Plan Review Notes For Project Z22090016
Project Number Z22090016
Review Stop AIPP
Sequence Number 1
Notes
Date Text
2022-10-11 14:18:00PUBLIC ART REQUIREMENT:
  
 TOTAL CONSTRUCTION COSTS OF THIS DEVELOPMENT ARE OVER
 $500,000 IT IS SUBJECT TO THE PUBLIC ART REQUIREMENT AS
 PER CITY ORDINANCE.
  
 OPTION 1: INSTALL ARTWORK ON THE DEVELOPMENT SITE
 VALUED IN AN AMOUNT NOT LESS THAN ONE PERCENT OF THE
 TOTAL CONSTRUCTION COSTS.
  
 FOR SITE PLAN APPROVAL PUBLIC ART NEEDS TO BE
 IDENTIFIED ON ALL THE SITE PLANS.
  
 OPTION 2: CONTRIBUTE AN AMOUNT EQUAL TO 75 PERCENT OF
 ONE PERCENT OF THE TOTAL CONSTRUCTION COSTS FOR DEPOSIT
 TO THE PUBLIC ART ACCOUNT.
  
 FOR EITHER OPTION A COMPLETED PUBLIC ART ASSESSMENT
 APPLICATION ALONG WITH EITHER THE ESCROW OF THE 1% OR
 IF CHOSEN OPTION 2 CONTRIBUTION INTO THE PUBLIC ART
 FUND IS REQUIRED AT TIME OF BUILDING PERMIT SUBMITTAL.
  
 DUE TO LACK OF PUBLICLY ACCESSIBLE LOCATIONS TO MEET
 THE PUBLIC ART REQUIREMENT IT IS RECOMMENDED THAT THE
 DEVELOPER CONTRIBUTE INTO THE PUBLIC ART FUND FOR THIS
 PROJECT.
  
 CONTACT SYBILLE WELTER, ADMINISTRATOR OF PUBLIC ART &
 CULTURE AT [email protected] WITH FURTHER QUESTIONS.