| 2022-06-08 21:22:53 | TRAFFIC COMMENTS |
| | 1) GIVEN THE SENSITIVE LOCATION OF THE PROPOSED |
| | DEVELOPMENT, A METHODOLOGY MEETING SHALL BE SCHEDULED |
| | FOR A COMPREHENSIVE TRAFFIC STUDY |
| | 2) PROVIDE A THOROUGH VALET SERVICE/QUEUE ANALYSIS |
| | 3) PROVIDE COUNTY TPS LETTER |
| | 4) PROVIDE FDOT D4 ACCESS MANAGEMENT LETTER |
| | |
| | SITE COMMENTS |
| | 5) ON THE SITE PLAN, PLEASE SHOWCASE BASIC CURB DETAILS |
| | (I.E. DRIVEWAY AND PARKING STALLS) ON THE OPPOSITE SIDE |
| | OF THE ROADS SURROUNDING THE PROPOSED DEVELOPMENT. |
| | PLEASE PROVIDE DOCUMENT NAME AND SHEET NUMBER |
| | SHOWCASING SUCH FEATURES. |
| | 6) SHEET C-102, RIGHT DRAWING. WB-40 MANEUVERING SHOWS |
| | ENCROACHMENT WITH THE INTERNAL SIDEWALK BY THE DROP-OFF |
| | AREA. IS THAT PORTION OF THE WALKWAY CURB LESS? |
| | 7) SHEET A1.04 TO 06, PROVIDE AND CLEARLY MARK |
| | TURNAROUND SPACE AT THE SOUTHERN DEAD-END |
| | 8) SHEET A1.07, PROVIDE AND CLEARLY MARK TURNAROUND |
| | SPACE AT THE SOUTHERN AND NORTHERN DEAD-ENDS |
| | 9) IDENTIFY AND DESIGNATE AN EASILY ACCESSIBLE |
| | MICRO-MOBILITY STATION AREA (MINIMUM 8 X 20 FEET) AND |
| | PROVIDE BASIC ELECTRIFICATION READINESS. FOR THE LATTER |
| | ITEM, MORE SPECIFICALLY: A CONDUIT (2? SCHEDULE 40 PVC) |
| | TO THE POWER SOURCE WITH AN ELECTRICAL PULL BOX (240V ? |
| | 10,000W CIRCUIT). PLEASE PROVIDE DOCUMENT NAME AND |
| | SHEET NUMBER SHOWCASING SUCH FEATURE. |
| | 10) PROVIDE NUMBER AND LOCATION OF BICYCLE PARKING |
| | 11) A MINIMUM OF 2 ADA VAN ACCESSIBLE PARKING SPACES |
| | MUST BE PROVIDED, PLEASE INDICATE THOSE STALLS |
| | 12) PROVIDE 10 FEET WIDE SIDEWALKS AROUND THE PROPOSED |
| | DEVELOPMENT |
| | 13) REMOVE THE PARALLEL PARKING STALLS ON DIXIE |
| | 14) MAKE THE NORTHERN DRIVEWAY ON LAKEVIEW AVE EXIT |
| | ONLY |
| | 15) CONSIDER MAKING THE SOUTHERN DRIVEWAY ON OKEECHOBEE |
| | BLVD ENTRY ONLY |
| | |
| | VALERIO ORICCHIO |
| | CITY TRANSPORTATION ENGINEER |
| | 561-494-1092 |
| | [email protected] |
| | |
| |