Plan Review Notes
Plan Review Notes For Project Z22080024
Project Number Z22080024
Review Stop STORM
Sequence Number 1
Notes
Date Text
2022-09-08 13:07:23THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. FLORIDA MANGO IS MAINTAINED BY PALM BEACH COUNTY.
  
 2. THE CITY?S OFFICIAL VERTICAL DATUM IS NGVD1929. THE
 CITY HAS ALLOWED THE USE OF NAVD1988 AS LONG AS THE
 CONVERSION EQUATION TO NGVD1929 AT THE PROJECT LOCATION
 IS PROVIDED. PROVIDE THE VERTICAL DATUM CONVERSION TO
 NGVD1929 ON THE SURVEY. PROVIDE VERTICAL DATUM
 REFERENCE AND CONVERSION EQUATION ON EVERY ENGINEERING
 SHEET WITH ELEVATION INFORMATION.
  
 3. SITE IS WITHIN A SPECIAL FLOOD HAZARD AREA.
 STRUCTURES ARE TO HAVE MINIMUM TWO FEET OF FREEBOARD
 ABOVE THE BASE FLOOD ELEVATION.
  
 4. THE CITY DOES NOT ALLOW THE USE OF BLEEDERS WITHIN
 THE WEIR WITH EXFILTRATION TRENCH SYSTEMS.
  
 5. PROVIDE CROSS SECTIONS FOR ALL SIDES OF THE PROPERTY
 FROM 10 FEET OUTSIDE THE PROPERTY TO THE BUILDING FACE.
 SHOW AND LABEL SURFACE FEATURES, GRADE BREAKS, PROPERTY
 LINE, SURFACE SLOPES, STREET NAMES, ETC.
  
 6. PROVIDE CROSS SECTIONS AT THE DRIVEWAYS FROM
 CENTERLINE OF THE ROAD TO 5 FEET PAST THE HIGH POINT.
 SHOW AND LABEL SURFACE FEATURES, GRADE BREAKS, RIGHT OF
 WAY LINE, STREET NAME, SURFACE SLOPES, ETC.
  
 7. THE GRATE ELEVATION OF STRUCTURES CB#1 AND CB#8 ARE
 AT OR BARELY HIGHER THAN THE WEIR ELEVATION. THERE WILL
 BE PONDING AROUND THESE STRUCTURES WHENEVER THERE IS
 DISCHARGE INTO THE CANAL.
  
 8. LABEL EXISTING UTILITIES (SIZE, MATERIAL).
  
 9. SHOW MILL AND RESURFACING LIMITS.
  
 10. SHOW THE EXISTING CURB AND GUTTER ALONG FLORIDA
 MANGO. SHOW DROP CURB ACROSS THE PROPOSED DRIVEWAYS.
  
 11. CAN SOUTH DRIVEWAY BE ADJUSTED TO AVOID THE
 EXISTING CATCH BASIN?
  
 12. DRIVEWAY APRONS SHOULD BE CONCRETE WITHIN THE RIGHT
 OF WAY.
  
 13. SHOW AND LABEL AND PERIMETER BERM THAT WILL BE
 NEEDED.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP
 CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH
 THE ENGINEERING PERMIT SUBMITTAL.
  
 2. PROVIDE COPY OF SFWMD ERP PERMIT BEFORE START OF
 CONSTRUCTION.
  
 3. PROVIDE EROSION AND SEDIMENT CONTROL PLAN WITH THE
 ENGINEERING PERMIT SUBMITTAL.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]
  