| 2022-09-03 08:41:42 | PLEASE PROVIDE WRITTEN RESPONSES TO THE FOLLOWING: |
| | -DOMESTIC 8 INCH METER WOULD NEED TO BE ABOVE-GROUND |
| | REFERENCING STANDARD DETAIL WS3. ADD WORDING |
| | ABOVE-GROUND TO LABEL ALONG WITH STANDARD DETAIL |
| | REFERENCE. |
| | -PROPOSED 8 INCH METER CANNOT BE OBSTRUCTED BY |
| | BUILDING, WALL, OR FENCE AND MUST BE NO GREATER THAN 15 |
| | FEET FROM STREET TO ALLOW REPLACEMENT WITH CITY CRANE |
| | TRUCK. |
| | -CITY DOES NOT STOCK 8 INCH METERS AND WOULD HAVE TO BE |
| | ORDERED AFTER FORMAL QUOTE IS PAID AND UTILITY BILLING |
| | ACCOUNTS SETUP. MAY EXPERIENCE LONG LEAD TIMES TILL |
| | METER IS RECEIVED AFTER ORDER, AND PROJECT SHOULD ALSO |
| | ANTICIPATE THE DELAY BETWEEN WATER SERVICE BUILDOUT AND |
| | METER INSTALLATION. |
| | -ADD SYMBOL FOR WATER METER ON LEGEND AND SHOW THEM ON |
| | PLANS. RECOMMEND SHOWING METERS AT MORE REALISTIC SCALE |
| | AS THE LARGER METERS AND BACKFLOWS CAN HAVE INCREASED |
| | FOOTPRINT. |
| | -SHEET C5. PROPOSED FIRELINE CANNOT BE UNDER OR NEAR |
| | EXISTING TRAFFIC SIGNAL POLE. |
| | -ENSURE THAT PROPOSED FIRELINE BACKFLOW ASSEMBLY |
| | LOCATIONS ARE NFPA COMPLIANT. |
| | -SHEET C7 SHOWS EXISTING UTILITY POLE AND GUY WIRE IN |
| | MIDDLE OF PROPOSED DRIVEWAY. |
| | -SHEET C6: FAR NORTHEAST DRIVEWAY FLARE SEEMS TO BE |
| | EXTENDING ONTO NEIGHBORING PROPERTY; EXISTING LIGHT |
| | POLE IN PROPOSED DRIVEWAY ON EAST SIDE; DIGITAL SIGN |
| | AND SEAL NOT READABLE. |
| | -IF FDC ARE NEEDED OR REQUIRED, SHOW AND LABEL ON PLANS |
| | AND ENSURE ACCEPTABLE DISTANCE FROM FIRE HYDRANT. |
| | -SHEET C6. NORTHWEST DOMESTIC WATER SERVICE SHOWS |
| | CONFLICT WITH SOME KIND OF UTILITY IN SIDEWALK. |
| | -ENGINEERING PLANS AND SURVEY SHOW GAS MARKER ON WEST |
| | SIDE OF PROJECT. HISTORIC PICTURES ALSO SHOW GAS LINE |
| | LOCATES. SHOW BETTER ALL EXISTING GAS UTILITIES, AND IF |
| | REMAINING ENSURE NO CONFLICT BETWEEN PROJECT AND GAS |
| | UTILITIES. |
| | -CALLOUT PROPOSED SANITARY SEWER MANHOLES AND |
| | CLEANOUTS. |
| | -SUBMIT SEPARATE LANDSCAPING SHEET THAT SHOWS ALL TREES |
| | AND UTILITIES. ENSURE THAT UTILITIES AND TREES HAVE |
| | APPROPRIATE CLEARANCE DISTANCE. |
| | -CONSIDER PARALLEL/DUAL DOMESTIC BACKFLOW ASSEMBLIES TO |
| | MINIMIZE WATER OUTAGES DURING BACKFLOW MAINTENANCE. |
| | -VERIFY PRIVATE FIRE SYSTEM WILL NOT HAVE ANY AUXILIARY |
| | WATER SUPPLIES CONNECTED TO IT SUCH AS WELLS. |
| | -WILL ACCESS EASEMENT INCLUDE USE OF BRIDGE AND |
| | TERRACES? |
| | -A2.1 SHOWS PROPOSED 4TH ST ALLEY AS ONE WAY. ON C7 ARE |
| | ANY ONE WAY OR DO NOT ENTER SIGNS NEEDED? |
| | -ON PGD PLAN NEAR THE NORTH PROPERTY LINE, IS THE AREA |
| | NEAR THE GENERATOR AND FPL ROOM DOORS CONCRETE? IF SO, |
| | ADD CORRECT CONCRETE SHADING. |
| | -A5.1 SHOWS AREA OF PROPOSED SOUTHWEST FIRELINE |
| | BACKFLOW ASSEMBLY TO BE ELEVATED. CITY UTILITY WORKERS |
| | MUST HAVE SAFE AND EASY ACCESS TO ALL WATER METERS |
| | INCLUDING FIRELINE DETECTOR METERS. ON WATER PLAN ADD |
| | SPOT ELEVATIONS AROUND THAT AREA SHOWING HEIGHT |
| | DIFFERENCE. |
| | -ADD WATER AND SEWER DEMAND CALCULATIONS TO SHEET C6. |
| | RESPECTFULLY, |
| | MARK HURLEY [email protected] |
| |