| 2022-07-14 08:59:38 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. THE CITY?S OFFICIAL VERTICAL DATUM IS NGVD1929. THE |
| | CITY HAS ALLOWED THE USE OF NAVD1988 AS LONG AS THE |
| | CONVERSION EQUATION TO NGVD1929 AT THE PROJECT LOCATION |
| | IS PROVIDED. PROVIDE VERTICAL DATUM REFERENCE AND |
| | CONVERSION TO NGVD1929 ON EVERY SHEET WITH ELEVATION |
| | INFORMATION (NEEDED ON SHEETS SP-1 AND SP-2). |
| | |
| | 2. WILL BOLLARDS BE LOCATED ALONG THE BACK OF THE |
| | FLUSHED CONCRETE CURB EAST OF THE NEW COMMUNITY CENTER? |
| | |
| | 3. REPLACE ANY VCP DRAINAGE PIPES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP |
| | CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH |
| | THE ENGINEERING PERMIT SUBMITTAL. |
| | |
| | 2. PROVIDE COPY OF SFWMD ERP PERMIT MODIFICATION BEFORE |
| | START OF CONSTRUCTION. |
| | |
| | 3. PROVIDE EROSION AND SEDIMENT CONTROL PLAN WITH THE |
| | ENGINEERING PERMIT SUBMITTAL. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | 561-351-0510 (M) |
| | [email protected] |
| | |
| |