| Date |
Text |
| 2022-10-12 23:54:24 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. LABEL ALL UTILITIES (SIZE, MATERIAL). |
| | |
| | 2. REVIEW SFWMD ERP APPLICATION 140917-4 REGARDING THE |
| | MANHOLE SHOWN WITHIN THE RAILROAD TRACKS AND THE PIPES |
| | CONNECTED TO THE MANHOLE. THE DEMOLITION PLAN FOR THE |
| | BRIGHTLINE STATION PERMIT CALLED FOR THESE TO BE |
| | REMOVED. |
| | |
| | 3. THERE MAY BE A STORM PIPE CONNECTED TO THE NORTH |
| | SIDE OF THE CATCH BASIN ON THE NORTH SIDE OF FERN ST. |
| | WEST OF THE F.E.C. R/W. |
| | |
| | 4. IDENTIFY WHERE THE BRICKSLOT TRENCH DRAINS WILL BE |
| | CONSTRUCTED. |
| | |
| | 5. EXPLAIN HOW STORM WATER QUALITY TREATMENT AND PEAK |
| | ATTENUATION WILL BE PROVIDED. |
| | |
| | 6. EXPLAIN WHAT THE WEST PIPE CONNECTED TO STRUCTURE |
| | YD-1 IS FOR. |
| | |
| | 7. IS THE SOLID HATCHING IN THE NORTH-SOUTH ALLEY ALONG |
| | THE WEST PROPERTY LINE NECESSARY? IT IS COVERING UP |
| | MANY UTILITY LINES IN THE ALLEY. |
| | |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP |
| | CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH |
| | THE ENGINEERING PERMIT SUBMITTAL. |
| | |
| | 2. PROVIDE COPY OF SFWMD ERP PERMIT BEFORE START OF |
| | CONSTRUCTION. |
| | |
| | 3. PROVIDE EROSION AND SEDIMENT CONTROL PLAN WITH THE |
| | ENGINEERING PERMIT SUBMITTAL. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | [email protected] |
| | |
| |