Plan Review Notes
Plan Review Notes For Project Z22050022
Project Number Z22050022
Review Stop STORM
Sequence Number 1
Notes
Date Text
2022-07-14 12:49:30THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. THE CITY?S OFFICIAL VERTICAL DATUM IS NGVD1929. THE
 CITY HAS ALLOWED THE USE OF NAVD1988 AS LONG AS THE
 CONVERSION EQUATION TO NGVD1929 AT THE PROJECT LOCATION
 IS PROVIDED. PROVIDE VERTICAL DATUM CONVERSION TO
 NGVD1929 ON THE SURVEY.
  
 2. MOVE THE CONSTRUCTION EXIT ON THE EROSION CONTROL
 PLAN OUT OF THE RIGHT OF WAY.
  
 3. PROVIDE CONTROL STRUCTURES FOR THE EXFILTRATION
 TRENCH SYSTEMS WITHIN THE PROJECT SITE. THE CITY DOES
 NOT ALLOW THE USE OF BLEEDERS WITH EXFILTRATION
 SYSTEMS.
  
 4. INDICATE HOW THE SURFACE DRAINAGE ON FERN STREET
 WILL BE ACCOMMODATED WITH THE NEW CURBING.
  
 5. EXPLAIN WHAT IS DEPICTED BY THE HATCHING ENCROACHING
 INTO THE FERN STREET R/W AT THE RESIDENTIAL USER
 BUILDING ENTRY/EXIT.
  
 6. PROVIDE CROSS SECTIONS FROM FACE OF BUILDING TO THE
 CENTERLINE OF EACH STREET. SHOW SURFACE FEATURES, GRADE
 BREAKS, GENERAL SURFACE SLOPES, MAXIMUM CROSS SLOPE
 PERCENTAGES, FINISHED FLOOR ELEVATION, RIGHT OF WAY
 LINE, DIMENSIONS FROM BACK OF CURB TO R/W, OFFSETS FROM
 R/W TO BUILDING FACE, ETC.
  
 7. PROVIDE CROSS SECTION FOR EACH DRIVEWAY FROM NEAREST
 INSIDE EDGE OF TRAVEL LANE TO FIVE FEET BEYOND THE HIGH
 POINT IN THE INTERIOR OF THE SITE. SHOW SURFACE
 FEATURES, SLOPES, BREAK POINTS, ETC.
  
 8. CONSIDER LOW IMPACT DEVELOPMENT DRAINAGE FACILITIES.
  
 9. PROVIDE THE FINISHED FLOOR ELEVATIONS.
  
 10. PROVIDE PROPOSED GRADES ON THE PAVING AND GRADING
 PLAN.
  
 11. SHOW MILL AND OVERLAY LIMITS FOR TRENCHING WITHIN
 THE ROAD RIGHT OF WAY.
  
 12. SHOW THE LOCATION FOR ADA TRUNCATED DOME MATS.
  
 13. SHOW DROP CURBS AT SIDEWALK CONNECTIONS TO
 DRIVEWAYS.
  
 14. ON SHEET A0.09 IT APPEARS THE BUILDING ENCROACHES
 THE FERN STREET R/W ON SECTION 3, LEVELS 3-6 PODIUM
 FLOOR PLAN.
  
 15. IT APPEARS THERE IS SANITARY SEWER PROPOSED ON LOT
 1. DOES THE PROPERTY OWNER APPROVE OF THIS AND OTHER
 IMPROVEMENTS ON LOT 1.
  
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP
 CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH
 THE ENGINEERING PERMIT SUBMITTAL.
  
 2. PROVIDE COPY OF SFWMD ERP PERMIT BEFORE START OF
 CONSTRUCTION.
  
 3. PROVIDE EROSION AND SEDIMENT CONTROL PLAN WITH THE
 ENGINEERING PERMIT SUBMITTAL.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)