SANITARY SEWERS, THE MAKE
 AND MODEL OF ALL VALVES, POTABLE AND IRRIGATION METERS,
 BACKFLOWS, FIRE HYDRANTS AND FDCS, AND OTHER DEVICES TO
 BE INSTALLED ON THE SYSTEM, CATCH BASINS, CULVERTS,
 DITCHES INCLUDING GRADES, PIPES SIZES, MATERIALS,
 ELEVATIONS, ASSUMPTIONS, CALCULATIONS, INVERT
 ELEVATIONS FOR ALL INLETS AND MANHOLES AND PROFILES OF
 SANITARY SEWER LINES.
 O GATE VALVE BOXES SHALL NOT BE INSTALLED IN CURB OR
 SIDEWALK. ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE
 PROFILE VIEW.
 O DIRECTION OF FLOW SHALL BE SHOWN ON PLAN VIEW FOR ALL
 SANITARY AND STORM SEWERS.
 O SHOW SLOPE % ON ALL SANITARY LINES AND CALL OUT
 MATERIAL.
 O PLAN VIEW SHALL SHOW ALL EXISTING AND PROPOSED
 UNDERGROUND UTILITY LAYOUT, INCLUDING FIBER OPTIC,
 ELECTRIC, GAS, AND CABLEVISION & TELECOMMUNICATION
 FACILITIES INCLUDING PIPE SIZE AND MATERIAL LOCATED IN
 THE RIGHT-OF-WAY.
 O PROVIDE PROFILE AND CLEARANCES BETWEEN WATER, SEWER
 AND STORM LINES PER CITY OF WEST PALM BEACH STANDARD
 DETAIL GN-2 SERIES, AT ALL UTILITY CROSSINGS. PLEASE
 INCLUDE FIBER OPTIC, ELECTRIC, GAS, AND CABLEVISION &
 TELECOMMUNICATION FACILITIES INCLUDING PIPE SIZE AND
 MATERIAL LOCATED IN THE RIGHT-OF-WAY.
 O SUBMIT COMPLETED LOS ANALYSIS SUMMARY TABLE DIRECTLY
 TO ENGINEERING (SHEET 33 OF CITY OF WPB DEVELOPMENT
 APPLICATION). PROVIDE CALCULATIONS ON PLANS OF EXISTING
 AND PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE,
 MAXIMUM AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS
 SHALL BE PER FAC 64E-6 FOR SEWER AND PER FAC 64-E.008
 FOR WATER.
 O PROVIDE FIRE FLOW TEST DATA.
 O PROVIDE CCTV VIDEO OF EXISTING SANITARY SEWER AND
 STORMWATER INFRASTRUCTURE ALONG ENTIRE PROJECT FRONTAGE
 (CONDITION OF SITE PLAN APPROVAL).
 O CUT AND CAP UTILITIES NOT IN USE AND REMOVE ANY
 ABANDONED UTILITY LINES LARGER THAN 2 INCHES FROM CITY
 ROW.
 O WHEN PROPOSED, WATER MAINS IN CITY RIGHT OF WAY SHALL
 BE MADE OF DUCTILE IRON PIPE (NOT PVC) AND SPECIFY
 PROPOSED LENGTH IN FEET.
 O CHECK TO SEE IF FDEP FORMS FOR PROPOSED SANITARY
 SEWER ARE REQUIRED.
 O PROVIDE CLEANOUTS FOR PROPOSED SANITARY LINE ONSITE
 JUST INSIDE PROPERTY LINE, AT JOINTS AND EVERY 75 FEET.
 O ADD NOTE TO PLANS SPECIFYING CITY???S DOWNSTREAM LIFT
 STATION NUMBER.
 O PROVIDE ONSITE CLEANOUTS NEAR PROPERTY LINE FOR
 PROPOSED SANITARY LATERALS.
  
  
  