| 2022-05-12 12:51:02 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. ARE THE FDOT STANDARD NOTES ON SHEET C-001 CURRENT? |
| | THERE IS NO MENTION OF THE STANDARD PLANS THAT REPLACED |
| | THE STANDARD INDEX AND NOTE 18 REFERENCES WEST |
| | MELBOURNE OPERATIONS OFFICE. |
| | |
| | 2. SHOWING FLOATING TURBIDITY CURTAINS AROUND THE |
| | OUTFALL(S) IN THE CANAL TO THE NORTH OF THE SITE ON |
| | SHEET C-010. |
| | |
| | 3. INLET PROTECTION MAY BE NEEDED FOR THE DRAINAGE |
| | STRUCTURES WITHIN CONGRESS AVE. AND NEXT TO AND IN THE |
| | ALLEY. |
| | |
| | 4. PROVIDE FDOT APPROVAL FOR THE CONSTRUCTION |
| | ENTRANCE/EXIT ON OKEECHOBEE BLVD. |
| | |
| | 5. LIST THE VERTICAL DATUM ON EVERY SHEET WITH |
| | ELEVATION INFORMATION AND PROVIDE THE CONVERSION |
| | EQUATION TO NGVD1929. |
| | |
| | 6. THE CITY?S OFFICIAL VERTICAL DATUM IS NGVD1929. THE |
| | CITY HAS ALLOWED THE USE OF NAVD1988 AS LONG AS THE |
| | CONVERSION EQUATION TO NGVD1929 AT THE PROJECT LOCATION |
| | IS PROVIDED. PROVIDE THE CONVERSION TO NGVD1929 ON THE |
| | SURVEY. |
| | |
| | 7. PROVIDE FINISHED FLOOR ELEVATIONS FOR THE EXISTING |
| | AND PROPOSED BUILDINGS. |
| | |
| | 8. INDICATE WHERE THE DRAINAGE PICKED UP BY STRUCTURES |
| | DS-01 THROUGH DS-08 AND DS-15 WILL DISCHARGE TO. THERE |
| | MAY BE A SOUTH PIPE CONNECTED TO STRUCTURE DS-13 THAT |
| | CONNECTS TO A MANHOLE UNDER THE CARPORT AREA. FROM THIS |
| | MANHOLE THERE MAY BE PIPES GOING TO THE WEST AND SOUTH. |
| | PERHAPS STRUCTURE DS-04 COULD BE INSTALLED OVER THE |
| | WEST PIPE IF THE MANHOLE UNDER THE CARPORT IS TO REMAIN |
| | ALONG WITH THE WEST AND NORTH PIPES CONNECTED TO THIS |
| | MANHOLE. |
| | |
| | 9. PROVIDE THE AGREEMENT OR EASEMENT FOR THE DRAINAGE |
| | FROM THE PROPERTY TO THE WEST TO CONNECT TO THE ONSITE |
| | DRAINAGE SYSTEM. |
| | |
| | 10. SHOW EXISTING AND PROPOSED UTILITIES ON THE |
| | LANDSCAPE PLANS. |
| | |
| | 11. OKEECHOBEE BLVD IS MAINTAINED BY FDOT. CONGRESS AVE |
| | IS MAINTAINED BY PALM BEACH COUNTY. PERMITS MAY BE |
| | REQUIRED FROM THE AGENCIES IF WORK IS PROPOSED WITHIN |
| | THEIR RESPECTIVE RIGHT OF WAY. |
| | |
| | 12. PROVIDE SPOT GRADES AND/OR SHOW FLOW ARROWS |
| | INDICATING HOW EACH AREA WILL BE SLOPED FOR STORMWATER |
| | RUNOFF. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP |
| | CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH |
| | THE ENGINEERING PERMIT SUBMITTAL. |
| | |
| | 2. PROVIDE COPY OF SFWMD ERP PERMIT MODIFICATION BEFORE |
| | START OF CONSTRUCTION. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | 561-351-0510 (M) |
| | [email protected] |
| | |
| |