Plan Review Notes
Plan Review Notes For Project Z22040026
Project Number Z22040026
Review Stop STORM
Sequence Number 3
Notes
Date Text
2022-09-29 16:35:56THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 9/16/22 SUBMITTAL. PREVIOUSLY SATISFIED COMMENTS ARE
 NOT INCLUDED. RESPONSES TO THE 7/15/22 COMMENTS WERE
 NOT FOUND IN THE 9/16/22 SUBMTITAL.
  
 2. [PARTIALLY SATISFIED] SHOWING FLOATING TURBIDITY
 CURTAINS AROUND THE OUTFALL(S) IN THE CANAL TO THE
 NORTH OF THE SITE ON SHEET C-010. ADDITIONAL COMMENT:
 INCLUDE FLOATING TURBIDITY CURTAIN AROUND THE OUTFALL
 PIPE FROM STRUCTURE IN THE ALLEY, APPROXIMATELY 125
 FEET EAST OF THE OUTFALL SHOWN ON THE OUTFALL SWPP PLAN
 VIEW ON SHEET C-010. THERE ARE TWO OUTFALL PIPES INTO
 THE CANAL THAT WILL NEED FLOATING TURBIDITY BARRIERS
 AROUND THEM. THIS CAN BE ADDRESSED WITH THE ENGINEERING
 PERMIT SUBMITTAL.
  
 6. [SATISFIED] THE CITY'S OFFICIAL VERTICAL DATUM IS
 NGVD1929. THE CITY HAS ALLOWED THE USE OF NAVD1988 AS
 LONG AS THE CONVERSION EQUATION TO NGVD1929 AT THE
 PROJECT LOCATION IS PROVIDED. PROVIDE THE CONVERSION TO
 NGVD1929 ON THE SURVEY.
  
 9. [NOT SATISFIED] PROVIDE THE AGREEMENT OR EASEMENT
 FOR THE DRAINAGE FROM THE PROPERTY TO THE WEST TO
 CONNECT TO THE ONSITE DRAINAGE SYSTEM. ADDITIONAL
 COMMENT - THE EASEMENT AGREEMENT (ORB13408 PG 1500
 COVERS THE AREA EAST OF THE COMMON PARCEL LINE BEING
 USED BY THE WEST PROPERTY OWNER (EASEMENT PARCEL).
 THERE ARE DRAINAGE FACILITIES ON THE WEST PROPERTY
 RECEIVING STORMWATER RUNOFF FROM AREAS OUTSIDE THE
 EASEMENT PARCEL THAT CONVEY RUNOFF THROUGH THE EAST
 PROPERTIES DRAINAGE SYSTEM. AS FAR AS STAFF CAN
 DISCERN, THE 1.74 ACRE SITE TO THE WEST DOES NOT HAVE A
 SFWMD ERP. THE DRY DETENTION AREAS AND UNDERDRAINS ON
 THE EAST PROPERTY WERE SIZED FOR THE AREA OF THE EAST
 PROPERTY ONLY.
  
 NEW COMMENTS (7/15/22 SUBMITTAL)
  
 13. [SATISFIED] FOR ENGINEERING PERMIT SUBMITTAL,
 INCLUDE 'DRAINAGE' IN THE SHEET TITLE OF THE PAVING AND
 GRADING PLAN (SHEET C-200).
  
 14. [SATISFIED] REVIEW AND UPDATE THE NOTES ON THE
 PAVING AND GRADING PLAN SHEET. NOTES REFERENCE NGVD
 1929, PBC TYPICAL T-P-10-001, FDOT STANDARD INDEX
 NUMBERS, ETC. ALL ELEVATION INFORMATION SHOULD BE
 REFERENCED TO NAVD1988, INCLUDING THE STORM DRAINAGE
 STRUCTURE TABLE.
  
 15. [NOT SATISFIED] FOR ENGINEERING PERMIT SUBMITTAL,
 UPDATE THE CITY'S STANDARD DETAILS TO THE LATEST
 VERSION.
  
 16. [PARTIALLY SATISFIED - DO NOT INCLUDE THE SIDEWALK
 AREA IN THE HATCH AREA] SHOW MILL AND RESURFACING
 LIMITS ON OKEECHOBEE BLVD.
  
 17. [NOT SATISFIED] SHOW THE EXISTING PIPE CONNECTED ON
 THE NORTH SIDE OF THE CATCH BASIN IN THE ALLEY NORTH OF
 THE DRY DETENTION AREA.
  
 NEW COMMENTS (9/16/22 SUBMITTAL):
 18. CHECK THE VERTICAL SCALE FOR THE CROSS SECTIONS ON
 SHEET C-202.
  
 19, REVIEW THE EXISTING GRADE LINE FOR SECTION E-E. IT
 APPEARS THERE IS A DIP IN THE EXISTING DRIVEWAY.
  
 20. ON SHEET C-106, FOR THE 60-DEGREE STANDARD PARKING
 STALL DETAIL, THE 12-INCH LONG STRIPE CONNECTING THE
 PARALLEL STRIPES CAN BE PARALLEL TO THE TRAVEL LANE,
 THUS CREATING 60-DEGREE AND 30-DEGREE ANGLES WITH THE
 PARALLEL STRIPES.
  
 21. WILL THERE BE A WHEEL STOP OR CURB AT THE BACK OF
 THE 90-DEGREE SMALL CAR PARKING STALL?
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]
  