Plan Review Notes
Plan Review Notes For Project Z22040014
Project Number Z22040014
Review Stop STORM
Sequence Number 2
Notes
Date Text
2022-07-18 16:28:46THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 6/15/2022 SUBMITTAL:
  
 1. [SATISFIED] DRAINAGE STRUCTURES, EXFILTRATION
 TRENCHES, ETC. ARE NOT TO CROSS THE PROPERTY LINE.
  
 2. [SATISFIED] THE CITY DOES NOT ALLOW THE USE OF
 BLEEDERS WITH EXFILTRATION TRENCH SYSTEMS.
  
 3. [PARTIALLY SATISFIED - VERTICAL DATUM REFERENCE
 (NAVD OR NGVD) NOT CONSISTENT ON THE ENGINEERING
 PLANS.]PLEASE PROVIDE CONVERSION EQUATION BETWEEN THE
 VERTICAL DATUM USED ON THE PLANS (NGVD1929) TO
 NAVD1988.
  
 4. [PARTIALLY SATISFIED - REVIEW BANYAN BLVD AS-BUILT
 DRAWINGS (OR DESIGN DRAWINGS) FOR STORM PIPE
 CONNECTIVITY.] SHOW CURRENT LAYOUT OF BANYAN BLVD.
  
 5. [NOT SATISFIED] PROVIDE FLOW ARROWS SHOWING
 DIRECTION OF SURFACE RUNOFF.
  
 6. [NOT SATISFIED] PROVIDE CROSS SECTIONS FOR THE
 DRIVEWAYS (EXTEND TO HIGH POINT) AND ON-STREET PARKING
 AREAS SHOWING HOW PAVEMENT WITH SLOPE. PROVIDE
 DIMENSIONS FROM EDGE OF TRAVEL LANE TO ALL CURBING,
 BREAK POINTS AND RIGHT OF WAY LINE.
  
 7. [NOT SATISFIED] PROVIDE CROSS SECTIONS AT EACH
 PROPERTY LINE FROM CENTERLINE OF ROAD TO FACE OF
 BUILDING. PROVIDE DIMENSIONS TO SURFACE FEATURES AND
 BREAK POINTS IN SURFACE SLOPES. LABEL THE RIGHT OF WAY
 WITH THE STREET NAME.
  
 8. [PARTIALLY SATISFIED - DEMO. PLANS DO NOT INDICATE
 WHETHER DRAINAGE SYSTEM ON CLEARWATER DEMOLITION PLAN
 INDICATES THE CURB INLETS ON CLEARWATER DRIVE ARE TO
 REMAIN BUT THE PGD PLAN CALLS FOR THEM TO BE REMOVED.
 EXISTING STRUCTURES SHOULD NOT REMAIN IF THE EXISTING
 PIPE CAN BE EXTENDED TO THE NEW STRUCTURES.
  
 9. [NOT SATISFIED] BUILDINGS OVER EXFILTRATION TRENCHES
 SHOULD HAVE SUFFICIENT VERTICAL CLEARANCE BELOW THE
 BUILDING FOR MAINTENANCE EQUIPMENT FOR THE EXFILTRATION
 TRENCH AND FOR REPLACING THE EXFILTRATION TRENCH IN THE
 FUTURE WHEN IT NO LONGER IS FUNCTIONING AS INTENDED.
  
 10. [SATISFIED] STREETS SHALL BE PROPERLY SHOWN ON THE
 PLAN VIEWS.
  
 NEW COMMENTS:
  
 11. PROVIDE WRITTEN RESPONSE TO THESE COMMENTS.
  
 12. PROVIDE EXFILTRATION TRENCH DETAIL.
  
 13. PROVIDE CONTROL STRUCTURE DETAIL.
  
 14. IT APPEARS A COLUMN IS PROPOSED OVER EXISTING STORM
 PIPE APPROXIMATELY 33 FEET NORTH OF MATCHLINE C-07 AND
 16 FEET WEST OF THE EAST PROPERTY LINE ON SHEET C-06.
  
 15. SHEETS COVER, C-12 AND C-13 INDICATE THE VERTICAL
 DATUM REFERENCE IS NAVD1988. SHEETS C-06 THROUGH C-09
 INDICATE THE VERTICAL DATUM REFERENCE IS NGVD1929.
 SHEETS C-01 AND C-02 NEED TO LIST THE VERTTICAL DATUM
 REFERENCE AND CONVERSION EQUATION. THE COVER NEEDS THE
 CONVERSION EQUATION.
  
 16. WATER QUALITY TREATMENT AND PEAK FLOW ATTENUATION
 WILL BE NEEDED FOR THE ADDITIONAL IMPERVIOUS AREA IN
 THE RIGHT OF WAY.
  
 17. SEPARATE PLAN AND PROFILE SHEETS FOR CLEARWATER
 DRIVE WILL BE NEEDED FOR THE ENGINEERING PERMIT
 SUBMITTAL. A BASELINE ON CLEARWATER DRIVE WILL NEED TO
 BE ESTABLISHED FOR THE ENGINEERING PERMIT SUBMITTAL.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved