Plan Review Notes
Plan Review Notes For Project Z22040021
Project Number Z22040021
Review Stop STORM
Sequence Number 1
Notes
Date Text
2022-05-12 13:02:26THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. INDICATE IF THERE IS AN OUTFALL PIPE FOR THE
 EXISTING DRAINAGE SYSTEM.
  
 2. CONFIRM THE EXISTING EXFILTRATION SYSTEM IS
 FUNCTIONING AS DESIGNED. PRB'S MAY BE REQUIRED FOR
 CONNECTIONS TO EXFILTRATION PIPE.
  
 3. PROVIDE ELEVATION INFORMATION OF EXISTING DRAINAGE
 AND SANITARY SEWER STRUCTURES (RIM/GRATE ELEVATIONS,
 INVERTS, BOTTOM ELEVATION, ETC.). LABEL VERTICAL DATUM
 AND PROVIDE CONVERSION EQUATION TO NGVD1929.
  
 4. REMOVE CURBS CROSSING THE SIDEWALK IN THE RIGHT OF
 WAY.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP
 CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH
 THE ENGINEERING PERMIT SUBMITTAL.
  
 2. PROVIDE COPY OF SFWMD ERP PERMIT, IF APPLICABLE,
 BEFORE START OF CONSTRUCTION.
  
 3. PROVIDE EROSION CONTROL PLAN WITH THE ENGINEERING
 PERMIT SUBMITTAL.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved